Publication of a Prospectus and Project Update

25th Sep 2026 13:39

RNS Number : 4082W
Bazalgette Finance PLC
25 September 2026
 

25 September 2026

Bazalgette Finance plc

 

PUBLICATION OF PROSPECTUS AND PROJECT UPDATE

The following prospectus has been approved by the Financial Conduct Authority and is available for viewing:

A prospectus dated 25 September 2026 (the "Prospectus") relating to the update of the £10,000,000,000 multicurrency programme for the issuance of bonds, under which Bazalgette Finance plc (the "Company") is the programme issuer.

A copy of the Prospectus has also been submitted to the National Storage Mechanism and is available for inspection at:

http://www.rns-pdf.londonstockexchange.com/rns/4082W_1-2026-9-25.pdf

In connection with the publication of the Prospectus, the Company also provides the following update on progress by Bazalgette Tunnel Limited ("Tideway"), the operating company responsible for delivering the Thames Tideway Tunnel (the "TTT") project.

The TTT has been fully connected to the Thames Water sewer network since February 2025 and has operated at full capacity as part of the commissioning process since July 2025. In August 2026, Tideway achieved Handover, a significant milestone marking the commencement of the System Acceptance phase and the transfer to Thames Water of responsibility for operating the TTT.

As previously disclosed, prolonged periods of dry weather and reduced inflows following the connection of the tunnel to the Thames Water network in February 2025 constrained Tideway's ability to complete certain required commissioning and testing activities. As a result, System Acceptance is expected to occur between February 2028 and August 2028, depending on when the applicable acceptance criteria are satisfied.

Tideway and Ofwat recognise that the revised expected timing of System Acceptance extends beyond the current Planned System Acceptance Date ("PSAD") of 31 August 2027. Ofwat has confirmed that it does not intend to impose financial penalties in respect of the weather-related delay. Discussions are ongoing regarding potential amendments to the regulatory framework to reflect the revised timetable, including an amendment to the PSAD and an increase to funding.

The Company's revised cost estimate as at 31 August 2026 remains £4.7bn.

Separately, as at 15 August 2026, the TTT had diverted more than 21 million cubic metres of sewage from the River Thames.

 

 

For further information, please contact:

 

Investor relations: [email protected]

Media enquiries: [email protected]

Taylor Geall

07813 450 682

Bazalgette Finance plc Part Level 7, Riverside House, 2A Southwark Bridge Road, London, SE1 9HA

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact [email protected] or visit www.rns.com.RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
PDIFLFVFADIEFIR
FTSE 100 Latest
Value10,717.02
Change21.77