7th Jan 2015 07:00
7 January 2015
Update on Progress at Tschudi Copper Mine
Grid Power Connected and Plant Ahead of Schedule
Weatherly International Plc (AIM: WTI) today announces a trading update on progress at its Tschudi copper mining project in Namibia.
Chairman, John Bryant, said, "Tschudi is on track to commence production in the second quarter of this year. I must congratulate our UK and Namibia teams on the progress they have made." The highlights are:
· Mining
Mining at Tschudi has been underway since July 2014 and ore continues to be stockpiled in readiness for the crushing plant to come on line. Full details will be contained in the quarterly production report.
· Crushing/Agglomeration/Stacking
On Friday 19 December, 2,000 tonnes of ore were run through the crushing and agglomeration plant as a pre-commissioning test with the plant achieving the desired throughput rates. A second 2,500 tonnes were crushed and agglomerated on Friday 2nd January, this time focussing on achieving the required agglomerate quality under full throughput. This has resulted in some minor modifications that are expected to be completed by the end of the week.
Leach Panels One and Two are close to completion and will be ready to receive ore once the crushing plant is in operation. The raw water and raffinate ponds have been completed and were filled with water over the Christmas break. Work on the pregnant leach solution pond is ongoing and is expected to be completed next week.
· Acid
On Wednesday 17 December, the first acid road tankers arrived from the Rössing Uranium Mine and began unloading into the newly commissioned acid storage tank, with approximately 650 tonnes delivered.
Originally, acid was to be sourced from the adjacent Tsumeb smelter, but construction of the smelter's acid plant has been delayed. As an interim move, Weatherly has signed a one year contract with Rössing Uranium to import acid through the port of Walvis Bay. Imported prices are currently lower than those offered by the smelter and, as a result, the contract (with Dundee Precious Metals) is being renegotiated.
· Electric Power
On Thursday 14 December, Nampower (the Namibian power utility) signed off on the High Voltage installation, enabling the site to switch to the main grid supply when read and, replacing the temporary generating sets that have been used for much of the commissioning work.
· Workforce and Plant Commissioning
Recruitment of the Weatherly workforce is complete and operators are currently undergoing training under the supervision of the specialist commissioning group, PPM Global.
The commissioning plan has been agreed, with crushed/agglomerated ore expected to be loaded onto the first panel early in the month, and for irrigation with acid to begin a week later, allowing the agglomerated ore sufficient time for curing.
Commissioning of the SX-EW will commence as soon as there are sufficient stocks of pregnant leach solution available at the required grade.
· Finance
The Company made its final payment under Tranche A of its loan facility with Orion in December 2014. Tranche A related to the original $7 million loaned by Louis Dreyfus to restart the underground mines. The discharge of the loan means the underground mines are now debt free going into 2015.
At the end of the year (2014), the Company had drawn down US$73 million of its US$80 million (Tranche B) facility with Orion. The loan is expected to be fully drawn by the second quarter of 2015 with the first quarterly repayment (expected to be approximately US$4.5 million) scheduled for November 30, 2015.
Chief Executive, Rod Webster, said:
"Progress on the Tschudi project has been impressive with large sections of the plant commissioned in advance of the Christmas break. We have made excellent progress with mining, our crushing and processing plant, acid delivery and the connection to grid electricity. We have completed the recruitment of our workforce and the plan for commissioning our plant has been agreed. We are ahead of schedule and looking forward to being in production in the second quarter of 2015."
For further information please contact:
Weatherly International Plc +44 (0) 20 7917 2989
Rod Webster, CEOKevin Ellis, CFO & Company Secretary
RFC Ambrian Limited (Nominated Adviser & Broker) +44 (0) 20 3440 6800
Samantha Harrison
Finncap (Joint Broker) +44(0)207 220 0514
Joanna Weaving
Blytheweigh (Financial PR/IR) +44(0)2071383204
Tim Blythe Halimah Hussain
About WeatherlyWeatherly is an AIM listed copper mining company operating in Namibia in southern Africa. Its principal assets are two underground copper mines, Otjihase and Matchless, and a larger open pit development called Tschudi scheduled to come on stream in the second quarter of calendar year 2015.
These assets will enable Weatherly to achieve its medium term goal of establishing a mining business capable of sustaining approximately 25,000 tonnes per annum of copper production.
The Company also has a 25% stake in the AIM listed company, China Africa Resources Plc (CAF), which is developing a lead/zinc mine called Berg Aukas also in Namibia.
Related Shares:
Weatherly International Plc