Puka-1 expected to spud in two weeks
Kea Petroleum Plc wishes to advise that its drilling programme in the Taranaki basin of New Zealand is delayed due to extreme weather conditions in the region.
Worst affected is the programme to drill Mauku which as previously advised requires challenging access and site preparations. The intention was to begin the drilling of Mauku with a shallow drilling rig but Kea may now proceed to drill the entire of the hole with the bigger rig later.
Further, Douglas 1 is now being considered to be drilled before Mauku as the site is already prepared.
Puka 1 is now expected to spud later next week.
For further information please contact:
Kea Petroleum plc Tel: +44 (0)20 7340 9970
Ian Gowrie-Smith, Executive Chairman
David Lees, Executive Director
RBC Capital Markets Tel: +44 (0)20 7653 4000
Matthew Coakes / Daniel Conti
Buchanan Tel: +44 (0)20 7466 5000
Tim Anderson /Isabel Podda
Related Shares:
KEA.L