Selene Gas Project Update

15th Apr 2025 07:00

RNS Number : 9876E
Deltic Energy PLC
15 April 2025
 

Prior to publication, the information contained within this announcement was deemed by the Company to constitute inside information as stipulated under the UK Market Abuse Regulation. With the publication of this announcement, this information is now considered to be in the public domain.

 

Deltic Energy Plc / Index: AIM / Epic: DELT / Sector: Natural Resources

 

15 April 2025

 

 

Deltic Energy Plc ("Deltic" or "the Company")

Selene Gas Project Update

 

Deltic Energy Plc, the AIM quoted natural resources investing company, is pleased to provide the following operational and commercial update in relation to the Selene Gas Project in the UK Southern North Sea:

 

Highlights

 

· Deltic now estimates Gross 2C Contingent Resources of 174 BCF at Selene, a 33% increase on earlier estimates

· Analysis of core samples from well 48/8b-3Z is now substantially complete

· Porosity and permeability characteristics improved over previous assumptions

· Reservoir modelling indicates enhanced production potential from key B-sand interval 

· Updated post-tax NPV10 of USD$83M net to Deltic at 80 pence per therm gas price and USD$114M at 100 pence per therm gas price

 

Selene Gas Project - Licence P2437

 

Deltic has a 25% non-operated interest in the Shell-operated Selene gas discovery in the Southern North Sea ("SNS").

 

Following the successful drilling of the well in 2024, the Joint Venture ("JV") partners unanimously voted to move into the second term of the licence and committed to the various engineering, commercial and regulatory workflows required to support a Field Development Plan ("FDP") and a future Final Investment Decision ("FID") scheduled for early 2027.

 

Reservoir Properties

 

The licence Operator, Shell UK Ltd, has provided porosity and permeability measurements on 176 core plugs taken from drill core samples over the Leman B-Sand, which is the key producing interval within the much thicker Leman Sandstone package. 

 

The core analysis indicates significantly better porosity and permeability than previously assumed in Deltic's P50 volumetric estimates and reservoir modelling. A comparison of the updated B-sand porosity assumptions based on the core analysis and the previously utilised assumptions are summarised in the table below:

 

 

Reservoir Characteristic

Units

Poro-Perm Assumptions

Time post-well completion

% Improvement

1 Month

6 Months

B-Sand Porosity

Low

%

11

13

18

Mid

12

14.5

21

High

13

16

23

Average

Permeability

Mid

Case

mD1

1.6

2.5

56

1 Klinkenberg corrected for Net Overburden Pressure

 

The improved view of porosity has been incorporated into Deltic's static subsurface model and our estimates of gas-initially-in-place (or "GIIP") for the Selene structure.

 

Reservoir Modelling Update

 

Incorporating the new porosity and permeability data into Deltic's dynamic reservoir model has resulted in improved overall recovery factors, higher initial flow rates, extended plateau production periods and increased estimates of gas recovered over a 20-year production life. A comparison of our 6 month post-well view with the previous reservoir modelling is set out below:

 

Mid-Case

Reservoir Model & Outputs1

Units

Assumptions

Time post-well completion

% Improvement

1 Month

6 Months

2 Well Development

 

Gas exported via Barque PB

Initial Production Rate

Mmscf/day

50

70

40

Production Plateau

Months

8

18

125

Technically Recoverable Gas

BCF

130

176.7

36

Implied P50 Recovery Factor

%

50

57

12

1 Field production metrics are reported on a Gross basis, reflects mid-case (ie P50) reservoir assumptions

 

Gas Quality Analysis

 

Analysis of the gas samples collected from the 48/8b-3Z well have proven the presence of a very dry, methane dominated natural gas with nominal concentrations of contaminants including CO2 and N2 and our expectation is that gas produced from Selene will require minimal processing to reach National Grid entry specifications.

 

Updated Volumetric Estimate

 

The core analysis data has allowed Deltic to refine and update its volumetric estimates for the Selene Gas Project utilising the recently delivered porosity data from the core samples and updated recovery factors from the reservoir modelling. 

 

Contingent Resources1

[Development Pending]

%

Improvement2

Units

BCF

Gross

BCF

Net to Deltic

1C

128

32

35

2C

174

44

33

3C

233

58

32

1 Deltic's in-house estimates of Contingent Resources

2 % Improvement compared to EUR volumes announced via RNS on 31 October 2024

 

Given the commerciality of the project, maturity of the technical analysis and ongoing pre-development workflows it was considered appropriate to move from using Estimated Ultimate Recovery (or 'EUR') to Contingent Resources - Development Pending to describe the status of the Selene project.

 

Updated Economic Model & Project Valuation

 

Given the material uplift in recoverable gas volumes, the economic model for Selene has been updated from that previously announced in the Company's announcement released on 11 March 2025. Deltic's base case development assumptions remain unchanged and incorporate a two well development with a new normally unmanned installation tied back to existing production infrastructure on the Barque field via a new c. 20km subsea pipeline.

 

This model reflects the revised volumetrics and production profiles and has been run at a 80 pence per therm gas price reflecting recent average National Balancing Point ('NBP') and a 100 pence per therm gas price which more closely reflects the average NBP gas price over the last six months.

 

Assumptions

Units

Value*

Deltic Working Interest

%

25

Gross 2C Contingent Resources

BCF

174

Initial Field Production Rate

MMscf/day

70

Gas Price

pence/therm

80 & 100

First Gas

Year

2029

Cost per BOE

USD$

$10 CAPEX

 &

 $15 OPEX

Fiscal Regime

As per Budget announced

30 October 2024

 

Economic Evaluation

Units

Value @ 80 p/therm

Value @ 100 p/therm

Gross Gas Sales (cumulative)

USD$

$2.1 billion

$2.7 billion

NPV10 (pre-tax, gross)

USD$

$430 million

$626 million

NPV10 (post-tax, net to Deltic)

USD$

$83 million

$114 million

Payback Period

Years

In year 2

of production

In year 2 of

production

Internal Rate of Return

%

42%

51%

 

 

Andrew Nunn, Deltic CEO, commented:

 

"The six month post discovery checkpoint is always a key stage gate on the path from a gas discovery to a gas development project, and as the technical work gathers momentum we narrow the inherent uncertainties of a new find and get greater clarity on the discovery and its potential. The integration of the core data into the volumetric and economic analysis has led to a significant refinement and improvement in Deltic's understanding of the Selene asset which continues to impress. This updated understanding will be critical as the JV moves forward into project scoping and early project design workflows. The circa 45% increase in the NPV10 of Selene net to Deltic is particularly pleasing, especially within the context of the current market cap of the Company.

Recent global events have reinforced the case for maximising the benefits from the United Kingdom's domestic resources. With continued government support for the development of new fields on existing licences there appears to have been a realisation that, while we continue to consume hydrocarbons as a society, then the focus should be on maximising the proportion of 'good barrels' in the energy mix. These barrels are, or will be, produced locally and, in the case of newer developments, from facilities which are specifically designed with a net zero target in mind. Hydrocarbons produced in the UK have a lower emissions footprint than imported oil and gas and are operated under the strictest environmental regulations. They also support high quality UK jobs and provide important tax revenues to the Exchequer. 

We continue to explore various avenues as we work to secure the funding required to maintain our interest in the Selene project as the JV works toward a Final Investment Decision in early 2027. We believe that it has never been more important for the UK to develop and maximise the benefit of its own resources, like Selene, and thereby maximising the proportion of 'good barrels' in the mix as we become increasingly dependent on imported oil and gas."

 

**ENDS**

 

For further information please contact the following:

 

 

Deltic Energy Plc

 

Tel: +44 (0) 20 7887 2630 

Andrew Nunn / Sarah McLeod

 

Allenby Capital Limited (Nominated Adviser)

Tel: +44 (0) 20 3328 5656

David Hart / Alex Brearley (Corporate Finance)

 

Canaccord Genuity Limited

 

Tel: +44 (0) 20 7523 8000

Adam James / Charlie Hammond

 

 

Vigo Consulting (IR Adviser)

 

Tel: +44 (0) 20 7390 0230

Patrick d'Ancona / Finlay Thomson / Kendall Hill 

 

Qualified Person

Andrew Nunn, a Chartered Geologist and Chief Executive Officer of Deltic, is a "Qualified Person" in accordance with the Guidance Note for Mining, Oil and Gas Companies, June 2009 as updated 21 July 2019, of the London Stock Exchange. Andrew has reviewed and approved the information contained within this announcement.

 

Standard

Estimates of resources have been prepared in accordance with the PRMS as the standard for classification and reporting.

 

Glossary of Technical Terms

BCF:

Billion Cubic Feet.

 

BOE

barrels of oil equivalent. Gas is converted at a conversion rate of 6,000 standard cubic feet of gas per BOE.

 

Contingent Resources - Development Pending

Discovered, potentially recoverable resources that are not yet considered commercially viable due to contingencies, but where development is actively being pursued and is expected within a reasonable timeframe with a high chance of success.

 

Estimated Ultimate Recovery ('EUR'):

Estimated Ultimate Recovery is defined as those quantities of petroleum which are estimated, on a given date, to be potentially recoverable from an accumulation, plus those quantities already produced therefrom.

 

GIIP

the estimated total volume of natural gas contained within a reservoir before any extraction or production takes place.

 

MMscf:

million standard cubic feet.

 

NPV10:

 

estimated net present value using a discount rate of 10%.

 

PRMS:

the June 2018 Society of Petroleum Engineers ("SPE") Petroleum Resources Management System.

 

P50 resource:

reflects a volume estimate that, assuming the accumulation is developed, there is a 50% probability that the quantities actually recovered will equal or exceed the estimate. This is therefore a median or best case estimate of resource.

 

Therm:

the energy equivalent of approximately a hundred cubic feet of natural gas.

 

 

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact [email protected] or visit www.rns.com.RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 