Become a Member
  • Track your favourite stocks
  • Create & monitor portfolios
  • Daily portfolio value
Sign Up
Quickpicks
Add shares to your
quickpicks to
display them here!

Second Quarter and First Half Production Report

23rd Apr 2009 07:00

RNS Number : 0070R
Lonmin PLC
23 April 2009
 



 

Lonmin Plc

Second Quarter and First Half 2009 

Production Report

Lonmin Plc, ("Lonmin" or "the company"), the world's third largest Platinum producer, today announces its production report for the three months and six months to 31 March 2009 (unaudited). 

Q209 Production

Total tonnes mined for the second quarter of the 2009 financial year were 2.7 million, an 8decline year-on-year. This was due to the planned closures of our Marikana opencast operations and our Baobab shaft at Limpopo 

Our underground Marikana mining operations produced 2.6 million tonnes during the second quarter of the 2009 financial year7increase from the same period last year, when production was impacted by the Eskom power outage in January 2008. The increase in production from the prior year period was supported by an improved performance from our conventional operationswhich was achieved despite the disruption caused by the significant restructuring programme being carried out during the period. Production at Saffy and Hossy shafts continued to ramp up, whilst underground ore reserve development at Marikana continued to improve. 

Our safety performance remained strong, with LTIFR at the end of 31 March 2009 improving 6% from the 2008 financial year. However, we regrettably suffered two fatalities during the quarter

Total tonnes milled in the quarter increased 2year-on-year to 2.8 million tonnes, reflecting increased production from Marikana and Pandora underground mining operations, and exceeded total tonnes mined, due to the milling of some opencast stock piles in the period. The remainder of these opencast stock piles and the further opencast tonnes from Pandora will be processed during the second half of the 2009 financial year

The concentrators produced 164,909 saleable ounces of Platinum in concentrate for the quarter, a 5% increase from the second quarter in the 2008 financial year, reflecting increased production from underground Marikana operations and Pandora. Underground and overall concentrator recoveries improved to 81.4% and 80.6% respectively from the first quarter of the 2009 financial year, when underground and overall recoveries were 80.2% and 79.4% respectively

Overall milled head grade was up 2% year-on-year to 4.68 grammes per tonne (5PGE+Au), whilst underground milled head grade increased marginally to 4.69 grammes per tonne (5PGE+Au)Encouragingly, underground head grade improved 5% from the first quarter of the 2009 financial year, reflecting in part the impact of management actions taken to tackle the unplanned dilution identified in the first quarter of 2009.

Refined production for the second quarter was 185,284 ounces of Platinum and 362,326 ounces of total PGMs, an increase of 45% and 41% respectively from the second quarter of the 2008 financial yearMetal sales during the second quarter of the 2009 financial year were 185,651 ounces of Platinum and 355,069 ounces of PGMs, increases of 30% and 26% respectively from the prior year periodThis growth in refined production and sales partly reflected the improved contribution from our Marikana underground operationsFurthermore, the Process Division delivered an excellent performance during the second quarter and, ahead of our expectations, it processed the vast majority of the inventory built up during the planned re-build of the Number One furnace which tapped matte on 13 January 2009Refined production and sales in the prior year period were more significantly impacted by a planned inspection and repair of the Number One furnace, following the Eskom power outage, which caused a build up of metal in process at that time.

 

 

 

 

 

H109 Production

Total tonnes mined during the first half of the 2009 financial year were 5.8 million tonnes, a 3% decline from 2008. This was due to the planned cessation of production at our Marikana opencast operations at the end of the first quarter of the 2009 financial year and production at our Baobab shaft at Limpopo being impacted by the winding down of the operation towards care and maintenance, as well as a 21 day wage related strike at Limpopo in the first quarter of the 2009 financial year. 

In the first six months of the 2009 financial year we mined a total of 5.3 million tonnes of ore from our core underground Marikana operationsan increase of 7% on the same period last year. This was due to an improved performance from our conventional sections with production rising in both the first and second quarters of the 2009 financial year from the same periods in 2008. Production from Saffy and Hossy shafts also increased during the first half of the 2009 financial year, from 2008

The concentrators produced a total of 338,142 saleable ounces of Platinum in concentrate in the first half of the 2009 financial year, a 3% year-on-year decline, mainly as a result of the planned operational changes at our Marikana opencast and Limpopo operations, as mentioned aboveOverall concentrator recoveries improved during the first half of the 2009 financial year to 80.0% from 78.8% in the first half of 2008, partly due to reduced levels of low grade opencast stock piles being processed during the first half of the 2009 financial year compared to the prior year period. However, during the first half of the 2009 financial year, underground recoveries fell to 80.8%, from 81.5% in the first half of the 2008 financial yearpartly as a result of undertaking extensive maintenance on some of our Marikana concentrators in the first quarter of the 2009 financial year

Overall milled head grade improved 2year-on-year to 4.58 grammes per tonne (5PGE+Au), mainly due to higher levels of low grade opencast stock piles processed during the first half of the 2008 financial year which had an adverse impact on grade at that timeUnderground milled head grade was 3% lower year-on-year at 4.57 grammes per tonne (5PGE+Au) as a result of an increased percentage of development ore coming from Hossy and Saffy and unplanned dilution on the UG2 reef horizon, as well as a lack of flexibility in face availability on the Merensky reef horizonwhere some localised lower grade areas were encountered, particularly during the first quarter. However, management actions initiated to tackle the latter two issues have already started to have a positive impact, as evidenced by the sequential improvement in underground head grade delivered in the second quarter of the 2009 financial year

Total refined production for the first half of the 2009 financial year was 318,219 ounces of Platinum and 606,145 of total PGMs, both up 13% from the same period in 2008, partly reflecting the improvement from our core Marikana underground operations during the first half of the 2009 financial yearIn addition, refined production during the first half of the 2008 financial year was adversely impacted by a build up of metal in process, partly due to the planned inspection and repair of the Number One furnace, following the Eskom power outage in January 2008.

During the first half of the 2009 financial year, our Process Division delivered an excellent performance and processed the vast majority of the inventory built up during the planned re-build of the Number One furnace in the first quarter. Final metal sales for the first half of the 2009 financial year were 311,853 ounces of Platinum and 583,873 ounces of total PGMs, up 8% and 5% respectively on the same period in 2008.

 

 

 

 

 

2009 Sales Guidance

We maintain our sales guidance for the 2009 financial year of around 700,000 Platinum ounces.

Platinum sales in the first half of the 2009 financial year were around 45% of the full year Platinum sales target for our core Marikana operations, which we first published in November 2008, and this was ahead of our initial expectations for the period. The key driver of this was the performance of the Process Division, where metal in process inventory was drawn down faster than had been expected following the Number One furnace re-build during the first quarter of the 2009 financial year.

For the second half of the 2009 financial year, management will be focused on minimising the possible disruption resulting from the execution of our significant restructuring programme, particularly as crews are redeployed around the Marikana property, and the closure of a small uneconomic decline shaft and a further five uneconomic half levels at Marikana as part of this restructuring programme. In addition, the continuing ramp up of Saffy shaft is a key area of focus. It is anticipated that any impact of these factors on production and sales will be compensated for by the normalising of metal in process inventory from the Process Division. 

Update on restructuring 

Further to our announcement on 24 February 2009, we have now essentially completed a major restructuring exercise at our Marikana and Limpopo operations. Further details, including expected annual cost savings and one-off costs, will be disclosed at our Interim Results on 11 May 2009. 

Debt re-financing 

We have completed a $575m debt re-financing package, comprising a $250m revolving credit facility and $150m amortising term loan both maturing in November 2012 in the UK and a $175m revolving credit facility in South Africa, maturing in November 2010. This re-financing significantly lengthens the tenure of the company's banking facilities.

ENQUIRIES: 

Investors / Analysts: 

Rob Gurner +44 (0) 207 201 6050

Head of Investor Relations

Media:

 

Cardew Group +44 (0) 207 930 0777

Anthony Cardew / Rupert Pittman

Financial Dynamics +27 (0) 21 487 9000

Dani Cohen / Ravin Maharaj

 

 
 
 
 
 
3 months to 31st March
3 months to 31st March
 
6 months
 to 31st
March
6 months to 31st March
 
 
 
 
 
2009
2008
 
2009
2008
Tonnes mined
Marikana
Underground - conventional
000
2,184
2,174
 
4,487
4,349
 
Underground - M&A1
000
400
252
 
771
552
 
Underground - total
000
2,584
2,426
 
5,258
4,901
 
Opencast
000
13
255
 
229
624
 
Total
000
2,598
2,681
 
5,488
5,525
Limpopo
Underground
000
0
126
 
87
264
 
Opencast
000
0
0
 
0
0
 
Total
000
0
126
 
87
264
Pandora attributable2
Underground
000
37
34
 
71
68
Opencast
000
41
54
 
110
101
 
Total
000
78
88
 
181
169
Lonmin Platinum
Underground
000
2,621
2,586
 
5,417
5,233
Opencast
000
55
309
 
339
725
ERROR
Total
000
2,676
2,895
 
5,756
5,958
 
 
 
 
 
 
 
 
 
 
Tonnes milled3
Marikana
Underground
000
2,462
2,335
 
5,124
4,844
 
Opencast
000
78
157
 
194
719
 
Total
000
2,540
2,491
 
5,319
5,563
Limpopo
Underground
000
0
78
 
92
207
 
Opencast
000
0
0
 
0
0
 
Total
000
0
78
 
92
207
Pandora4
Underground
000
88
78
 
168
159
 
Opencast
000
126
64
 
251
192
 
Total
000
214
142
 
419
351
Ore purchases5
Underground
000
0
0
 
0
0
 
Opencast
000
0
0
 
0
30
 
Total
000
0
0
 
0
30
Lonmin Platinum
Underground
000
2,550
2,491
 
5,384
5,210
Head grade6
g/t
4.69
4.68
 
4.57
4.72
Recovery rate7
%
81.4%
81.5%
 
80.8%
81.5%
Opencast
000
205
221
 
445
941
 
Head grade6
g/t
4.61
3.62
 
4.68
3.18
 
Recovery rate7
%
71.3%
54.6%
 
70.6%
56.8%
 
Total
000
2,754
2,711
 
5,829
6,151
 
 
 
Head grade6
g/t
4.68
4.59
 
4.58
4.48
 
 
 
Recovery rate7
%
80.6%
79.8%
 
80.0%
78.8%
 
 
 
 
 
3 months to 31st March
3 months to 31st March
 
6 months to 31st March
6 months to 31st March
 
 
 
 
 
2009
2008
 
2009
2008
Metals in concentrate8
Marikana
Platinum
oz
151,168
147,414
 
308,617
319,543
 
Palladium
oz
70,285
67,814
 
143,110
146,474
 
Gold
oz
3,444
3,851
 
7,057
8,522
 
Rhodium
oz
21,191
20,092
 
43,000
43,328
 
Ruthenium
oz
32,617
30,828
 
66,454
66,680
 
Iridium
oz
7,110
6,573
 
14,520
13,945
 
Total PGMs
oz
285,815
276,572
 
582,759
598,492
 
Nickel9
MT
642
685
 
1,321
1,493
 
Copper9
MT
405
413
 
825
906
Limpopo
Platinum
oz
0
3,062
 
3,770
8,589
 
Palladium
oz
0
2,618
 
3,331
6,493
 
Gold
oz
0
213
 
243
620
 
Rhodium
oz
0
357
 
487
894
 
Ruthenium
oz
0
498
 
688
1,302
 
Iridium
oz
0
116
 
159
274
 
Total PGMs
oz
0
6,864
 
8,679
18,172
 
Nickel9
MT
0
67
 
76
175
 
Copper9
MT
0
46
 
54
120
Pandora4
Platinum
oz
13,742
6,698
 
25,754
17,825
 
Palladium
oz
6,194
3,075
 
11,601
8,148
 
Gold
oz
110
50
 
202
133
 
Rhodium
oz
1,909
962
 
3,566
2,478
 
Ruthenium
oz
2,789
1,413
 
5,216
3,676
 
Iridium
oz
515
239
 
971
615
 
Total PGMs
oz
25,259
12,436
 
47,310
32,875
 
Nickel9
MT
13
10
 
25
25
 
Copper9
MT
8
4
 
15
11
Ore
Platinum
oz
0
104
 
0
937
purchases5
Palladium
oz
0
(141)
 
0
793
 
Gold
oz
0
(13)
 
0
74
 
Rhodium
oz
0
25
 
0
83
 
Ruthenium
oz
0
57
 
0
107
 
Iridium
oz
0
10
 
0
25
 
Total PGMs
oz
0
42
 
0
2,019
 
Nickel9
MT
0
4
 
0
16
 
Copper9
MT
0
2
 
0
11
Lonmin Platinum
Platinum
oz
164,909
157,277
 
338,142
346,894
Palladium
oz
76,479
73,366
 
158,042
161,908
 
Gold
oz
3,554
4,101
 
7,503
9,349
 
Rhodium
oz
23,100
21,436
 
47,053
46,783
 
Ruthenium
oz
35,406
32,796
 
72,358
71,765
 
Iridium
oz
7,625
6,938
 
15,649
14,859
 
Total PGMs
oz
311,074
295,914
 
638,748
651,558
 
Nickel9
MT
655
766
 
1,422
1,709
 
Copper9
MT
412
465
 
894
1,048
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
3 months to 31st March
3 months to 31st March
 
6 months to 31st March
6 months to 31st March
 
 
 
 
 
2009
2008
 
2009
2008
Metallurgy
Lonmin refined metal production
Platinum
oz
184,969
128,124
 
317,904
282,650
 
 
Palladium
oz
86,637
65,956
 
147,393
128,140
 
 
Gold
oz
5,151
6,042
 
8,647
9,563
 
 
Rhodium
oz
25,939
21,179
 
44,688
42,437
 
 
Ruthenium
oz
47,614
31,232
 
72,952
62,763
 
 
Iridium
oz
9,935
5,284
 
12,479
10,577
 
 
Total PGMs
oz
360,245
257,816
 
604,063
536,128
 
 
Toll refined metal production
Platinum
oz
315
0
 
315
0
 
 
Palladium
oz
0
0
 
0
0
 
 
Gold
oz
0
0
 
0
0
 
 
Rhodium
oz
573
0
 
573
0
 
 
Ruthenium
oz
1,009
0
 
1,009
0
 
 
Iridium
oz
184
0
 
184
0
 
 
Total PGMs
oz
2,081
0
 
2,081
0
 
 
Total refined PGMs
Platinum
oz
185,284
128,124
 
318,219
282,650
 
 
Palladium
oz
86,637
65,956
 
147,393
128,140
 
 
Gold
oz
5,151
6,042
 
8,647
9,563
 
 
Rhodium
oz
26,512
21,179
 
45,261
42,437
 
 
Ruthenium
oz
48,623
31,232
 
73,961
62,763
 
 
Iridium
oz
10,119
5,284
 
12,663
10,577
 
 
Total PGMs
oz
362,326
257,816
 
606,145
536,128
 
 
Base
Nickel10
MT
869
508
 
1,632
1,323
 
 
metals
Copper10
MT
579
286
 
1,079
795
 
 
 
 
 
 
 
 
 
 
Sales
Refined metal sales
Platinum
oz
187,250
140,875
 
313,671
284,731
Palladium
oz
92,439
70,662
 
147,184
133,991
Gold
oz
5,940
4,916
 
9,318
9,208
Rhodium
oz
21,636
21,818
 
38,739
43,537
Ruthenium
oz
41,833
33,374
 
67,501
65,941
Iridium
oz
9,392
6,088
 
12,500
11,720
Total PGMs
oz
358,490
277,732
 
588,913
549,127
Concentrate and other11
Platinum
oz
(1,600)
2,478
 
(1,818)
4,233
Palladium
oz
(1,822)
1,095
 
(3,222)
1,833
Gold
oz
0
55
 
0
97
Rhodium
oz
0
534
 
0
758
Ruthenium
oz
0
628
 
0
990
Iridium
oz
0
137
 
0
240
Total PGMs
oz
(3,421)
4,926
 
(5,039)
8,150
Lonmin Platinum
Platinum
oz
185,651
143,352
 
311,853
288,963
Palladium
oz
90,617
71,756
 
143,962
135,823
 
Gold
oz
5,940
4,971
 
9,318
9,305
 
Rhodium
oz
21,636
22,352
 
38,739
44,295
 
Ruthenium
oz
41,833
34,002
 
67,501
66,931
 
Iridium
oz
9,392
6,225
 
12,500
11,960
 
Total PGMs
oz
355,069
282,658
 
583,873
557,277
 
Nickel10
MT
693
413
 
1,368
1,216
 
Copper10
MT
503
376
 
907
805
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
3 months to 31st March
3 months to 31st March
 
6 months to 31st March

6 months to 31stMarch

 
 
 
 
 
2009
2008
 
2009
2008
Prices
Average
Platinum
$/oz
991
1,734
 
947
1,578
 
Palladium
$/oz
195
431
 
192
396
 
Gold
$/oz
901
908
 
871
853
 
Rhodium
$/oz
1,099
7,853
 
1,650
7,121
 
Ruthenium
$/oz
47
407
 
124
446
 
Iridium
$/oz
384
428
 
393
424
 
Basket price of PGMs12
$/oz
666
1,684
 
699
1,558
 
Nickel10
$/MT
16,285
23,374
 
15,721
27,235
 
Copper10
$/MT
6,953
8,042
 
6,062
6,936
 
 
 
 
 
 
 
 
 
 
Exchange Rates
Average rate for period
 
R/$
 
9.90
 
7.52
 
 
9.91
 
7.14
 
Closing rate
 
R/$
9.49
8.08
 
9.49
8.08
 
 
 
 
 
 
 
 
 
 
 
Notes:
 
 
 
 
 
1
M&A comprises ore produced by our fully mechanised shafts and from Saffy shaft, which is being transitioned to hybrid mining.
 
 
 
 
 
 
 
2
JV attributable tonnes mined includes Lonmin's share (42.5%) of the total tonnes mined on the Pandora joint venture.
 
 
 
 
 
 
 
3
Tonnes milled excludes slag milling.
 
 
 
 
 
 
 
 
 
4
Lonmin purchases 100% of the ore produced by the Pandora joint venture for onward processing which is included in downstream operating statistics.
 
 
 
 
 
 
 
5
Relates to the tonnes milled and derived metal in concentrate from third-party ore purchases.
 
 
 
 
 
 
 
6
Head Grade is the grammes per tonne (5PGE + Au) value contained in the tonnes milled and fed into the concentrator from the mines (excludes slag milled).
 
 
 
 
 
 
 
7
Recovery rate in the concentrators is the total content produced divided by the total content milled (excluding slag).
 
 
 
 
 
 
 
8
Metals in concentrate includes slag and have been calculated at industry standard downstream processing losses.
 
 
 
 
 
 
 
9
Corresponds to contained base metals in concentrate.
 
 
 
 
 
 
 
 
 
 
10
Nickel is produced and sold as nickel sulphate crystals or solution and the volumes shown correspond to contained metal. Copper is produced as refined product but typically at LME grade C.
 
 
 
 
 
 
 
11
Concentrate and other sales have been adjusted to a saleable ounces basis using standard industry recovery rates.
 
 
 
 
 
 
 
12
Basket price of PGMs is based on the revenue generated from the actual PGMs sold in the period.
 
 
 
 
 
 
 
This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCZGGZDKZMGLZM

Related Shares:

Lonmin
FTSE 100 Latest
Value8,684.56
Change50.81