30th Apr 2012 09:01
OILEX LTD
QUARTERLY REPORT TO SHAREHOLDERS
31 MARCH 2012
Highlights
Cambay PSC (45% Operator) onshore Gujarat, India
·; Milling operations on the Cambay-76H horizontal well were completed in April with all 8 stages now expected to flow back during well clean up and production testing.
·; An influx of fracture sand caused the milling assembly to packoff and the drill pipe to part downhole in April. Operations to retrieve the drill pipe are in progress and it is anticipated that on completion, production tubing will be run and the well will be flowed to surface for cleanup and production testing.
JPDA 06-103 PSC (10% Operator) offshore Timor Sea
·; The Bazartete Prospect has been confirmed by the JPDA 06-103 Joint Venture as the prospect to be tested by drilling the next exploration well.
·; Planning is underway to drill the Bazartete prospect.
Overview
Activity during the quarter was dominated by operations to control the Cambay-76H well and recovery of equipment that had been stuck downhole. The well has continued to flow gas and condensate to surface intermittently at high pressure and a mud system of a higher density has been installed. The intermittent flows of hydrocarbons and fracture stimulation fluids to surface observed during the quarter may be positive indicators of potentially good future reservoir performance.
The Cambay-76H well clean-up operations and production testing continue to be delayed due to the well control and equipment retrieval operations. However milling operations were completed during the quarter and after current retrieval operations are concluded, it is anticipated that production tubing will be installed and the well will be flowed back prior to performing a production test. The production test data obtained will be used to demonstrate commerciality for a potential future Y zone development.
OPERATIONS REVIEW
CAMBAY FIELD, Gujarat, India
(Oilex Operator - 45%)Cambay-76H Well
·; The retrieval operations that had been conducted in December 2011 continued in this quarter. The remainder of the coiled tubing and milling assembly was recovered in early March and milling operations resumed.
·; Retrieval (or fishing) operations were interrupted with high bottom hole pressure conditions and an influx of gas and fracture stimulation fluids requiring close monitoring and well control operations to stabilise the well were carried out frequently during January and February.
·; Gas and condensate, nitrogen (that had been injected in the early stages of attempting to free the milling assembly) and fracture stimulation fluids have been circulated to surface and the hydrocarbons have been flared.
·; Re-interpretation of the post- stimulation fracture pressure data revealed that the reservoir pressure is higher than previously anticipated and explained in part the unusually high pressure that was causing the well to flow at pressures not seen in any other wells known to Oilex in the Cambay Basin. The mud system was changed out to a solution that could be built up to a higher density than previously available and the well was stabilised.
·; With the well under control, operations to retrieve the stuck milling assembly and coiled tubing were successfully concluded in early March. Milling of the seats and balls of the remaining fracture stimulation stages then resumed.
·; Operations were terminated at a depth of 2,581 metres, with 6 stages fully opened to flow when a significant influx of fracture stimulation sand from a localised zone of higher pressure was encountered. The sand packed off the milling assembly and prevented further progress. At the same time the drill pipe parted while pulling out of the well. A further ten instances of deficiencies in the drill pipe integrity were identified after X ray testing and new pipe was procured as a contingency.
·; During April, operations to retrieve the drill pipe and milling assembly were progressing.
·; On completion of the retrieval operations, it is anticipated that production tubing will be run and the well will be flowed back to surface for cleanup prior to testing.
Oilex successfully drilled and completed the 2,740 metre Cambay-76H well in the period from June to July 2011. The well included a 610 metre horizontal section and an eight stage fracture stimulation program, the first well onshore India to apply these technologies for development of tight reservoirs. However clean-up operations in preparation for production testing were suspended when a coiled tubing milling assembly became stuck in the wellbore. Recovery operations have been attenuated by well control and equipment integrity problems.
During the Quarter a previously stimulated well - Cambay 73 (nearby Cambay 76H), was reopened in order to flow it back to surface, clean up the well and to gather additional data to evaluate the potential of the Y zone reservoir.
A further assessment of resources and reserves is anticipated to be undertaken by NSAI once sufficient production data are obtained from the Cambay 76H well.
BHANDUT FIELD, Gujarat, India
(Oilex Operator - 40%)·; Workover activity on two wells, Bhandut-3 and Bhandut-4, was partly successful with a thin gas zone in Bhandut-3 flowing gas to surface from a small structure. The zone has been tested and the results are being assessed.
·; Bhandut-4 well was shutin pending further evaluation.
WA-388-P, Australia
(Oilex - 8.4%)·; The Operator (Apache) provided the Joint Venture with the final prospectivity review for the permit following the completion of the Rose 3D seismic reprocessing and the updated calibration utilising the recent La-Rocca-1 well results.
·; The WA-388-P permit term will expire on the 28th August 2012. The Operator has proposed a relinquishment and renewal programme to be submitted to the Designated Authority for consideration.
JPDA 06-103, TIMOR SEA
(Oilex Operator - 10%)·; Interpretation of the Bazartete reprocessed seismic data was completed during the quarter. Volumetrics, risking and economics were also completed. The Bazartete prospect has been delineated as a significant structural depth closure. Final mapping of the Bazartete seismic data shows the presence of a broader depth closure than was previously mapped. The proposed Bazartete-1 well has been selected as the third commitment well location in JPDA 06-103.
·; Investigations regarding the availability of a suitable rig for drilling in the contract area and well planning were undertaken during the quarter.
West Kampar PSC, Central Sumatra
(Oilex - 45% + further 22.5% secured*)·; Negotiations are continuing as Oilex pursues a commercial resolution to the Joint Venture dispute. At the same time, the Company intends to protect its participating interest in the West Kampar PSC and to pursue enforcement of its Arbitration Award as appropriate.
Financial
·; Oilex retained cash at the end of the Quarter of A$7.7 million with no commercial loans.
Health, Safety, Security and Environment
No Lost Time Incidents were recorded for Oilex personnel or contractors at any location.
The Company's website www.oilex.com.au is regularly updated with current information.
For further information, please contact:
Oilex Ltd | ||
Bruce McCarthy - Managing Director: | +61 (0)8 9485 3200 | Western Australia |
Ben Clube - Finance Director & Company Secretary: | +61 (0)8 9485 3200 | Western Australia |
Read Corporate | ||
Nicholas Read: [email protected] | +61 (0)8 9388 1474 | Western Australia |
Tavistock Communications | +44 (0)20 79203150 | UK |
Paul Youens: [email protected] | +44 (0)7843 260 623 | UK |
Ed Portman: [email protected] | +44 (0)7733 363 501 | UK |
Ambrian Partners Limited (Nominated Adviser and AIM Broker) | ||
Samantha Harrison: [email protected] | +44 (0)20 7634 4712 | UK |
Information in this report relating to hydrocarbon reserves or resources has been compiled by Mr Ray Barnes B.Sc. (Hons), the Technical Director of Oilex Ltd who has over 38 years' experience in petroleum geology and is a member of the AAPG. Mr Barnes consents to the inclusion of the information in this report relating to hydrocarbon reserves and resources in the form and context in which it appears. Resource estimates contained in this report are in accordance with the standard definitions set out by the Society of Petroleum Engineers, Petroleum Resources Management System, 2007.
This document may include forward-looking statements. Forward-looking statements include, but are not necessarily limited to, statements concerning Oilex Ltd's planned exploration program and other statements that are not historic facts. When used in this document, the words such as "could", "plan", "estimate" "expect", "intend", "may", "potential", "should" and similar expressions are forward-looking statements. Although Oilex Ltd believes that its expectations reflected in these are reasonable, such statements involve risks and uncertainties, and no assurance can be given that actual results will be consistent with these forward-looking statements."
CORPORATE DETAILS | ||
Board of Directors | Share Registry | |
Max Cozijn | Non-Executive Chairman | Security Transfer Registrars Pty Ltd 770 Canning Highway Applecross WA 6153, Australia Telephone: +61 8 9315 2333 Facsimile: +61 8 9315 2233 Email: [email protected] |
Bruce McCarthy | Managing Director | |
Ray Barnes | Technical Director | |
Ben Clube | Finance Director & Company Secretary | |
Sundeep Bhandari | Non-Executive Vice Chairman | |
Ron Miller | Non-Executive Director | |
Capital Structure as at 30 April 2012 | Stock Exchange Listing | |
Ordinary Shares 253,324,885 | Australian Stock Exchange Code: OEX | |
Unlisted Options 33,625,000 | AIM Market of London Stock Exchange Code: OEX | |
Unlisted Performance Rights 22,000 |
LIST OF ABBREVIATIONS AND DEFINITIONS USED HEREIN
MMBO | Million standard barrels of oil or condensate |
BBO | Billion standard barrels of oil or condensate |
BCF | Billion Cubic Feet at standard temperature and pressure conditions |
BCFE | Billion Cubic Feet Equivalent calculated by applying a condensate gas conversion of 5.62 |
Discovered in place volume | Is that quantity of petroleum that is estimated, as of a given date, to be contained in known accumulations prior to production |
Undiscovered in place volume | Is that quantity of petroleum estimated, as of a given date, to be contained within accumulations yet to be discovered |
Prospective Resources | Those quantities of petroleum which are estimated, as of a given date, to be potentially recoverable from undiscovered accumulations by application of future development projects. Prospective Resources have both an associated chance of discovery and a chance of development. |
MMSCF/DAY | Million standard cubic feet (of gas) per day |
Contingent Resources | Those quantities of petroleum estimated, as of a given date, to be potentially recoverable from known accumulations, but the applied project(s) are not yet considered mature enough for commercial development due to one or more contingencies. Contingent Resources may include, for example, projects for which there are currently no viable markets, or where commercial recovery is dependent on technology under development, or where evaluation of the accumulation is insufficient to clearly assess commerciality. |
Reserves | Reserves are those quantities of petroleum anticipated to be commercially recoverable by application of development projects to known accumulations from a given date forward under defined conditions. Reserves must satisfy four criteria: they must be discovered, recoverable, commercial, and remaining (as of the evaluation date) based on the development project(s) applied. |
asset schedule | ||||
ASSET | BASIN / STATE / COUNTRY | JOINT VENTURE PARTIES | EQUITY % | OPERATOR |
Cambay Field PSC | Cambay/ Gujarat / India | Oilex Ltd | 30.0 | Oilex Ltd |
Oilex NL Holdings (India) Limited | 15.0 | |||
Gujarat State Petroleum Corp. Ltd | 55.0 | |||
Bhandut Field PSC | Cambay/ Gujarat / India | Oilex NL Holdings (India) Limited | 40.0 | Oilex NL Holdings(India) Limited |
Gujarat State Petroleum Corp. Ltd | 60.0 | |||
Sabarmati Field PSC | Cambay/ Gujarat / India | Oilex NL Holdings (India) Limited | 40.0 | Oilex NL Holdings (India) Limited |
Gujarat State Petroleum Corp. Ltd | 60.0 | |||
West Kampar PSC | Central Sumatra/ Indonesia | Oilex (West Kampar) Limited | 67.5 (1) | PT Sumatera Persada Energi |
PT Sumatera Persada Energi | 32.5 | |||
JPDA 06-103 PSC | Flamingo / Joint Petroleum Development Area / Timor-Leste & Australia | Oilex (JPDA 06-103) Ltd | 10.0 | Oilex (JPDA 06-103) Ltd |
Japan Energy E&P JPDA Pty Ltd | 15.0 | |||
GSPC (JPDA) Limited | 20.0 | |||
Videocon JPDA 06-103 Limited | 20.0 | |||
Bharat PetroResources JPDA Ltd | 20.0 | |||
Pan Pacific Petroleum (JPDA 06-103) Pty Ltd | 15.0 | |||
WA-388-P | Carnarvon/ WA / Australia | Oilex Ltd | 8.4 | Apache Northwest Pty Ltd |
Gujarat State Petroleum Corp. Ltd | 8.4 | |||
Videocon Industries Ltd | 8.4 | |||
Bharat PetroResources Ltd | 8.4 | |||
Hindustan Petroleum Corp Ltd | 8.4 | |||
Apache Northwest Pty Ltd | 40.0 | |||
Sasol Petroleum Australia Ltd | 18.0 |
(1)Oilex (West Kampar) Limited is entitled to have assigned an additional 22.5% to its holding through the exercise of its rights under a Power of Attorney granted by SPE following the failure of SPE to repay funds due. The assignment has been provided to BPMigas but has not yet been approved or rejected. If Oilex is paid the funds due then it will not pursue this assignment.
Rule 5.3
Appendix 5B
Mining exploration entity quarterly reportIntroduced 1/7/96. Origin: Appendix 8. Amended 1/7/97, 1/7/98, 30/9/01, 1/6/10, 17/12/10.
Name of entity
OILEX LTD |
ABN | Quarter ended ("current quarter") | |
50 078 652 632 | 31 MARCH 2012 |
1 | Consolidated statement of cash flows | ||||
| Current quarter $A'000 | Year to date (9 months) $A'000 | |||
Cash flows related to operating activities | |||||
1.1 | Receipts from product sales and related debtors | 99 | 244 | ||
1.2 | Payments for (a) exploration and evaluation | (2,288) | (10,339) | ||
(b) development | - | - | |||
(c) production | (162) | (325) | |||
(d) administration (net) | (300) | (1,289) | |||
1.3 | Dividends received | - | - | ||
1.4 | Interest and other items of a similar nature received | 51 | 196 | ||
1.5 | Interest and other costs of finance paid | (10) | (10) | ||
1.6 | Income taxes paid | - | - | ||
1.7 | Other (provide details if material) | - | - | ||
Net Operating Cash Flows | (2,610) | (11,523) | |||
Cash flows related to investing activities | |||||
1.8 | Payment for purchases of: (a) prospects (b) equity investments (c) other fixed assets |
- - (6) |
- - (35) | ||
1.9 | Proceeds from sale of: (a) prospects (b) equity investments (c) other fixed assets |
- - - |
- - - | ||
1.10 | Loans to other entities | - | - | ||
1.11 | Loans repaid by other entities | 1 | 1 | ||
1.12 | Other (provide details if material) | - | - | ||
Net investing cash flows | (5) | (34) | |||
1.13 | Total operating and investing cash flows (carried forward) | (2,615) | (11,557) | ||
Current quarter $A'000 | Year to date (9 months) $A'000 | ||
1.13 | Total operating and investing cash flows (brought forward) | (2,615) | (11,557) |
| Cash flows related to financing activities | ||
1.14 | Proceeds from issues of shares, options, etc | - | 13 |
1.15 | Proceeds from sale of forfeited shares | - | - |
1.16 | Proceeds from borrowings (net) | - | - |
1.17 | Repayment of borrowings | - | - |
1.18 | Dividends paid | - | - |
1.19 | Other (provide details if material) | - | - |
| Net financing cash flows | - | 13 |
Net increase (decrease) in cash held | (2,615) | (11,544) | |
1.20 | Cash at beginning of quarter/year to date | 10,459 | 19,070 |
1.21 | Exchange rate adjustments to item 1.20 | (108) | 210 |
1.22 | Cash at end of quarter | 7,736 | 7,736 |
Payments to directors of the entity and associates of the directors Payments to related entities of the entity and associates of the related entities | Current quarter $A'000 | |
1.23 | Aggregate amount of payments to the parties included in item 1.2 | 459 |
1.24 | Aggregate amount of loans to the parties included in item 1.10 | |
1.25 | Explanation necessary for an understanding of the transactions | |
2 | Non-cash financing and investing activities |
2.1 | Details of financing and investing transactions which have had a material effect on consolidated assets and liabilities but did not involve cash flows |
N/A | |
2.2 | Details of outlays made by other entities to establish or increase their share in projects in which the reporting entity has an interest |
N/A |
3 | Financing facilities available Add notes as necessary for an understanding of the position. | Amount available $A'000 | Amount used $A'000 |
3.1 | Loan facilities | - | - |
3.2 | Credit standby arrangements | - | - |
4 | Estimated cash outflows for next quarter | $A'000 |
4.1 | Exploration and evaluation | 3,400 |
4.2 | Development | - |
4.3 | Production | 150 |
4.4 | Administration | 350 |
Total | 3,900 |
5 | Reconciliation of cash | ||
Reconciliation of cash at the end of the quarter (as shown in the consolidated statement of cash flows) to the related items in the accounts is as follows. | Current quarter $A'000 | Previous quarter $A'000 | |
5.1 | Cash on hand and at bank | 4,173 | 3,817 |
5.2 | Deposits at call | 3,563 | 6,642 |
5.3 | Bank overdraft | - | - |
5.4 | Other (provide details) | - | - |
Total: cash at end of quarter (item 1.22) | 7,736 | 10,459 |
6 | Changes in interests in mining tenements | ||||
Tenement reference | Nature of interest (note (2)) | Interest at beginning of quarter | Interest at end of quarter | ||
6.1 | Interests in mining tenements relinquished, reduced or lapsed | Refer to Permit/Asset Schedule in Quarterly Report | |||
6.2 | Interests in mining tenements acquired or increased | Refer to Permit/Asset Schedule in Quarterly Report |
7 | Issued and quoted securities at end of current quarter Description includes rate of interest and any redemption or conversion rights together with prices and dates. | ||||||
Total number | Number quoted | Issue price per security | Amount paid up per security | ||||
7.1 | Preference +securities (description) | - | - | - | - | ||
7.2 | Changes during quarter (a) Increases through issues (b) Decreases through returns of capital, buy-backs, redemptions | - | - | - | - | ||
7.3 | +Ordinary securities | 253,324,885 | 253,324,885 | Various | - | ||
7.4 | Changes during quarter (a) Increases through issues (options exercised) (b) Decreases through returns of capital, buy-backs | - | - | - | - | ||
- | - | - | - | ||||
7.5 | +Convertible debt securities (description) | - | - | - |
- | ||
7.6 | Changes during quarter (a) Increases through issues (b) Decreases through securities matured, converted | - | - | - | - | ||
7 | Issued and quoted securities at end of current quarter (cont'd) Description includes rate of interest and any redemption or conversion rights together with prices and dates. | ||||||
Total number | Number quoted | Issue price per security | Amount paid up per security | ||||
7.7 | Options | Exercise price | Expiry date | ||||
(description and conversion factor) | |||||||
900,000 | - | $2.75 | 30/06/2012 | ||||
2,000,000 | - | $0.30 | 15/09/2012 | ||||
16,687,500 | - | $0.30 | 10/11/2012 | ||||
75,000 | - | $0.50 | 01/08/2013 | ||||
4,150,000 | - | $0.30 | 01/07/2014 | ||||
8,737,500 | - | $0.37 | 10/11/2014 | ||||
500,000 | - | $0.36 | 21/11/2014 | ||||
75,000 | - | $0.63 | 01/08/2015 | ||||
500,000 | - | $0.46 | 21/11/2017 | ||||
Total |
33,625,000 | ||||||
2008 Performance Rights | |||||||
22,000 |
Tranche 3 expire 1/07/2013 | ||||||
Total |
22,000 | ||||||
7.8 |
Issued during quarter | ||||||
- | - | - | - | ||||
7.9 | Exercised during quarter | - | - | - | - | ||
7.10 |
Expired during quarter | Options | |||||
300,000 | - | $2.75 | 31/03/2012 | ||||
75,000 | - | $0.50 | 01/08/2012 | ||||
75,000 | - | $0.63 | 01/08/2015 | ||||
2008 Performance Rights | |||||||
- | - | - | |||||
7.11 | Debentures (totals only) | Nil | Nil | ||||
7.12 | Unsecured notes (totals only) | Nil | Nil | ||||
Compliance statement
1 This statement has been prepared under accounting policies which comply with accounting standards as defined in the Corporations Act or other standards acceptable to ASX.
2 This statement does give a true and fair view of the matters disclosed.
Sign here: Date: 30 April 2012
(Director and Company Secretary)
Print name: Ben Clube
Related Shares:
OEX.L