22nd Oct 2018 07:00
LEI No: 213800FGJZ2WAC6Y2L94
REGULATORY RELEASE
22 October 2018
Fourth Quarter and Full Year 2018 Production Report and Business Update
Lonmin Plc ("Lonmin" or "the Company"), one of the world's largest primary platinum producers, today announces its production results for the three and twelve months to 30 September 2018, including a business update, both on an unaudited basis. Lonmin also released a separate announcement today, on a refinancing of its existing debt facilities.
Overview
· Regrettably we had a fatality on 30 September 2018, ending a 15 month fatality free period at Lonmin's operations. The twelve-month rolling LTIFR to 30 September 2018 improved by 12.39% to 3.96 per million man hours.
· Unaudited net cash improved to $114 million at 30 September 2018, up from $103 million at 30 September 2017.
· Tonnes mined by our Generation 2 shafts for the year increased 1.6% to 7.6 million tonnes, reflecting consistent performance at our core shafts. The average shaft utilisation capacity for our Generation 2 shafts was 83%, with Saffy shaft achieving an average shaft utilisation of 92% for the year.
· Tonnes mined by our Generation 2 shafts for the fourth quarter of 2.1 million tonnes were broadly flat on Q4 2017.
· Platinum sales of 681,580 ounces for the year exceeded our guidance of between 650,000 and 680,000 Platinum ounces. Platinum sales for the fourth quarter were 217,710 ounces, broadly flat on Q4 2017. Total PGM sales for the full year were 1,323,708 ounces.
· Our unaudited average Rand full basket price (including base metals) for the quarter up 25.5% on Q4 2017 at R14,512 per PGM ounce and up 19.7% for the year, at R13,447 per PGM ounce.
· Our unaudited unit costs for Q4 2018 were R11,617 per PGM ounce (6E basis), an increase of 0.8% on Q4 2017. Unaudited unit costs for the year were R12,271 per PGM ounce, an increase of 4.9% on prior year and within our unit cost guidance of between R12,000 and R12,500 per PGM ounce.
Ben Magara, Chief Executive Officer, said: "Despite tough market conditions, except the favourable Rand, we have delivered more than we promised in all areas of our business. These pleasing results demonstrate once again that despite these uncertain times, we can dig deep and use all levers within our control to maintain our net cash position. Both the good business performance and the new funding arrangement we announced today enhance Lonmin's short term liquidity. However, the new facility is still insufficient to avoid the announced retrenchments and shaft closures. Accordingly, the Board of Lonmin remains focused on completing the Sibanye-Stillwater all share transaction, which we firmly believe provides a sustainable solution and is in the best interest of all our stakeholders."
|
|
|
| 3 months | 3 months | % | 12 months | 12 months | % |
|
|
|
| to 30 Sep 2018 | to 30 Sep 2017 | change | to 30 Sep 2018 | to 30 Sep 2017 | change |
Tonnes | Generation 2 | K3 Shaft | kt | 778 | 852 | -8.6% | 2 858 | 2 831 | 1.0% |
Mined1 |
| Rowland Shaft | kt | 544 | 520 | 4.6% | 1 904 | 1 925 | -1.1% |
|
| Saffy Shaft | kt | 609 | 604 | 0.9% | 2 211 | 2 174 | 1.7% |
|
| East 3 Shaft combined | kt | 188 | 170 | 10.4% | 654 | 574 | 13.8% |
| Total | Generation 2 | kt | 2 120 | 2 146 | -1.2% | 7 627 | 7 504 | 1.6% |
| Generation 1 |
| kt | 625 | 650 | -3.9% | 2 257 | 2 600 | -13.2% |
Sales refined metal |
| Platinum Total PGMs | oz oz | 217 710 416 944 | 218 687 426 200 | -0.4% -2.2% | 681 580 1 323 708 | 706 030 1 381 413 | -3.5% -4.2% |
Average | $ basket incl. by-product revenue12 | $/oz | 1 027 | 880 | 16.7% | 1 016 | 844 | 20.4% | |
Prices | R basket incl. by-product revenue12 | ZAR/oz | 14 512 | 11 567 | 25.5% | 13 447 | 11 236 | 19.7% | |
Exchange rate | Average rate for period13 | ZAR/$ | 14.06 | 13.17 | 6.7% | 13.07 | 13.37 | -2.3% | |
Unit costs | Unaudited cost of production per PGM ounce | ZAR/oz | 11 617 | 11 524 | -0.8% |
|
|
|
Safety
Our continued collaboration with key stakeholders, including employees, the Department of Mineral Resources ("DMR") and our majority union, the Association of Mineworkers and Construction Union ("AMCU"), continues to yield results, as we have experienced improved safety performance and decreasing Section 54 stoppages. We apply the international OHSAS 18001 Occupational Health and Safety Management Systems at all our Generation 2 shafts including Processing and Shared Services to assist our operations to manage, control and improve our health and safety risks. Our safety strategy is centred on the belief that Zero Harm is achievable and important contributions are required from all stakeholders to achieve it.
· Despite most safety indicators showing improvement, regrettably one of our colleagues was fatally injured on 30 September 2018. We extend our deepest condolences to the family and friends of our colleague and deeply regret our loss.
· Our twelve month rolling Lost Time Injury Frequency Rate ("LTIFR") to 30 September 2018 improved by 12.39% to 3.96 per million man hours from 4.52 per million man hours in the prior year due to a 9.32% reduction in Lost Time Injuries.
· Our twelve month rolling Total Injury Frequency Rate ("TIFR") to 30 September 2018 improved by 5.23% to 10.14 per million man hours from 10.70 in the prior year due to a 11.45% reduction in Total Injuries.
· Lonmin achieved 15 months fatality free from 29 June 2017 to 29 September 2018.
· Lonmin received the most prestigious award at the National MineSafe 2018 - Best Safety Improvement Mining Company.
· At MineSafe 2018 our K3 Shaft UG2 Section won the JT Ryan award and four other awards were received in two more categories.
· Rowland Shaft achieved 3 million Fatality Free Shifts and 4B shaft and E3 shaft are both on 1 million Fatality Free Shifts.
· Some of the noteworthy achievements by the Processing Divisions include the Assay laboratory achieving 12 years of operating without a lost-time injury and the PMR operating 12 months without any injury.
· Our safety performance is only possible through our circa 32,000 employees and contractors remaining vigilant in order to work and return home safely.
Fourth Quarter Production Overview
Mining Operations
Our key Generation 2 shafts production for the quarter of 2.1 million tonnes (around 77% of total mining production) was broadly flat on the 2.1 million tonnes production in Q4 2017.
Generation 2 shafts
· K3 shaft produced 778,000 tonnes, a decrease of 8.6% on the prior year period as expected, as the development crews which had moved to stoping in the prior year (as part of the turnaround strategy), returned to their development area.
· Saffy shaft produced 609,000 tonnes, an increase of 0.9% on the Q4 2017, demonstrating the continued steady state performance.
· Rowland shaft produced 544,000 tonnes, an increase of 4.6% on Q4 2017, as we opened new reserves, released backlog sweepings and equipped previously unavailable remnant "white" areas. This was the shaft's best quarterly production since the fourth quarter of the 2011 financial year. Rowland's immediately available ore reserves have improved from 11.5 months to 14.3 months.
· The combined E3 unit (E3 plus Pandora) produced 188,000 tonnes for the quarter, an increase of 10.4% on Q4 2017 on the back of safety performance and steadfast management. On completion of the Pandora acquisition in December 2017, the E3 shaft and Pandora production were combined and reclassified as a Generation 2 shaft, with comparative numbers adjusted accordingly.
Generation 1 shafts
In line with the Group's rationalisation of high cost areas in an oversupplied market, production from our Generation 1 shafts (4B, Hossy, W1 and E1) at 625,000 tonnes continues to decline as planned, as we optimise our remaining ore reserves in these shafts, and was 3.9% lower than Q4 2017. The decrease is also due to E2, which produced until Q3 2017, being on care and maintenance since November 2017.
As W1 and E1 are at the end of their resource lives, mining is in remnant areas. Consequently, contractors operate these shafts and are responsible for all the costs associated with such shafts. Lonmin pays a predetermined rate per tonne of ore produced. We thus retain the flexibility to cease production if and when these shafts become unprofitable.
4B shaft produced 358,000 tonnes, an increase of 10.4% on the prior year period, as it sought to recover from worse than anticipated geological conditions and safety challenges of the previous quarter. As previously reported, following a review of 4B's performance and reserve life, this shaft was reclassified as a Generation 1 shaft and comparative numbers adjusted accordingly.
Hossy shaft produced 178,000 tonnes, an increase of 9.7% on Q4 2017. Hossy shaft was originally scheduled to be put on care and maintenance, but it continues to demonstrate potential to contribute to the business and its performance is being reviewed on a quarterly basis. Based on this and the Immediately Available Ore reserves ("IAOR"), which stands at 6.8 months, we continue to operate Hossy.
Production Losses
For the fourth quarter, production lost due to Section 54 safety stoppages totalled only 1,000 tonnes, compared to 38,000 tonnes in Q4 2017, on the back of our improved ongoing focus on safety and pro-active interactions with employees, organised labour, the Inspectorate of the DMR and communities.
| Q4 2018 Ore tonnes | Q4 2017 Ore tonnes |
Section 54 safety stoppages | 1,000 | 38,000 |
Management Induced Safety Stoppages and other | 15,000 | 22,000 |
Community disruptions and other | 22,000 | 56,000 |
Total tonnes lost | 38,000 | 116,000 |
Process Operations
Concentrator production - Mining
Total tonnes milled from mining operations in the quarter were broadly flat at 2.8 million tonnes.
Total metals-in-concentrate produced of 183,948 Platinum ounces decreased by 1.5% compared to Q4 2017.
Underground milled head grade at 4.57 grammes per tonne (5PGE+Au) decreased by 3.3% when compared to the 4.72 grammes per tonne achieved in the prior year period.
Concentrator recoveries from underground mining for the quarter were 86.8% compared to 87.6% achieved in Q4 2017.
Concentrator production - Bulk Tailings re-Treatment Project ("BTT")
The BTT project was successfully commissioned in February 2018. Total tonnes milled from the BTT project were 894,000 tonnes for the quarter, with a head grade of 1.12 grammes per tonne and a recovery rate of 23.2%, producing metals-in-concentrate of 3,633 Platinum ounces and 7,156 PGM ounces. Having reached designed throughput, we are now focusing on improving recoveries.
Concentrate purchases increased by 58% to 6,167 saleable Platinum ounces, as we sought to maximise downstream processing utilisation and reduce unit costs.
Processing
The smelters operated well and the stock that was previously locked up in the prior period has now been released.
Total saleable refined Platinum production at 217,951 ounces was 5.8% higher than Q4 2017. Total saleable PGMs produced were 423,833 ounces, an increase of 8.0% on Q4 2017.
We released 6,000 Platinum ounces from the smelter clean-up project during this period, compared to the 12,445 Platinum ounces released in Q4 2017.
Sales & Pricing
Platinum sales for the quarter were 217,710 ounces, broadly flat on Q4 2017. PGM sales were 416,944 ounces, down 2.2% on Q4 2017
The US Dollar basket price (including base metal revenue) at $1,027 per ounce during the quarter was up 16.7% on Q4 2017 while the corresponding Rand basket price (R14,512 per PGM ounce) was 25.5% higher than Q4 2017. The average Rand to US Dollar exchange rate was 6.7% weaker at 14.06 compared to 13.17 in Q4 2017.
Full Year Production Overview
Mining Operations
The improvement in our mining production performance and the mining rhythm established following implementation of flatter management structures and other measures to improve performance since March 2017 has continued in the current year, with our key Generation 2 shafts producing 7.6 million tonnes (around 77% of total mining production), increasing production by 1.6%.
Generation 2 shafts
· K3, our biggest shaft, produced 2.9 million tonnes, an increase of 1.0% on the prior year.
· Saffy shaft produced 2.2 million tonnes, an increase of 1.7% on the prior year, demonstrating the continued steady state performance.
· Rowland shaft produced 1.9 million tonnes, down 1.1% on the prior year, notwithstanding 4.6% year- on-year increase in the fourth quarter and the increase in the IAOR to 14.3 months from 11.5 months in Q3 2018, achieved by opening new reserves, releasing backlog sweepings and equipping previously unavailable remnant "white" areas.
· The combined E3 unit (E3 plus Pandora) produced 0.7 million tonnes for the year, an increase of 13.8% on the prior year, following the consolidation with E3 and the unlocking of synergies after the acquisition of 100% of Pandora.
Generation 1 shafts
Production from our Generation 1 shafts (4B, Hossy, W1, E1 and E2) at 2.3 million tonnes was 13.2% lower than the prior year, in line with the Group's rationalisation of these shafts. Newman shaft was placed on care and maintenance in March 2017.
Production Losses
We are encouraged that tonnes lost due to Section 54 safety stoppages for the year were significantly lower at 20,000 tonnes compared to the prior year of 276,000 tonnes. This emphasised our improving safety performance and our continued proactive engagement with all stakeholders including employees, organised labour, the Inspectorate of the DMR and communities. The reduced operational disruptions facilitated a safe mining rhythm which is crucial for good production.
| 2018 Ore tonnes | 2017 Ore tonnes |
Section 54 safety stoppages | 20,000 | 276,000 |
Management induced safety stoppages and other | 96,000 | 176,000 |
Community disruptions and other | 54,000 | 143,000 |
Total tonnes lost | 170,000 | 595,000 |
Immediately Available Ore Reserves
The immediately available ore reserve position of our Generation 2 shafts at 30 September 2018 was equivalent to 21 months average production versus 20 months at 30 September 2017.
|
(m2 '000) |
| Months | ||
| 2018 | 2017 |
| 2018 | 2017 |
K3 | 806 | 844 |
| 22 | 19 |
Rowland | 415 | 309 |
| 14 | 12 |
Saffy | 738 | 772 |
| 23 | 25 |
E3 | 348 | 345 |
| 30 | 29 |
Generation 2 | 2 307 | 2 270 |
| 21 | 20 |
Generation 1 | 448 | 700 |
| 21 | 17 |
K4 | 188 | 188 |
|
|
|
Total | 2 943 | 3 158 |
| 21 | 19 |
We have successfully increased Rowland's immediately available ore reserves to 14 months as at 30 September 2018 from 11.5 as at 30 June 2018, mainly due to the first "raise holings" in the MK2 area which have established additional mining faces.
Lonmin is progressing discussions to secure third party funding for the MK2 extension project.
The ore reserve position of the Marikana mining operations is still at a level that provides the necessary flexibility required for efficient mining (industry benchmark of around 12-15 months).
Process Operations
Concentrator production - Mining
Total tonnes milled from mining operations for the year at 9.8 million tonnes were broadly flat on the prior year, despite reduced output from depleting Generation 1 shafts
Total metals-in-concentrate produced at 653,969 Platinum ounces were broadly flat compared to the prior year.
Underground milled head grade at 4.57 grammes per tonne (5PGE+Au) decreased marginally by 0.9% when compared to the 4.61 grammes per tonne achieved in the prior year.
Concentrator recoveries from underground mining for the quarter increased marginally to 87.3% compared to 87.1% achieved in the prior year.
Concentrator production - Bulk Tailings re-Treatment Project ("BTT")
The BTT project was successfully commissioned in February. Total tonnes milled from the BTT project were 2.0 million tonnes for the year, with a head grade of 1.10 grammes per tonne and a recovery rate of 21.3%, producing metals-in-concentrate of 7,417 Platinum ounces and 14,584 PGM ounces.
Concentrate purchases increased by 345% to 21,678 saleable Platinum ounces, as we sought to maximise downstream processing utilisation and reduce unit costs.
Processing
Furnace Number One had an unplanned outage in December 2017 bringing forward its planned shutdown scheduled for the end of 2018. Furnace Number Two was on a planned shut-down from 3 April till 5 May 2018. During these periods the three Pyromet furnaces were in operation.
Both the main Furnaces are stable after their individual shutdowns and continue to run normally and the metal that was previously locked up has been released.
Total saleable refined Platinum production at 678,588 ounces was 1.3% lower than the prior year production. Total saleable PGMs produced were 1,318,618 ounces, broadly flat on the prior year.
The smelter clean-up project and permanent release from the smelting and refining plants continued during the current year and released a total of 6,000 ounces of Platinum during the year, less than the 31,682 ounces in the prior year as expected.
Lonmin Beneficiation
· Thakadu Nickel Purification Plant
Thakadu Battery Materials (Pvt) Ltd is in the process of constructing a R250-million nickel purification plant at Lonmin's base metal refinery. The plant will convert Lonmin's existing crude nickel sulphate into high quality battery-grade nickel sulphate, which can be sold at a premium and thus create value for both Thakadu and Lonmin. The plant is able to produce 25,000 tonnes per year of high-purity nickel sulphate. All major equipment has been ordered and key contracts have been awarded by Thakadu. Commissioning of the plant is scheduled for 2019. The plant is expected to create over 60 permanent jobs once in operation.
· PMR Beneficiation - 3D Printing
The Lonmin beneficiation strategy includes the Additive Manufacturing or 3D printing of pure platinum powder. The project was developed from concept by the Lonmin marketing and process technology teams. The platinum powder used in 3D printing has very particular specifications and the powder was developed in house by Lonmin employees. A 3D printer is housed at Lonmin's PMR and is unique in that it is the first to be used for the 3D printing of pure platinum metal. Commissioning and optimization of the 3D printer is ongoing, with assistance from members of Platforum, which is a collaboration between South Africa's Central University of Technology, Northwest University of Technology, Vaal University of Technology and Lonmin. This vehicle aims to provide prototype facilities to budding entrepreneurs to produce products containing PGM's via additive manufacturing or 3D printing.
Sales & Pricing
Sales for the year were 681,580 Platinum ounces (1,323,708 PGM ounces), exceeding the sales guidance of 650,000 to 680,000 Platinum ounces.
For the year, the unaudited US Dollar basket price (including base metal revenue) at $1,016 per PGM ounce increased by 20.4% on the prior year, while the corresponding unaudited Rand basket price (R13,447 per PGM ounce) was 19.7% higher than the prior year. The unaudited average Rand to US Dollar exchange rate for the year was 2.3% stronger at 13.07 compared to 13.37 for the prior year.
Unit Costs (subject to audit adjustments)
As we continue to manage our costs, unaudited unit costs for the quarter were R11,617 per PGM ounce, an increase of 0.8% on the R11,524 per PGM ounce achieved in the prior year and unaudited unit costs for the year were R12,271 per PGM ounce, an increase of 4.9% on the R11,701 per PGM ounce achieved in the prior year, and within our unit cost guidance of between R12,000 and R12,500 per PGM ounce.
Liquidity
· Unaudited gross cash improved to $264 million at 30 Sept 2018 up from $253 million at 30 September 2017.
· Unaudited net cash improved to $114 million (gross cash of $264 million less the drawn term loan of $150 million) at 30 Sept 2018, up from $103 million (gross cash of $253 million less the drawn term loan of $150 million) at 30 September 2017.
Capital Expenditure
We have improved our IAOR from 19 to 21 months year on year despite the unaudited Capital expenditure being limited to R967 million ($73 million) compared with R1,336 million ($100 million) in the prior year, and included R74 million (2017 - R370 million) for the third party funded Bulk Tailings Treatment project. This is in line with our strategy of limiting capital expenditure to levels required to satisfy regulatory and safety standards, essential sustaining capital expenditure in the continuing shafts and ensuring that IAOR positions where applicable, are maintained at an acceptable level to sustain production at our Generation 2 shafts.
| 2017 | 2018 |
| 2018 Revised Guidance | 2018 Original Guidance | |
| Actual | Actual |
|
|
| |
| Rm | Rm |
| Rm | Rm | |
|
|
|
|
|
| |
K3 | 170 | 92 |
| 130 | 157 | |
Saffy | 21 | 25 |
| 21 | 29 | |
Rowland | 48 | 46 |
| 55 | 61 | |
Rowland MK2 | 178 | 121 |
| 117 | 137 | |
Generation 2 shafts | 417 | 283 |
| 323 | 385 | |
K4 | 7 | - |
| - | 2 | |
Hossy | 1 | 28 |
| 42 | 30 | |
Generation 3 & 1 shafts | 8 | 28 |
| 42 | 32 | |
Central & other mining | 93 | 76 |
| 120 | 139 | |
Total Mining | 518 | 388 |
| 485 | 556 | |
|
|
|
|
|
| |
Concentrators - excl BTT | 158 | 128 |
| 130 | 159 | |
BTT | 370 | 74 |
| 74 | 59 | |
Smelting & Refining | 95 | 206 |
| 318 | 324 | |
|
|
|
|
|
| |
Total Process | 623 | 391 |
| 522 | 542 | |
Infill apartments | 151 | 150 |
| 161 | 191 | |
Other | 44 | 38 |
| 51 | 40 | |
Total | 1 336 | 967 |
| 1 219 | 1 329 | |
The capital expenditure was less than our revised guidance of R1,2 billion. The main deferrals were on K3, engineering, stay in business, design studies and regulatory compliance spending on smelting and refining.
Capital invested in the period included R121 million for the Rowland MK2 project.
Update on disposals
· Petrozim
As previously announced, Lonmin entered into a conditional Sale of Shares Agreement to sell Lonmin's 50% interest in Petrozim Line (Private) Limited ("Petrozim") for a gross cash consideration of $14,75 million to the National Oil Infrastructure Company of Zimbabwe (Private) Limited ("NOIC") (the "Transaction"). In addition, Lonmin will receive $8 million in the form of special dividends from Petrozim. The Transaction forms part of Lonmin's ongoing programme to dispose of non-core assets. The purchase price and special dividends will be used to pay down the term loan.
· Wallbridge Mining Toronto
Lonmin sold its approximately 6.8% portion of the outstanding shares of Wallbridge Mining Company Limited to Eric Sprott, for a total consideration of $4 million.
Update on all-share offer by Sibanye Stillwater
The South African Competition Commission (the "Commission") has recommended that the South African Competition Tribunal ("Tribunal") approves the proposed acquisition of Lonmin, subject to certain conditions, which are agreeable to both Sibanye-Stillwater and the Commission.
The Tribunal hearing has been set for 12 November to 14 November 2018. Lonmin is expecting to release its financial results for the year ended 30 September 2018 towards the end of November 2018.
The remaining substantive conditions to the closure of the transaction are the approval by the South African Competition Tribunal, and the approvals of Lonmin and Sibanye-Stillwater shareholders and the courts of England and Wales.
Lonmin remains fully committed to the transaction and continues to engage constructively with Sibanye Stillwater, the Tribunal and other stakeholders with a view to obtaining clearance in South Africa.
- ENDS -
ENQUIRIES
Investors / Analysts:
Tanya Chikanza (Executive Vice President: Corporate Strategy, Investor Relations and Corporate Communications) | +27 83 391 2859/+44 20 3908 1073
|
Andrew Mari (Investor Relations) +27 60 564 6419
Media:
TB Cardew Anthony Cardew / Emma Crawshaw / Tom Allison |
+44 207 930 0777 |
Lonmin Wendy Tlou (Head of Communications) |
+27 83 358 0049 |
Notes to editors
Lonmin, which is listed on both the London Stock Exchange and the Johannesburg Stock Exchange, is one of the world's largest primary producers of PGMs. These metals are essential for many industrial applications, especially catalytic converters for internal combustion engine emissions, as well as their widespread use in jewellery.
Lonmin's operations are situated in the Bushveld Igneous Complex in South Africa, where more than 70% of known global PGM resources are located.
The Company creates value through mining, refining and marketing PGMs and has a vertically integrated operational structure - from mine to market. Underpinning the operations is the Shared Services function which provides high quality levels of support and infrastructure across the operations.
For further information please visit our website: http://www.lonmin.com
|
|
|
|
|
| 3 months | 3 months | 12 months | 12 months | ||
|
|
|
|
|
| to 30 Sep | to 30 Sep | to 30 Sep | to 30 Sep | ||
|
|
|
|
|
| 2018 | 2017 | 2018 | 2017 | ||
Tonnes | Marikana | K3 Shaft | kt | 778 | 852 | 2 858 | 2 831 | ||||
mined1 |
| Rowland Shaft | kt | 544 | 520 | 1 904 | 1 925 | ||||
|
|
|
| Saffy Shaft | kt | 609 | 604 | 2 211 | 2 174 | ||
|
|
|
| East 3 Shaft Combined2 | kt | 188 | 170 | 654 | 574 | ||
|
|
|
| East 3 Shaft | kt | 188 | 14 | 553 | 71 | ||
|
|
|
| Pandora (100%) | kt |
| 156 | 101 | 503 | ||
|
|
|
| Generation 2 | kt | 2 120 | 2 146 | 7 627 | 7 504 | ||
|
|
|
| 4B Shaft | kt | 358 | 324 | 1 272 | 1 320 | ||
|
|
|
| Hossy Shaft | kt | 178 | 162 | 581 | 655 | ||
|
|
|
| Newman Shaft | kt |
|
|
| 51 | ||
|
|
|
| W1 Shaft | kt | 43 | 41 | 185 | 145 | ||
|
|
|
| East 1 Shaft | kt | 46 | 52 | 187 | 168 | ||
|
|
|
| East 2 Shaft | kt |
| 71 | 32 | 262 | ||
|
|
|
| Generation 1 | kt | 625 | 650 | 2 257 | 2 600 | ||
|
|
|
| Underground | kt | 2 745 | 2 796 | 9 884 | 10 104 | ||
|
|
|
| Opencast | kt | 17 |
| 93 | 45 | ||
|
|
| Lonmin (100%) | Total Tonnes Mined (100%) | kt | 2 762 | 2 796 | 9 977 | 10 148 | ||
|
|
|
| % tonnes mined from UG2 reef (100%) | % | 71.3% | 72.5% | 71.9% | 73.1% | ||
|
|
|
Lonmin (attributable) | Underground & Opencast | kt | 2 762 | 2 718 | 9 927 | 9 897 | ||
Ounces Mined3 | Lonmin excluding Pandora |
Pt Ounces | oz | 171 937 | 173 851 | 622 545 | 616 422 | ||||
| BTT | Pt Ounces | oz | 3 633 | 0 | 7 417 | 0 | ||||
| Lonmin excl Pandora incl BTT |
Pt Ounces | oz | 175 570 | 173 851 | 629 962 | 616 422 | ||||
| Pandora (100%) | Pt Ounces | oz |
| 11 198 | 7 557 | 34 886 | ||||
|
|
| Lonmin incl Pandora & BTT | Pt Ounces | oz | 175 570 | 185 049 | 637 519 | 651 307 | ||
|
|
| Lonmin excluding Pandora | PGM Ounces | oz | 331 927 | 334 154 | 1 200 482 | 1 182 793 | ||
|
|
| BTT | PGM Ounces | oz | 7 156 | 0 | 14 584 | 0 | ||
|
|
| Lonmin excl Pandora incl BTT | PGM Ounces | oz | 339 084 | 334 154 | 1 215 066 | 1 182 793 | ||
|
|
| Pandora (100%) | PGM Ounces | oz |
| 22 279 | 14 962 | 69 362 | ||
|
|
| Lonmin incl Pandora & BTT | PGM Ounces | oz | 339 084 | 356 433 | 1 230 028 | 1 252 155 | ||
Tonnes | Marikana | Underground | kt | 2 752 | 2 605 | 9 663 | 9 486 | ||||
milled4 |
| Opencast | kt | 14 | 0 | 70 | 49 | ||||
|
|
|
| Total | kt | 2 766 | 2 605 | 9 732 | 9 535 | ||
|
|
| Pandora 100%5 | Underground | kt | 0 | 156 | 101 | 503 | ||
|
|
| Lonmin Platinum | Underground | kt | 2 752 | 2 761 | 9 764 | 9 989 | ||
|
|
| Milled head grade7 | g/t | 4.57 | 4.72 | 4.57 | 4.61 | |||
|
|
| Recovery rate8 | % | 86.8% | 87.6% | 87.3% | 87.1% | |||
|
|
| Opencast | kt | 14 | 0 | 70 | 49 | |||
|
|
|
| Milled head grade7 | g/t | 4.55 | 4.97 | 4.66 | 4.42 | ||
|
|
|
| Recovery rate8 | % | 82.6% | 67.7% | 81.1% | 68.3% | ||
|
|
|
| BTT Plant6 | kt | 894 | 0 | 2 038 | 0 | ||
|
|
|
| Milled head grade7 | g/t | 1.12 | 0 | 1.10 | 0 | ||
|
|
|
| Recovery rate8 | % | 23.2% | 0.0% | 21.3% | 0.0% | ||
|
|
|
| Total | kt | 3 660 | 2 761 | 11 871 | 10 039 | ||
|
|
|
| Milled head grade7 | g/t | 3.73 | 4.72 | 3.97 | 4.61 | ||
|
|
|
| Recovery rate8 | % | 82.1% | 87.6% | 84.1% | 87.0% | ||
|
|
|
| 3 months | 3 months | 12 months | 12 months |
|
|
|
| to 30 Sep | to 30 Sep | to 30 Sep | to 30 Sep |
|
|
|
| 2018 | 2017 | 2018 | 2017 |
Metals-in- concentrate9 | Marikana | Platinum | oz | 174 148 | 171 659 | 617 316 | 609 354 |
| Palladium | oz | 81 801 | 79 810 | 288 516 | 282 246 | |
| Gold | oz | 3 968 | 4 259 | 14 938 | 15 171 | |
| Rhodium | oz | 25 515 | 24 229 | 88 806 | 86 254 | |
| Ruthenium | oz | 42 920 | 40 811 | 149 812 | 144 996 | |
| Iridium | oz | 8 948 | 8 611 | 31 139 | 30 303 | |
| Total PGMs | oz | 337 300 | 329 379 | 1 190 527 | 1 168 324 | |
| Nickel10 | MT | 807 | 880 | 3 005 | 3 144 | |
| Copper10 | MT | 510 | 544 | 1 922 | 1 964 | |
Pandora | Platinum | oz |
| 11 198 | 7 557 | 34 886 | |
| Palladium | oz |
| 5 303 | 3 573 | 16 509 | |
| Gold | oz |
| 76 | 52 | 243 | |
| Rhodium | oz |
| 1 906 | 1 261 | 5 928 | |
| Ruthenium | oz |
| 3 133 | 2 105 | 9 750 | |
| Iridium | oz |
| 662 | 414 | 2 047 | |
| Total PGMs | oz |
| 22 279 | 14 962 | 69 362 | |
| Nickel10 | MT |
| 18 | 11 | 65 | |
| Copper10 | MT |
| 10 | 6 | 31 | |
BTT Plant6 | Platinum | oz | 3 633 |
| 7 417 |
| |
| Palladium | oz | 1 509 |
| 3 095 |
| |
| Gold | oz | 34 |
| 69 |
| |
| Rhodium | oz | 521 |
| 1 051 |
| |
| Ruthenium | oz | 1 201 |
| 2 441 |
| |
| Iridium | oz | 259 |
| 510 |
| |
| Total PGMs | oz | 7 156 |
| 14 584 |
| |
| Nickel10 | MT | 5 |
| 11 |
| |
| Copper10 | MT | 5 |
| 10 |
| |
Concentrate | Platinum | oz | 6 167 | 3 907 | 21 678 | 4 871 | |
purchases | Palladium | oz | 2 099 | 1 239 | 7 158 | 1 550 | |
| Gold | oz | 23 | 16 | 78 | 21 | |
| Rhodium | oz | 894 | 503 | 2 989 | 597 | |
| Ruthenium | oz | 1 365 | 772 | 4 581 | 935 | |
| Iridium | oz | 325 | 221 | 1 126 | 263 | |
| Total PGMs | oz | 10 874 | 6 658 | 37 610 | 8 237 | |
| Nickel10 | MT | 8 | 5 | 25 | 6 | |
| Copper10 | MT | 5 | 3 | 15 | 4 | |
Lonmin Platinum | Platinum | oz | 183 948 | 186 764 | 653 969 | 649 111 | |
Palladium | oz | 85 409 | 86 353 | 302 342 | 300 305 | ||
| Gold | oz | 4 025 | 4 351 | 15 137 | 15 435 | |
| Rhodium | oz | 26 930 | 26 638 | 94 106 | 92 779 | |
| Ruthenium | oz | 45 486 | 44 716 | 158 940 | 155 680 | |
| Iridium | oz | 9 532 | 9 494 | 33 190 | 32 614 | |
| Total PGMs | oz | 355 330 | 358 316 | 1 257 684 | 1 245 923 | |
| Nickel10 | MT | 820 | 903 | 3 052 | 3 215 | |
| Copper10 | MT | 520 | 557 | 1 953 | 1 998 |
|
|
|
|
|
| 3 months | 3 months | 12 months | 12 months |
|
|
|
|
|
| to 30 Sep | to 30 Sep | to 30 Sep | to 30 Sep |
|
|
|
|
|
| 2018 | 2017 | 2018 | 2017 |
Refined | Lonmin refinedMetalProduction | Platinum | oz | 212 286 | 205 632 | 664 603 | 685 028 | ||
Production | Palladium | oz | 96 651 | 94 835 | 309 340 | 316 517 | |||
|
|
| Gold | oz | 5 376 | 5 563 | 17 324 | 18 017 | |
|
|
| Rhodium | oz | 32 326 | 28 108 | 100 136 | 100 677 | |
|
|
| Ruthenium | oz | 52 845 | 48 749 | 163 564 | 162 141 | |
|
|
| Iridium | oz | 11 578 | 8 914 | 34 634 | 33 654 | |
|
|
| Total PGMs | oz | 411 062 | 391 801 | 1 289 601 | 1 316 034 | |
|
|
| Toll refinedmetalproduction | Platinum | oz | 74 | 314 | 1 081 | 2 501 |
|
|
| Palladium | oz | 18 | 155 | 389 | 789 | |
|
|
| Gold | oz | 1 | 7 | 18 | 35 | |
|
|
| Rhodium | oz | 1 590 | 59 | 1 743 | 310 | |
|
|
| Ruthenium | oz | 78 | 137 | 623 | 926 | |
|
|
| Iridium | oz | 501 | 36 | 593 | 207 | |
|
|
| Total PGMs | oz | 2 262 | 707 | 4 448 | 4 768 | |
| TotalrefinedPGMs | Platinum | oz | 212 360 | 205 946 | 665 685 | 687 529 | ||
Palladium | oz | 96 670 | 94 990 | 309 729 | 317 306 | ||||
Gold | oz | 5 377 | 5 570 | 17 342 | 18 052 | ||||
|
|
| Rhodium | oz | 33 916 | 28 167 | 101 879 | 100 987 | |
|
|
| Ruthenium | oz | 52 923 | 48 885 | 164 187 | 163 067 | |
|
|
| Iridium | oz | 12 079 | 8 950 | 35 227 | 33 861 | |
|
|
| Total PGMs | oz | 413 325 | 392 508 | 1 294 049 | 1 320 802 | |
|
|
| BMR Concentrate Sales | Platinum | oz | 5 591 |
| 12 904 |
|
|
|
| (Saleable Refined | Palladium | oz | 2 416 |
| 5 756 |
|
|
|
| Production) | Gold | oz | 123 |
| 321 |
|
|
|
|
| Rhodium | oz | 810 |
| 1 903 |
|
|
|
|
| Ruthenium | oz | 1 252 |
| 3 034 |
|
|
|
|
| Iridium | oz | 316 |
| 653 |
|
|
|
|
| Total PGMs | oz | 10 509 |
| 24 570 |
|
|
|
| Total saleable refined | Platinum | oz | 217 951 | 205 946 | 678 558 | 687 529 |
|
|
| PGMs11 | Palladium | oz | 99 086 | 94 990 | 315 486 | 317 306 |
|
|
|
| Gold | oz | 5 500 | 5 570 | 17 663 | 18 052 |
|
|
|
| Rhodium | oz | 34 726 | 28 167 | 103 782 | 100 987 |
|
|
|
| Ruthenium | oz | 54 175 | 48 885 | 167 221 | 163 067 |
|
|
|
| Iridium | oz | 12 396 | 8 950 | 35 879 | 33 861 |
|
|
|
| Total PGMs | oz | 423 833 | 392 508 | 1 318 618 | 1 320 802 |
|
|
| Base metals | Nickel12 | MT | 1 085 | 1 022 | 3 605 | 3 502 |
|
|
|
| Copper12 | MT | 660 | 684 | 2 148 | 2 126 |
Sales | RefinedMetalSales | Platinum | oz | 212 119 | 218 687 | 668 676 | 706 030 | ||
|
|
| Palladium | oz | 96 548 | 104 549 | 311 019 | 324 273 | |
|
|
| Gold | oz | 4 772 | 4 989 | 17 580 | 16 675 | |
|
|
| Rhodium | oz | 34 620 | 29 312 | 103 128 | 107 742 | |
|
|
| Ruthenium | oz | 48 868 | 57 981 | 165 250 | 193 479 | |
|
|
| Iridium | oz | 9 508 | 10 682 | 33 485 | 33 212 | |
|
|
| Total PGMs | oz | 406 435 | 426 200 | 1 299 139 | 1 381 413 | |
|
|
|
| Nickel12 | MT | 1 126 | 1 031 | 3 558 | 3 770 |
|
|
|
| Copper12 | MT | 616 | 820 | 2 398 | 1 874 |
|
|
|
| Chrome12 | MT | 488 218 | 363 564 | 1 558 689 | 1 402 697 |
|
|
| BMR Concentrate Sales13 | Platinum | oz | 5 591 |
| 12 904 |
|
|
|
|
| Palladium | oz | 2 416 |
| 5 756 |
|
|
|
|
| Gold | oz | 123 |
| 321 |
|
|
|
|
|
|
| 3 months | 3 months | 12 months | 12 months |
|
|
|
|
|
| to 30 Sep | to 30 Sep | to 30 Sep | to 30 Sep |
|
|
|
|
|
| 2018 | 2017 | 2018 | 2017 |
|
|
| BMR Concentrate Sales13 | Rhodium | oz | 810 |
| 1 903 |
|
|
|
|
| Ruthenium | oz | 1 252 |
| 3 034 |
|
|
|
|
| Iridium | oz | 316 |
| 653 |
|
|
|
|
| Total PGMs | oz | 10 509 |
| 24 570 |
|
|
|
| Lonmin Platinum | Platinum | oz | 217 710 | 218 687 | 681 580 | 706 030 |
|
|
|
| Palladium | oz | 98 965 | 104 549 | 316 775 | 324 273 |
|
|
|
| Gold | oz | 4 895 | 4 989 | 17 901 | 16 675 |
|
|
|
| Rhodium | oz | 35 430 | 29 312 | 105 031 | 107 742 |
|
|
|
| Ruthenium | oz | 50 120 | 57 981 | 168 284 | 193 479 |
|
|
|
| Iridium | oz | 9 824 | 10 682 | 34 137 | 33 212 |
|
|
|
| Total PGMs | oz | 416 944 | 426 200 | 1 323 708 | 1 381 413 |
|
|
| Base metals | Nickel12 | MT | 1 126 | 1 031 | 3 558 | 3 770 |
|
|
|
| Copper12 | MT | 616 | 820 | 2 398 | 1 874 |
|
|
|
| Chrome12 | MT | 488 218 | 363 564 | 1 558 689 | 1 402 697 |
Average | Platinum |
| $/oz | 810 | 954 | 890 | 953 | ||
prices |
| Palladium |
| $/oz | 965 | 902 | 986 | 808 | |
|
|
| Gold |
| $/oz | 1 198 | 1 286 | 1 272 | 1 244 |
|
|
| Rhodium |
| $/oz | 2 376 | 1 063 | 1 988 | 915 |
|
|
| $ basket excl. by-product revenue14 | $/oz | 932 | 832 | 926 | 790 | |
|
|
| $ basket incl. by-product revenue15 | $/oz | 1 027 | 880 | 1 016 | 844 | |
|
|
| R basket excl. by-product revenue14 | R/oz | 13 191 | 10 966 | 12 245 | 10 526 | |
|
|
| R basket incl. by-product revenue15 | R/oz | 14 512 | 11 567 | 13 447 | 11 236 | |
|
|
| Nickel12 |
| $/MT | 11 300 | 8 289 | 10 875 | 8 274 |
|
|
| Copper12 |
| $/MT | 5 385 | 6 487 | 6 208 | 5 661 |
Unit Costs | Cost of Production per PGM ounce | R/oz | 11 617 | 11 524 | 12 271 | 11 701 | |||
ExchangeRates | Average rate for period16 |
| R/$ | 14.06 | 13.17 | 13.07 | 13.37 | ||
Closing rate |
| R/$ | 14.14 | 13.55 | 14.14 | 13.55 |
Notes |
|
|
|
|
|
|
|
|
|
|
1 | Reporting of shafts are in line with our operating strategy for Generation 1 and Generation 2 shafts. | |||||||||
2 | E3 Shaft and Pandora underground tonnes mined are reported as E3 Shaft Combined since 1 December 2017 when Lonmin required 100% of Pandora. | |||||||||
3 | Ounces mined have been calculated at achieved concentrator recoveries and with Lonmin standard downstream processing recoveries to present produced saleable ounces. | |||||||||
4 | Tonnes milled exclude slag milling. | |||||||||
5 | As from 1 December 2017 Lonmin owns 100% of Pandora joint venture and there will be no ore purchases thereafter. | |||||||||
6 | The BTT (Bulk Tailings Treatment) project was commissioned in February 2018. | |||||||||
7 | Head Grade is the grammes per tonne (5PGE + Au) value contained in the tonnes milled and fed into the concentrator from the mines (excludes slag milled). | |||||||||
8 | Recovery rate in the concentrators is the total content produced divided by the total content milled (excluding slag). | |||||||||
9 | Metals-in-concentrate are calculated at Lonmin standard downstream processing recoveries to present produced saleable ounces. | |||||||||
10 | Corresponds to contained base metals in concentrate. | |||||||||
11 | Saleable refined production includes production associated with BMR concentrate sales. | |||||||||
12 | Nickel is produced and sold as nickel sulphate crystals or solution and the volumes shown correspond to contained metal. Copper is produced as refined product but typically at LME grade C. Chrome is produced in the form of chromite concentrate and volumes shown are in the form of chromite. | |||||||||
13 | Includes saleable refined production associated with BMR concentrate sales. |
| ||||||||
14 | Basket price of PGMs is based on the revenue generated in Rand and Dollar from the actual PGMs (5PGE + Au) sold in the period based on the appropriate Rand/Dollar exchange rate applicable for each sale transaction. |
| ||||||||
15 | As per note 14 but including revenue from base metals. |
| ||||||||
16 | Exchange rates are calculated using the market average daily closing rate over the course of the period. |
|
Related Shares:
Lonmin