Q2 Production Report 2010

10th May 2010 07:00

RNS Number : 5905L
Lonmin PLC
10 May 2010
 



 

10 May 2010

Lonmin Plc

Second Quarter 2010 Production Report

 

Lonmin Plc, (Lonmin or the Company), the world's third largest PGM producer, today announces its production results for the three months to 31 March 2010 (unaudited).

 

Our core underground Marikana mining operations produced 2.6 million tonnes during the second quarter of the 2010 financial year, essentially in line with the same period last year, whilst tonnes milled from these operations were also flat with the prior year period at 2.5 million tonnes. Conventional operations at the property produced 2.1 million tonnes during the period, a decline of 0.1 million tonnes from the prior year period, mainly due to the planned closure of two decline shafts in 2009. Production from K3 shaft during the period was in line with the second quarter of 2009, however, the shaft suffered from significant Section 54 safety stoppages during the period. The impact of Section 54 safety stoppages across the Marikana property during the quarter was around 65,000 lost tonnes, which is better than the impact in the prior year period of 122,000 lost tonnes. Production at Saffy and Hossy shafts continued to ramp up during the second quarter of 2010, increasing by 41% over the prior year period.

 

As highlighted in November 2009, we re-commenced production at a Merensky opencast pit at Marikana at the end of the period. Pandora underground production increased by 6% during the second quarter of 2010 from the prior year period.

 

Due to the planned closures of opencast operations at our Marikana property and the Pandora joint venture in 2009, total tonnes mined from our operations for the second quarter of the 2010 financial year declined 2% year-on-year to 2.6 million. Total tonnes milled were down more, at 8%, to 2.5 million tonnes, as a result of opencast stock piles being milled in the prior year period.

 

Platinum in concentrate from our Marikana operations was 154,578 saleable ounces during the second quarter of 2010, increasing by 2% from the prior year period. This was due to achieving better levels of grade and concentrator recoveries during the quarter compared to the prior year period. In total the concentrators produced 160,019 saleable ounces of Platinum in concentrate for the quarter, a 3% decrease from the second quarter of the prior year, due to the impact of closing the Pandora opencast operations in 2009.

 

Underground milled head grade was up to 4.74 grammes per tonne (5PGE+Au), from 4.69 grammes per tonne (5PGE+Au), having been sustained from the first quarter of 2010. This was a result of a number of factors including cleaner mining across the property, a better ratio of stoping to development material at Hossy and Saffy as well as a better ore mix.

 

Underground concentrator recoveries improved slightly to 84.7% from 84.5% in the first quarter of the 2010 financial year but were up significantly from the 81.4% achieved in the second quarter of 2009. This was as a result of the factors impacting head grade and due to continued benefits from our concentrator optimisation programme, excellent plant availability and a rigorous focus on batch milling the right ore through the right concentrators.

 

Refined production for the second quarter of 2010 declined by 2% to 181,135 ounces of Platinum and 344,036 ounces of total PGMs. Metal sales during the second quarter of the 2010 financial year declined by 1% to 182,878 ounces of Platinum and 353,844 ounces of PGMs.

 

Lonmin Plc also publishes today, in a separate announcement, its Interim Results for the half year ending 31 March 2010.

 

ENQUIRIES:

Investors / Analysts:

Tanya Chikanza +44 (0) 207 201 6000

Acting Head of Investor Relations

 

Media:

Cardew Group +44 (0) 207 930 0777

Rupert Pittman / James Milton

 

Financial Dynamics +27 (0) 21 487 9000

Dani Cohen / Ravin Maharaj

 

3 months to

3 months to

31 Mar 2010

31 Mar 2009

Actual

Actual

Tonnes mined

Marikana

Underground - total

000

2,572

2,584

Underground - conventional

000

2,128

2,269

Underground - Hossy & Saffy1

000

444

315

Opencast

000

7

13

Total

000

2,579

2,598

Pandora

Underground

000

39

37

attributable2

Opencast

000

-

41

Total

000

39

78

Lonmin Platinum

Underground

000

2,611

2,621

Opencast

000

7

55

Total

000

2,618

2,676

Tonnes milled3

Marikana

Underground

000

2,453

2,462

Opencast

000

-

78

Total

000

2,453

2,540

Pandora4

Underground

000

78

88

Opencast

000

-

126

Total

000

78

214

Lonmin Platinum

Underground

000

2,531

2,550

Head grade5

g/t

4.74

4.69

Recovery rate6

%

84.7%

81.4%

Opencast

000

-

205

Head grade5

g/t

0.00

4.61

Recovery rate6

%

0.0%

71.3%

Total

000

2,531

2,754

Head grade5

g/t

4.74

4.68

Recovery rate6

%

84.7%

80.6%

 

3 months to

3 months to

31 Mar 2010

31 Mar 2009

Actual

Actual

Metals in concentrate7

Marikana

Platinum

oz

154,578

151,168

Palladium

oz

72,579

70,285

Gold

oz

3,129

3,444

Rhodium

oz

22,124

21,191

Ruthenium

oz

33,543

32,617

Iridium

oz

7,353

7,110

Total PGMs

oz

293,306

285,815

Nickel8

MT

615

642

Copper8

MT

377

405

Pandora3

Platinum

oz

5,441

13,742

Palladium

oz

2,531

6,194

Gold

oz

37

110

Rhodium

oz

871

1,909

Ruthenium

oz

1,289

2,789

Iridium

oz

224

515

Total PGMs

oz

10,394

25,259

Nickel8

MT

8

13

Copper8

MT

5

8

Lonmin Platinum

Platinum

oz

160,019

164,909

Palladium

oz

75,110

76,479

Gold

oz

3,166

3,554

Rhodium

oz

22,995

23,100

Ruthenium

oz

34,832

35,406

Iridium

oz

7,577

7,625

Total PGMs

oz

303,700

311,074

Nickel8

MT

623

655

Copper8

MT

381

412

 

3 months to

3 months to

31 Mar 2010

31 Mar 2009

Actual

Actual

Metallurgy

Lonmin refined

Metal Production12

Platinum

oz

180,956

184,969

Palladium

oz

79,325

86,637

Gold

oz

4,028

5,151

Rhodium

oz

21,381

25,939

Ruthenium

oz

47,117

47,614

Iridium

oz

10,502

9,935

Total PGMs

oz

343,310

360,245

Toll refined metal production

Platinum

oz

179

315

Palladium

oz

63

-

Gold

oz

-

-

Rhodium

oz

485

573

Ruthenium

oz

-

1,009

Iridium

oz

-

184

Total PGMs

oz

727

2,081

Total refined PGMs

Platinum

oz

181,135

185,284

Palladium

oz

79,388

86,637

Gold

oz

4,028

5,151

Rhodium

oz

21,866

26,512

Ruthenium

oz

47,117

48,623

Iridium

oz

10,502

10,119

Total PGMs

oz

344,036

362,326

Base metals

Nickel9

MT

883

869

Copper9

MT

526

579

Sales

Refined Metal Sales

Platinum

oz

182,878

187,250

Palladium

oz

81,783

92,439

Gold

oz

5,393

5,940

Rhodium

oz

22,039

21,636

Ruthenium

oz

50,360

41,833

Iridium

oz

11,390

9,392

Total PGMs

oz

353,844

358,490

Concentrate and other10

Platinum

oz

-

(1,600)

Palladium

oz

-

(1,822)

Gold

oz

-

-

Rhodium

oz

-

-

Ruthenium

oz

-

-

Iridium

oz

-

-

Total PGMs

oz

-

(3,421)

Lonmin Platinum

Platinum

oz

182,878

185,651

Palladium

oz

81,783

90,617

Gold

oz

5,393

5,940

Rhodium

oz

22,039

21,636

Ruthenium

oz

50,360

41,833

Iridium

oz

11,390

9,392

Total PGMs

oz

353,844

355,069

Nickel9

MT

814

693

Copper9

MT

523

503

 

3 months to

3 months to

31 Mar 2010

31 Mar 2009

Actual

Actual

Average prices

Platinum

$/oz

1,535

991

Palladium

$/oz

432

195

Gold

$/oz

1,110

901

Rhodium

$/oz

2,467

1,099

Ruthenium

$/oz

173

47

Iridium

$/oz

447

384

Basket price of PGMs11

$/oz

1,103

666

Basket price of PGMs11

R/oz

8,432

6,631

Nickel9

$/MT

15,309

16,285

Copper9

$/MT

6,404

6,953

Exchange Rates

Average rate for period13

R/$

7.49

9.90

Closing rate

R/$

7.28

9.49

 

Footnotes:

1

Hossy and Saffy are replacement/growth shafts in ramp up. Hossy is fully mechanised whilst Saffy has conventional stoping but mechanised development. In previous production reports this section showed all M&A/Hybrid mining. All comparatives have been restated.

2

Pandora attributable tonnes mined includes Lonmin's share (42.5%) of the total tonnes mined on the Pandora joint venture.

3

Tonnes milled excludes slag milling.

4

Lonmin purchases 100% of the ore produced by the Pandora joint venture for onward processing which is included in downstream operating statistics.

5

Head grade is the grammes per tonne (5PGE + Au) value contained in the tonnes milled and fed into the concentrator from the mines (excludes slag milled).

6

Recovery rate in the concentrators is the total content produced divided by the total content milled (excluding slag).

7

Metals in concentrate include metal derived from slag processing and have been calculated at industry standard downstream processing losses to present produced saleable ounces.

8

Corresponds to contained base metals in concentrate.

9

Nickel is produced and sold as nickel sulphate crystals or solution and the volumes shown correspond to contained metal. Copper is produced as refined product but typically at LME grade C.

10

Concentrate and others sales essentially relates to BMR concentrate and BMR/PMR residues.

11

Basket price of PGMs is based on the revenue generated from the actual PGMs (5PGE + Au) sold in the period.

12

Lonmin refined metal production and sales include an estimated 3,000 oz saleable ounces of Platinum produced from toll refining third party concentrate (Q2 2009 - nil).

13

Exchange rates are calculated using the market average daily closing rate over the course of the period.

 

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCLKLLBBEFBBBZ

Related Shares:

Lonmin
FTSE 100 Latest
Value8,684.56
Change50.81