Q1 2016 Preliminary Production Results

7th Apr 2016 07:00

RNS Number : 4240U
Centamin PLC
07 April 2016
 

For immediate release

7th April 2016

Centamin plc ("Centamin" or "the Company")

(LSE:CEY, TSX:CEE)

 

Q1 2016 Preliminary Production Results

 

Centamin is pleased to announce preliminary production results for the quarter ended 31 March 2016 from its Sukari Gold Mine ("Sukari") in Egypt.

 

Preliminary total gold production for the quarter was 125,268 ounces, a 6.5% increase on the previous quarter and a 15.7% increase on Q1 2015. Full year production guidance of 470,000 ounces is maintained.

 

Quarterly throughput at the process plant was 2,876kt, a 4.3% increase on the previous quarter and above our base case target rate of 11 million tonnes per annum (Mtpa).

 

Open pit total material movement increased 10.2% on the previous quarter to 15,157kt, with open pit ore production increasing by 7.9% to 2,405kt. The run of mine ore stockpile balance decreased by 213kt to 491kt at the end of the period.

 

The underground operation delivered 281kt of ore, a 6.3% decrease on the previous quarter but remaining above our forecast production rate of 1 million tonnes per annum.

 

Q1 2016 (preliminary)

Q4 2015

Q1 2015

Open Pit - Total Material Movement (kt)

15,157

13,754

15,996

Open Pit - Ore Production (kt)

2,405

2,229

2,562

Underground Ore Production (kt)

281

300

264

Process Plant Throughput (kt)

2,876

2,758

2,478

Process Plant Productivity (tph)

1,421

1,345

1,286

Gold Produced (oz)

125,268

117,644

108,233

 

Andrew Pardey, CEO of Centamin, commented:

 

"These production results reflect a solid start to the year for Sukari and support our forecast 2016 production of 470,000 ounces of gold. The processing operation was a highlight and the key driver of the quarterly increase in output, with throughput rising above our base case forecast rate of 11Mt per annum. The open pit delivered an increase in material movement over the previous quarter and the underground mine continues to deliver production rates in excess of our base case forecast. With quarterly production rates expected to remain within the 450,000 to 500,000 ounces per annum range, our full year guidance remains unchanged at 470,000 ounces. Continuing optimisation of the expanded Sukari processing and mining operations supports the potential for further productivity increases over the coming quarters."

 

For more information, please contact:

 

Centamin plc

Josef El-Raghy, Chairman

Andrew Pardey, CEO

Andy Davidson, Head of Investor Relations

([email protected]) +44 (0) 1534 828708

 

Buchanan

Bobby Morse, Robbie Ceirog-Hughes

+ 44 (0) 20 7466 5000

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCIFMFTMBTMBPF