Project Update

8th Jul 2011 14:18

RNS Number : 0748K
Herencia Resources PLC
08 July 2011
 



Herencia Resources plc

("Herencia" or the "Company")

 

Project Update

 

Herencia wishes to advise on the status of its Paguanta Project (Herencia 70% owner) and the Guamanga Project (Herencia earning 51%), located in northern Chile.

·; Earlier this week the region around Paguanta experienced unusually high snowfall (snow is not common at Paguanta) with the site itself receiving approximately 30cm. The snowfall has resulted in regional road closures, including access roads to the project site. In light of this the Company has suspended site work and withdrawn all personnel until permanent road access is re-established. We will advise when site activity resumes which we anticipate will be in the next 14-21 days.

·; Work on the Patricia Feasibility Study continues.

·; The snow fall has not affected the region around the Guamanga Project and site work is continuing, with geologists having commenced field mapping earlier this week.

 

For further information, please contact:

Michael Bohm, Herencia Resources plc

+61 8 9481 4204

Katy Mitchell, WH Ireland Limited

+44 161 832 2174

Simon Courtenay, Broker Profile

+44 207 448 3244

 

Further background details on the Company can be found at www.herenciaresources.com

**ENDS**

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCDKFDDNBKDOOK

Related Shares:

Herencia Resources
FTSE 100 Latest
Value8,275.66
Change0.00