PROGRESS REPORT

5th Apr 2011 07:00

RNS Number : 2784E
Patagonia Gold PLC
05 April 2011
 



PATAGONIA GOLD PLC

 

  5th April 2011

 

PROGRESS REPORT

LOMADA GOLD PROJECT

SANTA CRUZ PROVINCE, ARGENTINA

 

Highlights:

 

·; Final preparations for the commissioning of the Lomada Trial Heap leach project are nearing completion. Irrigation for conditioning of the ore pad is scheduled to commence on the 10th April with handover of the commissioned process facility by the construction company, INFA, scheduled for the 25th April.

 

·; Initial results from the recently completed extension and infill drilling campaign on the Lomada deposit are highly encouraging, including drill hole LLD10-17 intersecting 18 metres at 10.95 grams per tonne gold . A Resource and Scoping study upgrade is in progress with completion anticipated in Q2.

 

Lomada de Leiva project:

The Lomada de Leiva gold-heap leach project (Lomada project) is located on the La Paloma property block approximately 40km to the south of the town of Perito Moreno and currently contains a Canadian National Instrument 43-101 (NI 43-101) compliant resource of 161,346 ounces of gold in the measured and indicated categories with a further inferred 73,725 ounces of gold.

 

The first stage of the Lomada project consists of a 50,000 tonne trial heap leach pad and processing facility, which based on 70% recovery, is estimated to yield approximately 2,500 ounces of gold for the first 6 metre loading.

 

Work on the Lomada project commenced in late September 2010. All sections of works are now complete with the exception of the processing facility, the commissioning of which will commence next week, with handover by the construction company, INFA, scheduled for the 25th April.

 

All staff and operators have been hired and are currently undergoing training in the safe use and operation of the facilities and equipment on site. Power generators, fuel and water storage together with other ancillary items have been installed and are in operation. Sufficient reagents and consumables have been purchased for the anticipated life of the Lomada project.

 

Full operation of the Lomada project will commence soon after the commissioning of the processing plant with the first production of gold expected in early May.

 

Updated images of the Lomada project can be viewedon the website, www.patagoniagold.com 

 

 

Subject to successful leaching and additional permitting, further loading and production from the first stage heap leach will continue until the main 5 million tonne heap leach project is fully operational.

 

Lomada Resource Upgrade:

Patagonia Gold SA (PGSA) has recently completed an extension and infill drilling campaign, comprising 35 diamond drill holes HQ core for 4,441 metres, aimed at enlarging the resource and advancing the inferred part of the resource into an indicated category. Results received to date are highly encouraging and include:

 

Hole No.

From

To

Interval

Grade

metres

metres

metres

Au g/t

LLD-10-01

93.00

99.00

6.00

11.22

including

95.00

97.00

2.00

20.30

LLD-10-03

71.00

85.00

14.00

5.67

LLD-10-14

54.00

74.00

20.00

6.86

including

60.00

67.00

7.00

14.52

LLD-10-15

97.00

112.00

15.00

3.91

including

100.00

105.00

5.00

7.62

LLD-10-17

61.00

79.00

18.00

10.95

including

73.00

78.00

5.00

27.14

LLD-10-24

98.00

107.00

9.00

4.37

 

Table 1: Lomada Project table of significant Intercepts 2010/11 DDH extension and infill.

 

PGSA has retained Mining Engineers, Chlumsky, Armbrust and Meyer, LLC (CAM) of Lakewood, Colorado, to prepare a NI 43-101 report for the upgrade of the resource at Lomada, scheduled for completion in Q2, 2011.

 

The upgraded resource, together with the results from the trial Lomada project, will be used to revise the 2009 Scoping study of the Lomada project prior to the commencement of the main heap leach project.

 

Matthew Boyes, (BSC. Geology, member AusIMM) Development Manager for Patagonia Gold PGSA and a qualified person as defined in Canadian National Instrument 43-101, has reviewed and verified all scientific or technical mining disclosure contained in this press release.

 

ENDS

 

For more information, please contact:

Bill Humphries/Richard Prickett

Patagonia Gold Plc

Tel: +44(0)20 7409 7444

 

Simon Raggett / Angela Peace

Strand Hanson Ltd

Tel: +44(0)20 7409 3494

David Bick / Mark Longson

Square 1 Consulting

Tel : +44(0)20 7929 5599

 

Robin Henshall / Tim Graham

Matrix Corporate Capital LLP

Tel : +44(0)20 3206 7172 / +44(0)20 3206 7206

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
DRLSSUFMLFFSESL

Related Shares:

Patagonia Gold
FTSE 100 Latest
Value8,275.66
Change0.00