10th Sep 2012 07:00
10 September 2012
Great Eastern Energy Corporation Limited
("Great Eastern" or "the Company")
Operational update
Great Eastern Energy Corporation Limited (LSE: GEEC), the fully integrated, leading Indian Coal Bed Methane (CBM) company, is pleased to provide the following operational update:
Raniganj (South) Block:
·; Production currently running at 11.2 mmscfd (25 June 2012, 9.8 mmscfd) up 14.3%
·; A total of 128 wells drilled to date; including 29 deviated wells (25 June 2012, 121 wells)
·; 111 wells fractured (25 June 2012, 98 wells)
·; 11 deviated wells producing gas
Outlook:
Prashant Modi, President and COO of Great Eastern, said:
"Great Eastern continues to make good progress. Deployment of the second rig at Raniganj is accelerating fracturing, production is increasing as planned, and we are on track to achieve our target of completing 40 wells per year."
For further information please contact:
Andrew Benbow |
Related Shares:
GEEC.L