MATILDA GOLD PRODUCTION COMMENCES

12th Oct 2016 12:04

RNS Number : 3703M
Polo Resources Limited
12 October 2016
 

12 October 2016

 

 

 

Polo Resources Limited

 ("Polo" or the "Company")

 

MATILDA GOLD PRODUCTION COMMENCES

Polo Resources Limited (AIM: POL), the natural resources investment company with interests in oil, gold, coal, copper, phosphate, iron and vanadium, is pleased to announce that Blackham Resources Limited ("Blackham") ("ASX: BLK") has reported that gold production has commenced from its 5.1Moz Matilda Gold Project. The CIL tanks are operational and milling of ore has commenced. Commissioning is also underway on the gravity circuit, elution circuit, and gold room.

 

During the September quarter 1.57 million BCM's of material were mined. Mining focused on removal of overburden to open up ore sources from both the Matilda M10 and M3 pits. Ore mined to date is lower grade ore as expected from the laterite and depletion zones at the top of the pits. The M10 pit is now approaching the main higher grade structure.

Open Pit Mining for Quarter

Ore

t

46,886

Ore

BCM

22,327

Au

g/t

0.7

Waste

BCM

1,650,797

Total Material

BCM

1,708,223

 

Underground mining for the quarter focused on lateral development around the old Golden Age stopes. There are currently three jumbos on site focused on development and rehabilitation activities. Development ore is currently being mined from three development headings. Initial Golden Age development ore produced was 20% higher than expected. Visible gold has also been sighted on the 980 development level.

Underground Mining for Quarter

Ore Mined

T

1,720

Au Grade Mined

g/t

4.4

Total Lateral development

M

517

 

Mining from the open pits, underground and existing stockpiles has resulted in gold stockpiles of 172,000t @ 1.4g/t for 7,900oz available for milling. Current stockpiles represent over a full month of production.

 

With milling of ore having commenced, gold in circuit is accumulating and first gold pour is now expected within days. Blackham is focused on a safe, efficient and timely ramp up to commercial production.

The full details of Blackham's announcements can be found at www.blackhamresources.com, including a competent person's statement (JORC 2012) in respect of the Matilda Gold Project Resource Summary.

This announcement contains inside information as defined in Article 7 of the EU Market Abuse Regulation No 596/2014 and has been announced in accordance with the Company's obligations under Article 17 of that Regulation.

 

For further information, please contact:

Polo Resources Limited

Kudzayi Denenga, Investor Relations

+ 27 (0) 787 312 919

ZAI Corporate Finance Ltd (nominated adviser)

Ray Zimmerman, John Treacy

 

+44 (0) 20 7060 2220

Liberum Capital (broker)

Henry Freeman

+44 (0) 20 3100 2000

 

Blytheweigh (public relations)

Tim Blythe, Nick Elwes, Camilla Horsfall

+44 (0) 207 138 3204 

 

 

About the Company

Polo Resources Limited is a natural resources investment company focused on investing in undervalued companies and projects with strong fundamentals and attractive growth prospects. For further details on Polo, please refer to: www.poloresources.com. 

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 