Korean Recycling Plant Commissioning Update

2nd Apr 2012 07:00

RNS Number : 5470A
ZincOx Resources PLC
02 April 2012
 
Date:2 April 2012
On behalf of:ZincOx Resources plc ('ZincOx')
Embargoed until:0700hrs

 

 

 

 

ZincOx Resources plc

 

Korean Recycling Plant Commissioning Update

 

ZincOx Resources plc, which specialises in the recovery of zinc concentrate from steel industry waste, announces that its wholly owned Korean Recycling Plant is in the final stages of commissioning and is confident that the plant will be operational within two weeks, narrowly outside of the original schedule set 18 months ago.

 

For the purposes of commissioning, the plant has been divided into two zones. Zone 1 includes EAFD unloading, coal pulverization, binder preparation, briquetting, drying and screening. Commissioning of Zone 1 is complete and briquettes have been tested in the plant's laboratory. These tests have shown that the briquettes are of excellent quality and after heating demonstrated high zinc removal and iron metallisation. Over 600 tonnes of briquettes have been produced and are waiting to feed the furnace.

 

 

Zone 2 includes the rotary hearth furnace ("RHF"), gas handling system and hot briquetting tower. The RHF has been operated in a cold state with good briquette loading and discharge and is ready for production. The gas handling system which has undergone its final testing of emergency systems, is ready for operation. The hot briquetting tower is awaiting hot DRI for final commissioning. The burners on the RHF are being tuned and then the furnace will be gradually heated up over a two day period, ahead of the commencement of production.

 

All staff for the operation have been recruited and trained.

 

Commenting on the announcement, Andrew Woollett, ZincOx's Chairman, said:

 

"We set ourselves an ambitious development schedule when we started this project 18 months ago so notwithstanding the very fast track approach taken in this development, I am delighted to report that the project has, to date, been developed within budget and without a single lost time injury. I look forward to reporting the start of production within a fortnight."

 

 

 

 

 

Enquiries:

ZincOx Resources plc

Tel: +44 (0)1276 450 100

Andrew Woollett, Executive Chairman

Peel Hunt LLP (Nominated Adviser and Joint Broker)

Tel: +44 (0)20 7418 8900

Richard Kauffer

Daniel Harris

 

finnCap Limited (Joint Broker)

Matthew Robinson

Joanna Weaving

 

Tel: +44 (0)20 7220 0500

Tavistock Communications

Tel: +44 (0)20 7920 3150

Paul Youens

Simon Hudson

Lydia Eades

 

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCSSDFUFFESEIL

Related Shares:

Zincox Resources Plc
FTSE 100 Latest
Value8,275.66
Change0.00