30th Jun 2016 07:00
BMR Group PLC
("BMR" or the "Company")
Kabwe Project Update and Activities
BMR, the Zambian-focused mineral processing business, notes the weakness in its share price during June 2016 and announces that the Board is not aware of any developments within the business that may have caused this.
The Board sets out below an update on the Company's current activities.
Product Off Take Sale and Purchase Agreement
The Board is pleased to announce that negotiations are proceeding well with the private South African group engaged in mining, energy and agri-business concerning a US$2 million facility for the construction of the plant at Kabwe ("Plant") and the related sale and purchase agreement, for the sale of agricultural grade zinc sulphate heptahydrate (ZSH) (500 tpm) and lead sponge (300 tpm).
Plant Construction
Civil works to the floor space in the old mine concentrator building in preparation for the construction of the Plant are well advanced. In the meantime, BMR has started placing orders for locally manufactured items for the leach/precipitation section. The main 90 m3 sulphuric acid storage tank has been acquired and is in place. Plant design optimisation has resulted in standardising tank sizes for leach/precipitation/zinc re-leach and lead leach sections. Similarly in the zinc Solvent Extraction (SX) circuit, optimisation of the extraction and stripping phases has resulted in a reduction in the tank sizes. This will result in a modest reduction in plant capital costs. The expected Plant commissioning date for the commencement of production remains on schedule, for early 2017.
Geological Potential of the Kashitu area
Preliminary work has started on the evaluation of the Kashitu area following the collection of all available historic drilling and ground magnetic data. A pitting and trenching programme will commence in August 2016 to follow up historical anomalies plus additional exploration to extend our knowledge of this section of our Large Scale mining licence.
ZEMA
A programme to establish baseline studies for monitoring air, ground water and personal health in compliance with the conditions set out by ZEMA following their approval to build the Plant has been agreed with J A Consultancy. This work will commence shortly and take between 6 and 8 weeks to complete.
A decision is awaited from ZEMA for the EPB submitted by BMR to sell the Waelz Kiln slag. ZEMA have advised that the earliest likely date for this approval will be the end of July 2016. The delay has been due to internal re-organization of their managing committee responsible for approving such applications.
Alex Borrelli, Chairman, commented: "We continue to make good progress towards the key sale and purchase agreement for zinc sulphate heptahydrate and lead sponge from our Plant and look forward to confirming this by the end of July 2016."
Ends
For further information:
BMR Group PLC
020 7734 7282 Alex Borrelli, CEO and Chairman
WH Ireland Limited 020 7220 1666
NOMAD and Joint Broker Chris Fielding, Head of Corporate Finance
Peterhouse Corporate Finance 020 7469 0930
Joint Broker Lucy Williams/ Duncan Vasey/ Heena Karani
Related Shares:
Berkeley Mineral Resources