Fourth Quarter 2013 Production Report

11th Nov 2013 07:00

RNS Number : 6381S
Lonmin PLC
11 November 2013
 



 

 

 

 

 

 

 

 

 

REGULATORY RELEASE

 

 

11 November 2013

 

Fourth Quarter 2013 Production Report

 

Lonmin Plc ("Lonmin" or "the Company"), the world's third largest Platinum producer, today announces its production results for the three months to 30 September 2013. Lonmin also publishes today, in a separate announcement, its final results for the year ended 30 September 2013.

 

Overview

 

The positive trend of our rolling 12 month average Lost Time Injury Frequency Rate (LTIFR) continued and LTIFR for 2013 was 3.50 incidents per million man hours compared to 3.55 at the end of June 2013 and 4.16 for 2012. Regrettably one of our colleagues, Ayanda Dziliyana,was fatally injured in August at Saffy shaft and we extend our sympathies to his family and friends.

 

We maintained the overall operational momentum built since the labour disruptions and achieved an impressive performance in the fourth quarter with 3.2 million attributable tonnes being mined reflecting an improvement of 9.5% against Q3 2013. This represents an increase of 1.5 million tonnes or 94.0% on the prior year period when production was affected by the labour unrest and Events at Marikana. Total tonnes lost in Q4 due to Section 54 safety stoppages, management induced safety stoppages (MISS) and industrial relations issues were 69,000 tonnes less than Q3. Momentum was interrupted in August following the fatality at Saffy shaft and the associated safety stoppage but the operations recovered resulting in the exceptional performance.

 

During the quarter, we produced total Platinum metal in concentrate of 198,428 ounces reflecting an improvement of 6.4% against Q3. Platinum sales were 288,280 ounces driven by good smelter performance in the quarter after the Number Two furnace forced shut down in Q3. For the financial year 2013 we achieved 750,942 ounces of Platinum metal in concentrate, the highest amount since 2007. Refined production of 709,029 Platinum ounces were lower as a result of refilling the pipeline and a stock build-up following the smelter incident at Number Two furnace which occurred during the planned shut down of the Number One furnace for maintenance. We sold 695,803 Platinum ounces during the financial 2013 year.

 

Mining Division

 

Our underground mining operations produced 3.0 million tonnes during the fourth quarter, an increase of 1.5 million tonnes or 101.0% more than the prior year period. The comparative numbers were negatively affected by the Events at Marikana during the prior year period. Production from our Merensky opencast operations was comparable to the prior year period. Pandora attributable production increased by 43,000 tonnes, or 171.4% on the prior year period following labour disruptions in 2012.

 

Production at Karee increased by 686,000 tonnes, up 105.0% on the prior year period and 12.9% compared to Q3. K4 was placed on care and maintenance at the beginning of the year having produced 22,000 tonnes in Q4 2012.

 

Similarly production at Westerns increased by 414,000 tonnes, or 108.9% on the prior year period and 15.1% against the previous quarter. Output from Rowland shaft increased by 20.8% or 86,000 tonnes compared to Q3 as the operations regained momentum following the fatal accident in April and Section 54 safety stoppage. The preliminary work around the de-bottlenecking project has started to deliver positive returns and the ore reserve position has been improved. Newman increased by 16,000 tonnes, or 7.0% compared to Q3.

 

Production at Middelkraal continued to increase, and was 296,000 tonnes or 96.1% more than the prior year. The quarter on quarter increase was, however, only 4.4% as the momentum established at Saffy was impacted by a Section 54 safety stoppage which resulted in a loss of 89,000 tonnes following the fatal accident on 14 August.

 

Production at Easterns increased by 92,000 tonnes over the prior year period. The planned depletion of East 1 shaft continues as it approaches the end of its life.

 

In total, 165,000 tonnes of production were lost during the quarter, of which 105,000 tonnes related to Section 54 safety stoppages, 9,000 tonnes to MISS and an additional 51,000 tonnes was due to labour stoppages. This compared to a total of 1,822,000 tonnes lost in the prior year period of which 26,000 tonnes were due to Section 54 safety stoppages, 2,000 tonnes were due to MISS and 1,794,000 tonnes were due to strike action.

 

Process Division

 

Total tonnes milled in the quarter increased by 1.4 million tonnes or 85.2% to 3.1 million tonnes with underground 92.4% higher than the prior year period and opencast down 27.2%.

 

Underground milled head grade decreased slightly by 3.0% to 4.55 grammes per tonne (5PGE+Au) when compared to 4.69 grammes per tonne in the prior year period and remains within our expected grade range. The overall milled head grade was 4.51 grammes per tonne, a decrease of 1.7% on the prior year period.

 

Underground and overall concentrator recoveries for the quarter increased by 0.9 percentage points to 87.6% when compared to the prior year and 1.0 percentage point versus Q3 2013. These are record achievements.

 

Platinum in concentrate from the Marikana operations for the quarter was 186,332 saleable ounces, an 81.2% increase on the prior year period and an increase of 6.7% on Q3. Total Platinum in concentrate at 198,428 ounces was 82.4% higher than the prior year period. The increases were a consequence of the increase in ore mined.

 

Total refined production for the fourth quarter was up 38.5% to 271,773 ounces of saleable Platinum when compared against the prior year period. Total Platinum Group Metals (PGMs) produced in the fourth quarter were 493,110 ounces, an increase of 24.4% on the prior year period reflecting the longer lead time for extracting non-Platinum PGMs. Both furnaces were running during the quarter and high smelting rates were achieved as the build-up in pipeline stock during the third quarter was processed.

 

Sales & Pricing

 

Platinum sales for the quarter were up 23.7% to 288,280 ounces and PGM sales were up 9.1% to 519,222 ounces. The US dollar basket price (excluding base metal credit) at $1,058 per ounce during the quarter was broadly flat on the prior year period while the corresponding Rand basket price was 21.7% higher than the prior quarter on the back of Rand weakness.

 

- ENDS -

 

ENQUIRIES

 

Investors / Analysts:

Lonmin

Tanya Chikanza (Head of Investor Relations)

+27 11 218 8358 /

+44 20 7201 6007

 

Media:

Cardew Group

James Clark / Emma Crawshaw

 

+44 20 7930 0777

Sue Vey

+27 72 644 9777

 

Notes to editors

 

Lonmin, which is listed on both the London Stock Exchange and the Johannesburg Stock Exchange, is one of the world's largest primary producers of PGMs. These metals are essential for many industrial applications, especially catalytic converters for internal combustion engine emissions, as well as their widespread use in jewellery.

 

Lonmin's operations are situated in the Bushveld Igneous Complex in South Africa, where nearly 80% of known global PGM resources are found.

 

The Company creates value for shareholders through mining, refining and marketing PGMs and has a vertically integrated operational structure - from mine to market. Underpinning the operations is the Shared Services function which provides high quality levels of support and infrastructure across the operations.

 

For further information please visit our website: http://www.lonmin.com

 

3 months

3 months

to 30 Sep

to 30 Sep

2013

2012

Tonnes mined

Marikana

Karee1

kt

1,340

654

Westerns1

kt

793

380

Middelkraal1

kt

605

308

Easterns1

kt

242

150

Underground

kt

2,980

1,491

Opencast

kt

113

113

Total

kt

3,093

1,604

Pandora attributable2

Underground

kt

68

25

Lonmin Platinum

Underground

kt

3,048

1,516

Opencast

kt

113

113

Total

kt

3,161

1,629

% UG2

%

73.7%

71.0%

Tonnes milled3

Marikana

Underground

kt

2,911

1,523

Opencast

kt

74

102

Total

kt

2,985

1,625

Pandora4

Underground

kt

160

72

Lonmin Platinum

Underground

kt

3,071

1,596

Head grade5

g/t

4.55

4.69

Recovery rate6

%

87.6%

86.7%

Opencast

kt

74

102

Head grade5

g/t

2.93

3.06

Recovery rate6

%

85.0%

86.9%

Total

kt

3,145

1,698

Head grade5

g/t

4.51

4.59

Recovery rate6

%

87.6%

86.7%

 

3 months

3 months

to 30 Sep

to 30 Sep

2013

2012

Metals in concentrate7

Marikana

Platinum

oz

186,332

102,822

Palladium

oz

86,945

47,685

Gold

oz

4,499

2,730

Rhodium

oz

25,648

13,265

Ruthenium

oz

38,329

21,532

Iridium

oz

8,801

4,688

Total PGMs

oz

350,554

192,721

Nickel8

MT

950

554

Copper8

MT

607

352

Pandora4

Platinum

oz

11,213

5,068

Palladium

oz

5,345

2,368

Gold

oz

86

38

Rhodium

oz

1,812

778

Ruthenium

oz

2,667

1,228

Iridium

oz

479

207

Total PGMs

oz

21,602

9,687

Nickel8

MT

21

9

Copper8

MT

12

5

Concentrate purchases

Platinum

oz

883

905

Palladium

oz

272

329

Gold

oz

5

4

Rhodium

oz

109

104

Ruthenium

oz

105

132

Iridium

oz

45

39

Total PGMs

oz

1,418

1,513

Nickel

MT

1

0

Copper

MT

1

0

Lonmin Platinum

Platinum

oz

198,428

108,795

Palladium

oz

92,562

50,382

Gold

oz

4,589

2,772

Rhodium

oz

27,569

14,146

Ruthenium

oz

41,101

22,892

Iridium

oz

9,325

4,934

Total PGMs

oz

373,574

203,921

Nickel8

MT

972

564

Copper8

MT

619

358

 

3 months

3 months

to 30 Sep

to 30 Sep

2013

2012

Refined production

Lonmin refined metal production

Platinum

oz

271,773

178,158

Palladium

oz

122,904

89,857

Gold

oz

7,081

5,006

Rhodium

oz

21,651

44,096

Ruthenium

oz

61,982

38,675

Iridium

oz

6,286

8,475

Total PGMs

oz

491,677

364,269

Toll refined metal production

Platinum

oz

-

18,021

Palladium

oz

-

8,564

Gold

oz

-

48

Rhodium

oz

-

263

Ruthenium

oz

1,333

4,224

Iridium

oz

100

939

Total PGMs

oz

1,433

32,058

Total refined PGMs

Platinum

oz

271,773

196,179

Palladium

oz

122,904

98,421

Gold

oz

7,081

5,054

Rhodium

oz

21,651

44,359

Ruthenium

oz

63,315

42,900

Iridium

oz

6,386

9,414

Total PGMs

oz

493,110

396,327

Base metals

Nickel9

MT

1,224

921

Copper9

MT

776

531

Sales

Refined metal sales

Platinum

oz

288,280

233,054

Palladium

oz

122,951

121,096

Gold

oz

5,885

5,262

Rhodium

oz

25,108

53,534

Ruthenium

oz

68,611

51,887

Iridium

oz

8,387

11,271

Total PGMs

oz

519,222

476,104

Nickel9

MT

1,246

1,074

Copper9

MT

845

724

Chrome9

MT

378,361

287,165

 

3 months

3 months

to 30 Sep

to 30 Sep

2013

2012

Average prices

Platinum

$/oz

1,443

1,477

Palladium

$/oz

718

603

Gold

$/oz

1,475

1,526

Rhodium

$/oz

975

1,106

Ruthenium

$/oz

70

100

Iridium

$/oz

841

1,033

$ basket excl. by-product revenue10

$/oz

1,058

1,053

$ basket incl. by-product revenue11

$/oz

1,110

1,103

R basket excl. by-product revenue10

R/oz

10,556

8,674

R basket incl. by-product revenue11

R/oz

11,070

9,031

Nickel9

$/MT

11,242

11,866

Copper9

$/MT

6,827

6,948

Chrome9

$/MT

18

21

Exchange Rates

Average rate for period12 

R/$

9.95

8.24

Closing rate

R/$

9.99

8.30

 

Notes:

1 Karee includes the shafts K3, K4 (currently on care and maintenance) and 4B/1B. Westerns comprises Rowland, Newman and ore purchases from W1. Middelkraal represents Hossy and Saffy. Easterns includes E1, E2 and E3.

2 Pandora attributable tonnes mined represents Lonmin's share (42.5%) of the total tonnes mined on the Pandora joint venture.

3 Tonnes milled excludes slag milling.

4 Lonmin purchases 100% of the ore produced by the Pandora joint venture for onward processing which is included in downstream operating statistics.

5 Head grade is the grammes per tonne (5PGE + Au) value contained in the tonnes milled and fed into the concentrator from the mines (excludes slag milled).

6 Recovery rate in the concentrators is the total content produced divided by the total content milled (excluding slag).

7 Metals in concentrate include metal derived from slag processing and have been calculated at industry standard downstream processing losses to present produced saleable ounces.

8 Corresponds to contained base metals in concentrate.

9 Nickel is produced and sold as nickel sulphate crystals or solution and the volumes shown correspond to contained metal. Copper is produced as refined product but typically at LME grade C. Chrome is produced in the form of chromite concentrate and volumes shown are in the form of chromite.

10 Basket price of PGMs is based on the revenue generated in Rand and Dollar from the actual PGMs (5PGE + Au) sold in the period based on the appropriate Rand / Dollar exchange rate applicable for each sales transaction.

11 As per note 10 but including revenue from base metals.

12 Exchange rates are calculated using the market average daily closing rate over the course of the period.

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 