29th Jan 2015 07:00
REGULATORY RELEASE
29 January 2015
First Quarter 2015 Production Report
Overview
We are pleased to report that the Company has been fatality free for the fourth quarter in succession following the one fatality which occurred on 26 October 2013. The rolling 12 month average Lost Time Injury Frequency Rate (LTIFR) for the 12 months to 31 December 2014 improved by 2.7% to 3.58 incidents per million man hours compared to 3.69 at 31 December 2013.
Lonmin maintained the strong operational momentum that was built up in Q4 2014 by achieving the highest Q1 production from underground (including Pandora) since 2011. Total attributable tonnes mined in the quarter were 2.8 million tonnes, 7.2%, or 0.2 million tonnes higher than the prior year period. Employee attendance levels have returned quickly to normal levels following the December 2014 holiday period.
Saleable metal-in-concentrate was the highest Q1 production since 2007 with output of 200,170 Platinum ounces. This was 11.4%, or 20,479 ounces higher than the prior year period.
RefinedPlatinum production of 139,823 ounceswas unfortunately impacted by the repairs to the Number One furnace and decreased by 28.8%, or 56,426 ounces comparedto the prior year period. We expect to process the build-up in concentrate stock by the end of the financial year.
Sales of 146,890Platinum ounces increased by 9.0%, or 12,086 ounces on the prior year period.
Mining Operations
The Marikana underground mining operations produced 2.7 million tonnes during the first quarter, an increase of 7.9%, or 0.2 million tonnes on the prior year period.
Production at Karee was 1,124,000 tonnes, an increase of 6.9%, or 72,000 tonnes on the prior year period. K3, our biggest shaft, increased production by 8.2%, or 53,000 tonnes. We saw limited activity at K4 with 8,000 tonnes produced.
Production at Westerns was 1,045,000 tonnes, an increase of 3.0%, or 30,000 tonnes on the prior year period. Rowland, our second largest shaft,increased production by 1.4%. Newman shaft delivered a 9.0% increase from the prior year period and Hossy shaft, which remains under review, pleasingly increased production by 4.9%. East 1 shaft, which is reaching its end of life saw a decrease in production of 13,000 tonnes. (East 1 has been reported under Westerns since Q4 2014 in-line with changes in management structure).
Production at Easterns was 523,000 tonnes which was 22.3%, or 95,000 tonnes higher than the prior year period. Saffy shaft recorded an increase of 30.1%, or 95,000 tonnes over the prior year period demonstrating the progress that we have made with our planned ramp up.
These results have been achieved with significantly reduced safety and industrial relations stoppages. Tonnes of production lost due to safety and labour stoppages in the quarter totalled only 22,000 tonnes. This was 249,000 tonnes lower than the prior year period which was impacted by a fatality and tensions around the wage negotiations.
Q1 2015 | Q1 2014 | |
tonnes | tonnes | |
Section 54 safety stoppages | 7,000 | 175,000 |
Management induced safety stoppages | 13,000 | 19,000 |
Labour stoppages | 2,000 | 77,000 |
Total tonnes lost | 22,000 | 271,000 |
Process Operations
Total tonnes milled in the quarter increased by 9.5%, or 0.3 million tonnes to 3.1 million tonnes when compared to the prior year. This was the highest Q1 volume milled in seven years and was achieved using six out of our seven Marikana concentrators as part of our measures to reduce costs. Underground tonnes milled were 11.7% or 318,000 tonnes higher than the prior year period and opencast tonnes milled decreased by 33.3%, or 46,000 tonnes.
Underground milled head grade increasedslightly by 0.8% to 4.55 grammes per tonne (5PGE+Au) when compared to the 4.51 grammes per tonne in the prior year period. The overall milled head grade was 4.50 grammes per tonne, up 1.3% on the prior year period due to the aforementioned increase in the grade of underground ore and the increase of underground ore in the mix.
Concentrator recoveries for the quarter were slightly lower than the prior year period at 87.1% largely due to ore mix.
Total Platinum in concentrate for the quarter at 200,170saleable ounces was 11.4% higher than the prior year period. Total PGMs in concentrate were 381,804saleable ounces which was 10.6% higher than the prior year period.
As announced on 8 December 2014, the Number One furnace was safely stopped in early December following the detection of a leak. We are making good progress with repairs to this furnace and the additional maintenance work that was brought forward and we are on track to complete these within the scheduled three months. As announced on 31 December 2014, the Number Two furnace was also safely stopped at the end of December following the detection of electrode breaks. The repairs have been successfully made to the Number Two furnace and the first matte tap was successfully made last week. The three smaller Pyromet furnaces were restarted in early December to increase smelting capacity during this time. We expect to process the build-up of concentrate by the end of Q4 2015.
Sales & Pricing
Completion of Black Economic Empowerment transaction
As announced on 26 November 2014, wesuccessfully completed the three BEE transactions in the quarter thus achieving the target of 26% BEE ownership. At the end of the quarter the Bapo ba Mogale Traditional Community were shareholders in the Company and held 3.3%. Through an Employee Share Ownership Plan our employees held 3.8% and through a Community Share Ownership Trust the local communities on the western portion of our Marikana operations held 0.9%. All three transactions collectively provided the additional 8% equity empowerment which Lonmin required to achieve the 26% effective BEE equity.
Outlook and Guidance
Because of low dollar metal prices and short to medium term uncertainty around platinum prices we will reduce our expected capital expenditure for 2015 from $250 million to $185 million and will keep this under review. Despite the revised capital expenditure for 2015 we reiterate our production guidance for the year.
As previously anticipated we expect our net borrowings to be higher at the end of March as a direct result of the lower sales volume in H1 which will unwind in H2. We are confident of managing our working capital requirements through cost conservation measures and capital discipline to keep borrowings and debt covenants well within our committed debt facilities.
We are disappointed that the repairs and maintenance to both our main furnaces necessitated by the shutdowns have overlapped and caused a temporary bottleneck in our processing operations. Following the repairs to the Number Two furnace that we built in 2012, we have sufficient smelting capacity during 2015 to overcome this obstacle and we anticipate processing the current build-up in concentrate stock during the financial year. We are making good progress towards achieving the target of more than R2 billion value benefits over three years through the freezing of general recruitment, natural attrition and reduction of contractors as we redeploy some employees to areas previously worked on by contractors. This, combined with our focus on efficiencies has resulted in a quarter on quarter mining productivity improvement of 8%. Our mining operations continue to perform well and consequently we are maintaining our guidance for the full year of sales of around 730,000 Platinum ounces. Additionally we are managing our costs so as to maintain our guidance for the unit cost of production of around R10,800 per PGM ounce.
- ENDS -
ENQUIRIES
Investors / Analysts:
Lonmin
Tanya Chikanza (Head of Investor Relations) +44 20 7201 6007 / +27 11 218 8358
Floyd Sibandze (Manager: Investor Relations) +27 11 218 8381
Media:
Cardew Group Anthony Cardew / James Clark |
+44 20 7930 0777 |
Sue Vey | +27 60 523 7953 |
Notes to editors
For further information please visit our website: http://www.lonmin.com
3 months | 3 months | |||||
to 31 Dec | to 31 Dec | |||||
2014 | 2013 | |||||
Tonnes mined | Marikana | K3 shaft | kt | 699 | 646 | |
K4 shaft | kt | 8 | - | |||
4B/1B shaft | kt | 418 | 406 | |||
Karee | kt | 1,124 | 1,052 | |||
Rowland shaft | kt | 474 | 468 | |||
Newman shaft | kt | 220 | 202 | |||
Hossy | kt | 267 | 255 | |||
W1 shaft | kt | 47 | 41 | |||
East 1 shaft 1 | kt | 35 | 49 | |||
Westerns | kt | 1,045 | 1,015 | |||
Saffy shaft | kt | 410 | 315 | |||
East 2 shaft | kt | 95 | 103 | |||
East 3 shaft | Kt | 18 | 10 | |||
Easterns | kt | 523 | 428 | |||
Underground | kt | 2,692 | 2,494 | |||
Opencast | kt | 56 | 78 | |||
Total | kt | 2,748 | 2,572 | |||
Pandora (100%)2 | Underground | kt | 165 | 126 | ||
Limpopo3 | Underground | kt | - | 4 | ||
Lonmin (100%) | Total tonnes mined (100%) | kt | 2,913 | 2,703 | ||
% tonnes mined from UG2 reef (100%) | % | 76.5 | 75.7 | |||
Lonmin (attributable) | Underground & Opencast | kt | 2,821 | 2,630 | ||
Ounces mined 4 | Lonmin excluding Pandora | Pt ounces | oz | 175,357 | 160,723 | |
Pandora (100%) | Pt ounces | oz | 11,329 | 9,017 | ||
Limpopo | Pt ounces | oz | - | 167 | ||
Lonmin | Pt ounces | oz | 186,686 | 169,907 | ||
Lonmin excluding Pandora | PGM ounces | oz | 334,417 | 308,221 | ||
Pandora (100%) | PGM ounces | oz | 22,172 | 17,748 | ||
Limpopo | PGM ounces | oz | - | 239 | ||
Lonmin | PGM ounces | oz | 356,589 | 326,209 | ||
Tonnes milled 5 | Marikana | Underground | kt | 2,864 | 2,575 | |
Opencast | kt | 93 | 139 | |||
Total | kt | 2,957 | 2,715 | |||
Pandora 6 | Underground | kt | 183 | 126 | ||
Limpopo 7 | Underground | kt | - | 27 | ||
Lonmin Platinum | Underground | kt | 3,047 | 2,729 | ||
Head grade8 | g/t | 4.55 | 4.51 | |||
Recovery rate9 | % | 87.2% | 87.9% | |||
Opencast | kt | 93 | 139 | |||
Head grade8 | g/t | 3.01 | 3.09 | |||
Recovery rate9 | % | 85.0% | 84.2% | |||
Total | kt | 3,140 | 2,868 | |||
Head grade8 | g/t | 4.50 | 4.44 | |||
Recovery rate9 | % | 87.1% | 87.8% |
3 months | 3 months | |||||
to 31 Dec | to 31 Dec | |||||
2014 | 2013 | |||||
Metals-in-concentrate10 | Marikana | Platinum | oz | 186,092 | 168,820 | |
Palladium | oz | 84,817 | 78,277 | |||
Gold | oz | 4,406 | 3,902 | |||
Rhodium | oz | 27,348 | 24,680 | |||
Ruthenium | oz | 43,655 | 39,907 | |||
Iridium | oz | 8,448 | 8,268 | |||
Total PGMs | oz | 354,765 | 323,855 | |||
Nickel 11 | MT | 960 | 837 | |||
Copper 11 | MT | 592 | 528 | |||
Pandora | Platinum | oz | 12,425 | 8,966 | ||
Palladium | oz | 5,700 | 4,242 | |||
Gold | oz | 43 | 56 | |||
Rhodium | oz | 2,116 | 1,528 | |||
Ruthenium | oz | 3,404 | 2,441 | |||
Iridium | oz | 644 | 404 | |||
Total PGMs | oz | 24,332 | 17,638 | |||
Nickel 11 | MT | 28 | 16 | |||
Copper 11 | MT | 12 | 9 | |||
Limpopo | Platinum | oz | - | 1,121 | ||
Palladium | oz | - | 974 | |||
Gold | oz | - | 93 | |||
Rhodium | oz | - | 114 | |||
Ruthenium | oz | - | 161 | |||
Iridium | oz | - | 44 | |||
Total PGMs | oz | - | 2,508 | |||
Nickel 11 | MT | - | 27 | |||
Copper 11 | MT | - | 19 | |||
Concentrate purchases | Platinum | oz | 1,653 | 783 | ||
Palladium | oz | 490 | 241 | |||
Gold | oz | 7 | 4 | |||
Rhodium | oz | 210 | 92 | |||
Ruthenium | oz | 262 | 96 | |||
Iridium | oz | 84 | 42 | |||
Total PGMs | oz | 2,707 | 1,259 | |||
Nickel 11 | MT | 1 | 0 | |||
Copper 11 | MT | 1 | 0 | |||
Lonmin Platinum | Platinum | oz | 200,170 | 179,691 | ||
Palladium | oz | 91,007 | 83,735 | |||
Gold | oz | 4,456 | 4,055 | |||
Rhodium | oz | 29,674 | 26,415 | |||
Ruthenium | oz | 47,320 | 42,605 | |||
Iridium | oz | 9,177 | 8,759 | |||
Total PGMs | oz | 381,804 | 345,259 | |||
Nickel 11 | MT | 989 | 880 | |||
Copper 11 | MT | 605 | 557 |
3 months | 3 months | |||||
to 31 Dec | to 31 Dec | |||||
2014 | 2013 | |||||
Refined production | Lonmin refined metal production | Platinum | oz | 139,712 | 196,249 | |
Palladium | oz | 63,443 | 92,985 | |||
Gold | oz | 3,654 | 4,124 | |||
Rhodium | oz | 18,944 | 27,293 | |||
Ruthenium | oz | 32,522 | 46,505 | |||
Iridium | oz | 4,349 | 11,407 | |||
Total PGMs | oz | 262,625 | 378,562 | |||
Toll refined metal production | Platinum | oz | 111 | - | ||
Palladium | oz | 1 | 770 | |||
Gold | oz | - | 61 | |||
Rhodium | oz | - | 822 | |||
Ruthenium | oz | 1,889 | 4,312 | |||
Iridium | oz | 502 | 190 | |||
Total PGMs | oz | 2,503 | 6,155 | |||
Total refined PGMs | Platinum | oz | 139,823 | 196,249 | ||
Palladium | oz | 63,444 | 93,755 | |||
Gold | oz | 3,655 | 4,185 | |||
Rhodium | oz | 18,944 | 28,115 | |||
Ruthenium | oz | 34,411 | 50,817 | |||
Iridium | oz | 4,851 | 11,597 | |||
Total PGMs | oz | 265,128 | 384,717 | |||
Base metals | Nickel 12 | MT | 660 | 1,053 | ||
Copper 12 | MT | 392 | 595 | |||
Sales | Refined metal sales | Platinum | oz | 146,890 | 134,804 | |
Palladium | oz | 67,836 | 47,921 | |||
Gold | oz | 5,200 | 2,800 | |||
Rhodium | oz | 17,114 | 23,927 | |||
Ruthenium | oz | 33,335 | 27,042 | |||
Iridium | oz | 4,050 | 9,262 | |||
Total PGMs | oz | 274,425 | 245,755 | |||
Nickel 12 | MT | 832 | 673 | |||
Copper 12 | MT | 402 | 503 | |||
Chrome 12 | MT | 367,507 | 388,822 |
3 months | 3 months | |||||
to 31 Dec | to 31 Dec | |||||
2014 | 2013 | |||||
Average prices | Platinum | $/oz | 1,213 | 1,393 | ||
Palladium | $/oz | 787 | 724 | |||
Gold | $/oz | 1,512 | 1,510 | |||
Rhodium | $/oz | 1,199 | 937 | |||
Ruthenium | $/oz | 52 | 53 | |||
Iridium | $/oz | 509 | 489 | |||
$ basket excl. by-product revenue 13 | $/oz | 961 | 1,038 | |||
$ basket incl. by-product revenue 14 | $/oz | 1,033 | 1,112 | |||
R basket excl. by-product revenue 13 | R/oz | 10,689 | 10,538 | |||
R basket incl. by-product revenue 14 | R/oz | 11,488 | 11,299 | |||
Nickel 12 | $/MT | 12,683 | 11,464 | |||
Copper 12 | $/MT | 6,517 | 6,771 | |||
Chrome 12 | $/MT | 18 | 18 | |||
Exchange rates | Average rate for period 15 | R/$ | 11.22 | 10.12 | ||
Closing rate | R/$ | 11.56 | 10.44 |
Notes:
1 East 1 shaft is now reported under Westerns in-line with changes in management structure. Prior periods have been adjusted accordingly.
2 Pandora underground tonnes mined represents 100% of the total tonnes mined on the Pandora joint venture of which 42.5% for October and November 2014 and 50% thereafter is attributable to Lonmin.
3 Limpopo underground tonnes mined represents low grade development tonnes mined whilst on care and maintenance.
4 Ounces mined have been calculated at achieved concentrator recoveries and with Lonmin standard downstream processing recoveries to present produced saleable ounces.
5 Tonnes milled excludes slag milling.
6 Lonmin purchases 100% of the ore produced by the Pandora joint venture for onward processing which is included in downstream operating statistics.
7 Limpopo tonnes milled represents low grade development tonnes milled.
8 Head grade is the grammes per tonne (5PGE + Au) value contained in the tonnes milled and fed into the concentrator from the mines (excludes slag milled).
9 Recovery rate in the concentrators is the total content produced divided by the total content milled (excluding slag).
10 Metals-in-concentrate have been calculated at Lonmin standard downstream processing recoveries to present produced saleable ounces.
11 Corresponds to contained base metals-in-concentrate.
12 Nickel is produced and sold as nickel sulphate crystals or solution and the volumes shown correspond to contained metal. Copper is produced as refined product but typically at LME grade C. Chrome is produced in the form of chromite concentrate and volumes shown are in the form of chromite.
13 Basket price of PGMs is based on the revenue generated in Rand and Dollar from the actual PGMs (5PGE + Au) sold in the period based on the appropriate Rand / Dollar exchange rate applicable for each sales transaction.
14 As per note 13 but including revenue from base metals.
15 Exchange rates are calculated using the market average daily closing rate over the course of the period.
Related Shares:
Lonmin