Become a Member
  • Track your favourite stocks
  • Create & monitor portfolios
  • Daily portfolio value
Sign Up
Quickpicks
Add shares to your
quickpicks to
display them here!

Final Results for the year ended 31 December 2012

5th Jun 2013 07:00

RNS Number : 2886G
Trans-Siberian Gold PLC
05 June 2013
 



 

 

Trans-Siberian Gold plc

 

Final results for the year ended 31 December 2012

 

Highlights

·; Asacha JORC resource update adds 321,000 oz. gold and 703,000 oz. silver, net of 2011 and 2012 production

·; JORC resource update includes 252,000 oz. gold and 395,000 oz. silver in Asacha's new Eastern zone

·; Asacha 2012 production 27,920 oz. gold, 35,924 oz. silver

·; Changes in mining methods, equipment and personnel to address Asacha dilution problem

·; $6.4 million debt converted to equity in February 2012

 

ASACHA JORC MINERAL RESOURCES - as of 31 December 2012

 

Category

Tonnes

Au Grade g/t

Ag Grade g/t

Au Equivalent g/t

Contained Au oz

Contained Ag oz

Contained *Au Equivalent oz

Measured

284,541

19.1

31.5

19.7

174,700

288,400

180,500

Indicated

855,506

19.5

56.0

20.6

536,800

1,540,500

567,600

Sub-total

1,140,047

19.4

49.9

20.4

711,500

1,828,900

748,100

Inferred

454,828

21.2

40.0

22.0

310,600

585,200

322,200

Total

1,594,875

19.9

47.1

20.9

1,022,100

2,414,100

1,070,300

4 g/t cut-off

* 50oz of Ag = 1oz of Au equivalent

JORC = Australasian Joint Ore Reserves Committee.

 

 

Chairman's Statement

Trans-Siberian Gold plc ("TSG" or "the Company") reports that the Asacha mine's first full year of operation produced more than 27,500 oz. of gold and more than 35,000 oz. of silver. During the year the Asacha plant performed well, operating at close to its designed capacity of 12,500 tonnes per month in the second half of 2012 and achieving gold recoveries of more than 95% throughout the year. However several operational problems, principally dilution in the mine, caused lower than expected gold grades in the ore delivered to the plant. This resulted in lower gold production and higher per oz. gold production costs, with a consequent negative impact on the 2012 results.

 

A comprehensive technical mine audit highlighted several factors which had contributed to the dilution problem, including stoping methods, the blasting scheme, a lack of both appropriate equipment and experienced personnel. The audit concluded that the mining method prescribed in the design of the mine, long hole blasting, was not appropriate for some areas of fractured rock enclosing the main stoping zone planned for mining in 2012. On the basis of the mine auditor's recommendations, where practicable, some of the adjacent blocks were mined by shallow hole blasting which achieved better results in terms of dilution.

Mine performance in the third quarter was affected by the breakdown of some underground equipment. This reduced the amount of stoping ore which could be delivered to the plant, necessitating blending the mined ore with lower grade ore from the surface ore stockpile. Additional spare parts were purchased and new machines, including a new underground truck and underground loader were delivered to site in November and late December respectively. Additional equipment for the site laboratory increased its sample capacity to more than 100 assays per day.

The mine's management team was also strengthened by the recruitment of a technical director, two new underground mining engineers and a mining geologist. These appointments of experienced personnel, together with the new equipment, consolidated the steady improvement in the mine's performance during the fourth quarter, with ore grades delivered to the plant increased from 5.4 g/t in October to 7.2 g/t in December. 3,263 oz. of refined gold were produced in December.

In the first quarter of 2013, ore extraction (including stoping and mine development) amounted to 45,352 metric tonnes, the highest quarterly total to date. Mining activity is now focused on increasing the volume and quality of stoping ore, since the 4,100 metres of mine development in 2012 included the preparation of stoping areas to be mined in 2013.Plant throughput averaged 11,862 tonnes per month (95% of planned 12,500 tonnes). Plant performance continued to be affected by low ore grades, due to dilution.  

TSG is cautiously optimistic that ore dilution can be reduced further through planned adjustments in the mining methods, in particular, reducing the diameter of drill holes and the introduction of additional supports. Other measures under consideration include the use of less brisant explosives (i.e. explosives with less shattering effect). However fractured rock in the upper part of the orebody makes it likely that this problem will take time to resolveand the positive impact of changes in stoping methods will not be fully reflected in improved ore grades until ore from 2012's mine development which remains underground, and therefore subject to further dilution, can be moved to the surface and new mine development schemes are fully introduced.

With the aim to increase the Company's gold resources geological drilling amounting to approximately 11,200 metres was undertaken on the Eastern flank of the Asacha deposit, resulting in the addition of approximately 252,000 oz. gold, included in the updated JORC Resource table shown above. The update also showed a net increase of 119,300 oz. gold in the measured and indicated resources in Asacha's main zone. 

 

In April 2013 the federal authorities prescribed the implementation of two provisions of the Rodnikova licence by April 2014: the finalisation of the design documentation and the commencement of work at the deposit, failing which the authorities will consider the termination of the licence. The designing institute began work in 2012 and is expected to complete the design documentation in 2013. Although we are seeking to comply with these requirements it is unclear whether there is adequate time or available funding to do so. Therefore full provision has been recognised in respect of Rodnikova's $2.9 million exploration costs.

 

Financial Review

Gold production commenced at Asacha in September 2011. Revenue from the sale of 26,326 oz. of refined gold (2011: 6,539 oz.) and 32,964 oz. of refined silver (2011: 7,189 oz.) was $43.9 million and $976,000 respectively (2011: $11.7 million and $223,000). Average realised prices were $1,668 per oz. gold and $30 per oz. silver (2011: $1,790 per oz. gold and $31 per oz. silver). Cost of sales per oz. gold, net of the credit from silver sales revenue, was $1,275 (2011: $1,212). Cash cost per oz. gold including depletion, net of the silver credit and excluding royalty, was $858 (2011:$960).

The Group recorded an operating profit for the year of $681,000 (2011: $590,000), after recognising a $2.9 million impairment charge against Rodnikova's exploration and evaluation expenditure and crediting an exchange gain of $2.1 million (2011: $2.0 million). Administration expenses amounted to $838,000 in UK and $5.4 million in Russia (2011: $1.6 million and $4.2 million respectively), in aggregate $6.3 million (2011: $5.8 million). Russian administration costs included the write off of non-recoverable Value Added Tax (VAT) of $422,000 (2011: $926,000) and an inventory provision of $488,000 (2011: nil).

Finance income was $6,000 (2011: $12,000). Finance costs were $4.1 million (2011: $1.5 million), net of $nil (2011: $3.4 million) interest capitalised.

Total non-current assets decreased from $128.0 million to $110.6 million. Mining properties of $29.5 million (2011:$34.2 million) reflected $10.5 million additional mining and mine development, more than offset by depletion of $15.2 million. Property, plant and equipment decreased by $9.5 million to $75.4 million. Capitalised exploration and evaluation costs reduced from $2.9 million to $1.6 million, reflecting the impairment provision in respect of expenditure on the Rodnikova deposit, partially offset by exploration of the eastern zone at Asacha. 

Inventories at Asacha at 31 December 2012 comprised $4.1 million gold and silver in production (2011: $1.3 million), $12.4 million ore stocks (2011: $4.7 million) and $3.9 million fuel and other materials and supplies (2011: $4.5 million), in aggregate $20.4 million (2011: $10.5 million). Recoverable VAT at 31 December 2012 was $2.1 million (2011: $3.3 million) all of which is expected to be received during 2013.

Loans and borrowings at 31 December 2012 totalled $34.7 million (2011: $48.5 million), comprising $32.6 million (2011: $40.0 million) outstanding under two five year facilities, totalling $43.0 million, provided by Sberbank for the development of Asacha, $815,000 short term loan finance (2011: $8.2 million), including accrued interest, provided by TSG's major shareholders UFG Asset Management (UFG) and AngloGold Ashanti Limited (AGA) in June 2012 and $1,009,000 finance lease obligations (2011: $334,000).

Shareholder loans

In February 2012, 5,842,390 new TSG ordinary shares were issued to UFG and AGA in settlement of the Company's indebtedness, in aggregate $6.4 million including accrued interest, under various short term loan facilities provided by UFG and AGA in September 2011.The remaining $1.8 million was repaid to UFG and AGA in March and April 2012.

 

Asacha mine

A further $21.5 million of capital expenditure, including contingency of $3.6 million, will be incurred in 2013 and subsequent years, comprising:

$ million

Mine development and mining equipment and facilities

7.2

Gold plant expansion and site facilities

3.4

Tailings storage (2nd phase)

5.7

Infrastructure

1.6

Contingency

3.6

21.5

 

At a gold price of $1,500/oz., Life of mine ("LOM") cash costs on an all equity basis on total expected gold production of 589,000 oz. are forecast at $347/oz., before taking account of a $51/oz. credit from silver production (assuming a silver price of $30/oz.). Cash costs including all royalties and taxes (in total $147.4 million, net of VAT recoveries) on an all equity basis are forecast at $597/oz. Total costs on the same basis, after depreciation of all capital expenditure (including $29.0 million post start up) and pre-start up mining and other operating expenditure, are forecast at $873/oz., giving a $627/oz. margin at a gold price of $1,500/oz.

 

At a gold price of $1,300/oz., cash costs including all royalties and taxes (in total $120.0 million, net of VAT recoveries) on an all equity basis are forecast at $551/oz. Total costs on the same basis, after depreciation of all capital expenditure and pre-start up operating expenditure, are forecast at $826/oz., giving a $474/oz. margin at a gold price of $1,300/oz.

 

Events after the reporting date

By the end of the first quarter of 2013, $15 million of the $43 million facilities provided by Sberbank for the development of Asacha had been repaid. Scheduled repayments in the remaining nine months of 2013 and the first half of 2014 amount to $15.5 million and $12.5 million respectively. During the first half of 2013 discussions took place with Sberbank in respect of a restructuring of these facilities or the provision of an additional facility, either of which would have the effect of extending the facility repayments over a longer period into 2015. These discussions are continuing and a further announcement will be made in due course.

  

 

Ends

 

Contacts:

TSG +44 (0) 1480 811871

Simon Olsen +44 (0) 7770 484965

 

 

Cantor Fitzgerald Europe

+44 (0) 207 894 7000

David Foreman / Stewart Dickson (Corporate Finance)

 

Jeremy Stephenson (Corporate Broking)

 

Trans-Siberian Gold plc

Consolidated Statement of Financial Position

 

Note

31 December

2012

$000

31 December

2011

$000

Assets

Non-current assets

Mining properties

2

29,498

34,224

Property, plant and equipment

3

75,354

84,894

Deferred exploration and evaluation costs

4

1,643

2,866

Deferred tax asset

5

4,096

6,009

Total non-current assets

110,591

127,993

Current assets

Inventories

20,404

10,544

Trade and other receivables

2,823

3,963

Cash and cash equivalents

669

2,190

Total current assets

23,896

16,697

Total assets

134,487

144,690

Liabilities

Non-current liabilities

Borrowings

6

13,028

32,690

Deferred tax liabilities

5

-

623

Provisions

1,045

644

Total non-current liabilities

14,073

33,957

Current liabilities

Trade and other payables

6,776

4,401

Borrowings

6

21,399

15,808

Total current liabilities

28,175

20,209

Total liabilities

42,248

54,166

Total net assets

92,239

90,524

Capital and reserves attributable to owners of the Company

Share capital

7

18,988

18,050

Share premium

7

89,520

84,013

Retained deficit

(16,269)

(11,539)

Total equity

92,239

90,524

 

Trans-Siberian Gold plc

Consolidated Statement of Comprehensive Income

 

Note

Year ended

31 December

2012

$000

Year ended

31 December

2011

$000

Revenue

8

44,886

11,930

Cost of sales

9

(37,184)

(8,149)

Gross profit

7,702

3,781

Administrative expenses

(6,269)

(5,806)

Other income

75

635

Impairment provision

4

(2,902)

-

Net foreign exchange differences on operating activities

2,075

1,980

Profit from operations

681

590

Finance expense

(4,111)

(1,465)

Finance income

6

12

Net foreign exchange differences on financing activities

1

54

Loss before tax

(3,423)

(809)

Income tax (charge) credit

(1,307)

5,393

(Loss) profit for the year

(4,730)

4,584

Total comprehensive (expense) income for the year

(4,730)

4,584

(Loss) profit for the year attributable to:

Owners of the parent company

(4,730)

4,584

(Loss) profit for the year

(4,730)

4,584

Total comprehensive (expense) income for the year attributable to:

Owners of the parent company

(4,730)

4,584

(Loss) profit for the year

(4,730)

4,584

(Loss) profit per share attributable to the owners

of the parent company (expressed in cents)

- basic and diluted

(4.33)

4.57

 

 

Trans-Siberian Gold plc

Consolidated Statement of Cash Flows

 

 

Note

Year ended

31 December

2012

$000

Year ended

31 December

2011

$000

Cash flows from operating activities

(Loss) profit for the year

(4,730)

4,584

Adjustment for:

Mining properties depletion charged to income statement

6,915

-

Depreciation of property, plant and equipment charged to income statement

12,434

667

Finance expense - net

4,105

1,399

Impairment provision

2,902

-

Share based payments

-

339

Corporation tax charge (credit)

1,307

(5,393)

Loss on sale of property, plant and equipment

31

1

Cash flows from operating activities before changes in working capital and provisions

22,964

4,425

Increase in inventories

(1,049)

(9,902)

Decrease in trade and other receivables

2,344

3,204

Increase in trade and other payables

1,117

1,722

Cash generated from (used in) operations

25,376

(551)

Corporation tax (paid) received

(4)

7

Interest paid on borrowings

(4,058)

(857)

Net cash flows generated from (used in) operating activities

21,314

(1,401)

Investing activities

Mining and mine development

(10,099)

-

Purchase of property, plant and equipment (PPE)

(3,445)

(15,231)

Proceeds from sale of PPE

44

-

Purchase of exploration and evaluation assets including capitalised interest

(891)

(6,493)

Interest received - third party

6

12

Net cash used in investing activities

(14,385)

(21,712)

Financing activities

Proceeds from bank borrowings

-

12,087

Repayment of bank borrowings

(7,375)

(3,000)

Proceeds from short term borrowings

781

8,000

Repayment of short term borrowings

(1,760)

-

Proceeds from long term borrowings

-

4,330

Repayment of finance leases

(97)

(149)

Net cash (used in) generated from financing activities

(8,451)

21,268

Net decrease in cash and cash equivalents

(1,522)

(1,845)

Cash and cash equivalents at beginning of the year

2,190

3,981

Exchange gains on cash and cash equivalents

1

54

Cash and cash equivalents at end of the year

669

2,190

Notes

1. Going concern

The Group's operations are cash generative but the repayment of $32.5m of bank borrowings, which is due in 2013 and 2014, cannot be funded from the cash generated from operations and existing working capital. The Directors are currently in advanced negotiations with the Group's bankers to refinance the existing bank debt. The Directors are confident that an agreement can be reached and therefore consider it appropriate to prepare the financial statements on a going concern basis. Should the Group be unable to refinance the bank debt it may be unable to realise its assets and discharge its liabilities in the normal course of business.

 

These conditions indicate the existence of a material uncertainty which may cast significant doubt over the Group's ability to continue as a going concern. The financial statements do not include the adjustments that would result if the Group was unable to continue as a going concern.

 

2. Mining properties

Mining properties assets relate to the Asachinskoye (Asacha) mining licence held by the Company's subsidiary ZAO Trevozhnoye Zarevo (TZ).

Asacha

$000

Rodnikova

$000

Total

$000

At 1 January 2011

-

-

-

Transfers from Deferred exploration and evaluation costs i

37,052

-

37,052

Depletion

(2,828)

-

(2,828)

At 31 December 2011

34,224

-

34,224

At 1 January 2012

34,224

-

34,224

Additions

10,501

-

10,501

Depletion

(15,227)

-

(15,227)

At 31 December 2012

29,498

-

29,498

i Transfers from Deferred exploration and evaluation costs represent assets brought into use on the commencement of production.

 

Under the Licencing Agreement as revised in 2006, TZ was required to bring the Asacha mine into operation at its projected capacity in accordance with the technical design at a rate of at least 1,000 kg of gold per annum by 31 December 2008. That requirement was partially fulfilled in 2008, with the commencement of mining activities and first ore extraction. In December 2008 the Kamchatka regional governmental commission noted the delay in mining but concluded that work to finalise construction should continue to put the gold plant into operation in 2009. Government authorities have since been kept advised of the development of the project and although funding constraints arising in 2008-09 delayed completion of construction at Asacha until the middle of 2011 with gold production commencing in September 2011, the Company believes that there will be no adverse consequences of the delay. Discussions in respect of any required amendments to the licence have already commenced with the appropriate authorities and it is expected that these will be concluded in 2013.

3. Property, plant and equipment

Group

Buildings

$000

Plant and

machinery

$000

Motor

vehicles

$000

Office

equipment

and furniture

$000

Assets under

construction i

$000

Total

$000

Cost

At 1 January 2011

1,167

7,395

2,089

408

67,421

78,480

Additions

-

474

-

-

14,647

15,121

Disposals

(12)

(309)

(44)

-

-

(365)

Re-classifications

71,455

8,408

294

88

(80,245)

-

At 31 December 2011

72,610

15,968

2,339

496

1,823

93,236

Depreciation

At 1 January 2011

(940)

(2,836)

(1,356)

(271)

-

(5,403)

Charge for year iii

(1,634)

(1,211)

(400)

(58)

-

(3,303)

Disposals

12

308

44

-

-

364

At 31 December 2011

(2,562)

(3,739)

(1,712)

(329)

-

(8,342)

Net book value

At 1 January 2011

227

4,559

733

137

67,421

73,077

At 31 December 2011

70,048

12,229

627

167

1,823

84,894

 

Cost

At 1 January 2012

72,610

15,968

2,339

496

1,823

93,236

Additions

1,673

870

-

19

903

3,465

Disposals

(8)

(162)

(46)

(19)

-

(235)

Re-classifications

1,009

205

-

6

(1,220)

-

At 31 December 2012

75,284

16,881

2,293

502

1,506

96,466

Depreciation

At 1 January 2012

(2,562)

(3,739)

(1,712)

(329)

-

(8,342)

Charge for year iii

(10,344)

(2,320)

(201)

(65)

-

(12,930)

Disposals

6

90

46

18

-

160

At 31 December 2012

(12,900)

(5,969)

(1,867)

(376)

-

(21,112)

Net book value

At 1 January 2012

70,048

12,229

627

167

1,823

84,894

At 31 December 2012

62,384

10,912

426

126

1,506

75,354

i Assets under construction comprise $1,239,426 (2011: $798,727) for building construction and infrastructure at Asacha, $69,366 (2011: $1,023,727) for plant and equipment at Asacha and $197,361 (2011: $nil) for plant and equipment at Rodnikova.

ii $314,328 (2011: $2,636,164) of the depreciation charge related to property, plant and equipment used on exploration and evaluation projects or assets under construction and was capitalised in exploration and evaluation costs or property, plant and equipment in accordance with the Group's accounting policy.

iii The net carrying amount of property, plant and equipment includes the following amounts in respect of assets held under finance leases

2012

$000

2011

$000

Plant and machinery

817

437

Motor vehicles

-

-

Office equipment and furniture

-

-

817

437

 

4. Deferred exploration and evaluation costs

Deferred exploration and evaluation expenditure relates to the "Asacha East" zone, a separate orebody within the Asacha mineral rights licence discussed in Note 2, and the Rodnikova mining licence, also held by the Company's subsidiary ZAO Trevozhnoye Zarevo (TZ).

Asacha

$000

Rodnikova

$000

Total

$000

At 1 January 2011

27,027

2,848

29,875

Additions i

10,025

18

10,043

Transfers to Mining Properties ii

(37,052)

-

(37,052)

At 31 December 2011

-

2,866

2,866

At 1 January 2012

-

2,866

2,866

Additions i

1,643

36

1,679

Impairment provision

-

(2,902)

(2,902)

Transfers to Mining Properties ii

-

-

-

At 31 December 2012

1,643

-

1,643

i Additions include capitalised PPE depreciation.

ii Transfers to mining properties represent assets brought into use upon the commencement of production, see Note 2.

 

Under the Licencing Agreement as revised in 2006, TZ was required to complete the exploration programme of the licence area and to submit a geological report containing reserve calculations for approval by the state geological authorities before 31 December 2008 and to prepare and permit a feasibility study for the development of the deposit before 31 March 2010. A pre-feasibility study containing the required reserve calculations was submitted in December 2008. The comments and recommendations of the State Expert Commission for Reserves were received in August 2009. During 2010 the geologic report and the pre-feasibility study were completely revised taking into account the latest geologic exploration results. The final report on Rodnikova's Mineral Reserves and the pre-feasibility study were submitted to the authorities in March 2011. The Mineral Reserves report was approved by the Kamchatka authorities in April 2011. The Russian State Commission for Reserves approved the expert opinion on the Report on Reserves and Pre-feasibility study of the Rodnikova deposit on 28 October 2011, with a recommendation for underground mining.

Following an inspection in 2012, the Federal Service for Supervision of Natural Resources Management prescribed the implementation of two provisions of the Rodnikova licence by April 2014, first the finalisation of the design documentation, secondly the commencement of work at the deposit, failing which the federal authorities will consider the termination of the licence. The designing institute began work in 2012 and is expected to complete the design documentation in 2013. Although TZ is seeking to comply with these requirements it is unclear whether there is adequate time or available funding to do so. Therefore full provision has been recognised in respect of Rodnikova's deferred exploration and evaluation costs.

 

5. Deferred tax

Deferred income tax at 31 December relates to the following:

1 January

2012

$000

Charged/(Credited)

to Income Statement

$000

31 December

2012

$000

Tax effect of deductible temporary differences:

Inventory

(25)

(153)

(178)

Accounts receivable & other debtors

(173)

76

(97)

Recognised taxable losses

(5,811)

1,990

(3,821)

Gross deferred tax asset

(6,009)

1,913

(4,096)

Tax effect of taxable temporary differences:

Property, plant and equipment

552

(552)

-

Accounts payable etc.

71

(71)

-

Gross deferred tax liabilities

623

(623)

-

Total net deferred tax asset

(5,386)

1,290

(4,096)

 

6. Borrowings

Note

31 December

2012

$000

31 December

2011

$000

Non-current:

Bank Borrowings

12,500

32,500

Finance lease obligations

528

190

13,028

32,690

Current:

Bank Borrowings

20,103

7,477

Related party - other loans

815

8,187

Finance lease obligations

481

144

21,399

15,808

34,427

48,498

 

Movement in borrowings is analysed as follows:

 

Note

2012

$000

2011

$000

At 1 January

48,498

32,939

Increase in borrowings

781

24,417

Interest on related party loans

103

610

Repayment of loan and accrued interest

(9,185)

(3,000)

Conversion of loans to equity

7

(6,445)

(6,802)

Finance leases

675

334

At 31 December

34,427

48,498

 

In 2009 and 2010 ZAO Trevozhnoye Zarevo (TZ) arranged two loan facilities for the Asacha project, in total $43 million, with the Russian bank Sberbank. Repayments under the initial five year $25 million facility, which bears an annual interest rate of 10.5%, commenced in November 2011 with the second instalment, due in March 2012, prepaid in December 2011. Repayments under the second, $18 million, facility which also bears an annual interest rate of 10.5%, commenced in September 2012.

 

In October 2010 and April 2011 UFG Asset Management (UFG), a related party by virtue of its then 54.3% holding in the shares of the Company, provided TSG with two long term loan facilities, each of $2 million, on commercial terms. In April 2011 AngloGold Ashanti Limited (AGA), also a related party by virtue of its then 30.7% holding in the shares of the Company, agreed to provide TSG with a long term loan facility of $2.3 million on commercial terms. Each of the three loan facility agreements included an option for the lender, subject to the requisite approval of TSG's shareholders, to convert any part of the outstanding loan into TSG shares at a price equivalent to the volume weighted average price of TSG's shares for the period of 60 business days prior to notice of such conversion.

 

On 8 November 2011, as discussed in Note 7, the above three loan facilities, in aggregate $6,802,279 including accrued interest, were converted into TSG ordinary shares.

 

In September 2011 UFG provided TSG with four short term loan facilities amounting to $5 million on commercial terms, each with the same conversion option as their previous loans, exercisable prior to scheduled repayment 180 days after drawdown. On 23 September 2011 AGA agreed to provide a short term loan facility of $3 million on commercial terms, with the same conversion option as the UFG loans, exercisable prior to scheduled repayment 180 days after drawdown.

 

In February 2012, as discussed in Note 7, three of the short term loan facilities provided by UFG and part of the short term facility provided by AGA, in aggregate $6,445,099 including accrued interest, were converted into TSG ordinary shares. The fourth UFG facility and the remaining part of the AGA facility were repaid in March 2012 and April 2012 respectively.

 

In June 2012 UFG and AGA agreed to provide additional short term facilities, in aggregate $781,000, on commercial terms. In September 2012 the terms of the two facilities were extended to 1 March 2013, the revised facility agreements each including the same conversion option as the previous loan facilities provided by UFG and AGA. In January 2013, as discussed in Note 10, the two facilities were increased to an aggregate $891,000 and their terms were further extended to 30 September 2013.

 

In consideration of a loan facility provided by UFG in 2009, the Company also agreed, subject to obtaining the necessary shareholder approvals, to issue warrants to subscribe for additional TSG shares to UFG on terms to be agreed and considered as fair and reasonable by the Company's Board (excluding those directors connected to UFG) after consultation with TSG's Nominated Adviser. No warrants were issued in 2011 or 2012 or after the reporting date.

.

7. Share capital and premium

Group and Company

Number of

shares

authorised

Number of

shares allotted

and fully paid

Share capital

$000

Share premium

$000

Total

$000

At 1 January 2011

150,000,000

99,669,370

17,323

77,938

95,261

Shares issued

 - Debt conversion

-

4,541,313

727

6,075

6,802

At 31 December 2011

150,000,000

104,210,683

18,050

84,013

102,063

At 1 January 2012

150,000,000

104,210,683

18,050

84,013

102,063

Shares issued

 - Debt conversion

-

5,842,390

938

5,507

6,445

At 31 December 2012

150,000,000

110,053,073

18,988

89,520

108,508

All shares are ordinary shares with a par value of 10 pence.

On 8 November 2011, 4,541,313 ordinary shares were issued to UFG Asset Management (UFG) and AngloGold Ashanti Limited (AGA) in settlement of the Company's indebtedness, in aggregate $6,802,279 including accrued interest. 2,938,890 ordinary shares were issued to UFG, at 93.4 pence per share, and 1,602,423 ordinary shares were issued to AGA, at 93.6 pence per share, in consideration of the conversion of the outstanding amounts of three loan facilities as discussed in Note 6. and 33.

 

In February 2012, 5,842,390 ordinary shares were issued to UFG and AGA in settlement of the Company's indebtedness, in aggregate $6,445,099 including accrued interest. 3,738,665 ordinary shares were issued to UFG, 2,808,151 ordinary shares on 1 February 2012 at 69.94 pence per share and 930,514 ordinary shares on 3 February 2012 at 69.98 pence per share, and 2,103,725 ordinary shares to AGA, 1,578,620 ordinary shares on 1 February 2012 at 69.98 pence per share and 525,105 ordinary shares on 3 February 2012 at 69.75 pence per share, in consideration of the conversion of the outstanding amounts of four loan facilities as discussed in Note 6.

 

8. Revenue

 

Group

Year ended

31 December

2012

$000

Year ended

31 December

2011

$000

Gold

43,911

11,707

Silver

975

223

44,886

11,930

 

9. Cost of sales

 

Group

Year ended

31 December

2012

$000

Year ended

31 December

2011

$000

Wages and salaries

7,985

2,996

Energy and materials

7,802

2,840

Depreciation

12,434

623

Depletion

6,915

-

Other costs

2,048

1,690

37,184

8,149

 

10. Events after the reporting date

By the end of the first quarter of 2013, $15 million of the $43 million facilities provided by Sberbank for the development of Asacha had been repaid. Scheduled repayments in the remaining nine months of 2013 and the first half of 2014 amount to $15.5 million and $12.5 million respectively. During the first half of 2013 discussions took place with Sberbank in respect of a restructuring of these facilities or the provision of an additional facility, either of which would have the effect of extending the facility repayments over a longer period into 2015. These discussions are continuing. In conjunction with its major shareholders, the Company is also considering other options to reduce the impact of its existing loan repayment schedule.

 

On 21 January 2013 TSG's major shareholder AngloGold Ashanti Limited (AGA) agreed to increase its $281,000 short term facility to $321,000 and to extend the facility's repayment date to 30 September 2013. On 29 January 2013 TSG's other major shareholder UFG Asset Management (UFG) agreed to increase its $500,000 short term facility to $570,000 and to extend the repayment date to 30 September 2013.

 

11. Basis of accounting and presentation of financial information

The Group's financial statements have been prepared in accordance with International Financial Reporting Standards (IFRS) as adopted by the European Union. However this announcement does not in itself contain sufficient information to comply with IFRS.

 

The financial information does not constitute the Group's statutory financial statements as defined in section 434 of the Companies Act 2006 but is derived from those accounts. The financial information for the year ended 31 December 2012 has been extracted from the audited accounts of Trans-Siberian Gold plc which will be delivered to the Registrar of Companies in due course. The auditors reported on those accounts and their report was unqualified and did not contain a statement under section 498 (2) or (3) of the Companies Act 2006. The financial information for the year ended 31 December 2011 has been extracted from the audited accounts of Trans-Siberian Gold plc which have been delivered to the Registrar of Companies. The auditors reported on those accounts and their report was unqualified and did not contain a statement under section 498 (2) or (3) of the Companies Act 2006.

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
FR UGUAWQUPWGAC

Related Shares:

TSG.L
FTSE 100 Latest
Value8,850.63
Change-34.29