Exploration & Development Report Q/E 30 Sept 08

22nd Oct 2008 07:00

RNS Number : 4008G
BHP Billiton PLC
22 October 2008
 



22 October 2008 Number 35/08

BHP BILLITON QUARTERLY REPORT ON 

EXPLORATION AND DEVELOPMENT ACTIVITIES

QUARTER ENDED 30 SEPTEMBER 2008

This report covers the Group's exploration and development activities for the quarter ended 30 September 2008. This report, together with the Production Report, represents the Interim Management Statement for the purposes of the UK Listing Authority's Disclosure and Transparency Rules. There have been no significant changes to the financial position of the Group in the quarter ended 30 September 2008. Unless otherwise stated, BHP Billiton's interest in the projects referred to in this report is 100 per cent and references to project schedules are based on calendar years.

DEVELOPMENT

First production was successfully achieved during the quarter at Neptune and North West Shelf Train 5 (both petroleum). In addition, North West Shelf Angel (petroleum) delivered first production on 3 October 2008. These projects will not be reported in future Exploration and Development Reports. 

During the quarter, we sanctioned two gas projects - Bass Strait Turrum and Angostura Gas Phase II. Atlantis North is now also detailed in the report.

PROJECT AND OWNERSHIP

SHARE OF APPROVED CAPEX US$M

INITIAL PRODUCTION TARGET DATE

PRODUCTION CAPACITY (100%)

QUARTERLY PROGRESS

Petroleum Projects

Neptune (US)

35%

Oil/Gas

405

Mid CY08

50,000 barrels of oil and 50 million cubic feet gas per day

First production announced, see News Release dated 6 July 2008.

North West Shelf Train 5 

(Australia)

16.67%

LNG

350

Late CY08

LNG processing capacity of 4.4 million tpa

Start-up achieved ahead of schedule and on budget. See News Release dated 1 September 2008.

North West Shelf Angel (Australia)

16.67%

Oil/Gas

200

End CY08

800 million cubic feet gas per day and 50,000 bpd condensate

Start-up achieved ahead of schedule and on budget. See News Release dated 3 October 2008.

Shenzi (US)

44%

Oil/Gas

1,940

Mid CY09

100,000 barrels of oil and 50 million cubic feet gas per day

Ahead of schedule and on budget. Subsea hook-up of wells and commissioning of topsides commenced. Two of five wells complete, with the third and fourth wells nearing completion.

Atlantis North (US)

44%

Oil/Gas

185

H2 CY09

Tieback to Atlantis South

On schedule and budget. Flowlines installed and manifold fabrication continuing.

Pyrenees

(Australia)

71.43% 

Oil/Gas

1,200

H1 CY10

96,000 barrels of oil and 60 million cubic feet gas per day 

On schedule and budget. Floating Production Storage and Offtake (FPSO) conversion continues.

Angostura Gas Phase II (Trinidad and Tobago)

45%

Gas

180

H1 CY11

280 million cubic feet gas per day

On schedule and budget. The project was sanctioned during the quarter. See News Release dated 16 September 2008.

Bass Strait Kipper (Australia)

32.5% - 50%

Gas/Gas Liquids

500

CY11

10,000 bpd condensate and processing capacity of 80 million cubic feet gas per day

On schedule and budget. Line pipe delivered, with engineering and procurement progressing.

Bass Strait Turrum (Australia)

50%

Gas/Gas Liquids

625

CY11

11,000 bpd condensate and processing capacity of 200 million cubic feet gas per day 

On schedule and budget. The project was sanctioned during the quarter. See News Release dated 25 July 2008.

North West Shelf North Rankin B Gas Compression 

(Australia)

16.67%

LNG

850

CY12

2,500 million cubic feet gas per day 

On schedule and budget. Detailed engineering and procurement progressing.

  

PROJECT AND OWNERSHIP

SHARE OF APPROVED CAPEX US$M

INITIAL PRODUCTION TARGET DATE

PRODUCTION CAPACITY (100%)

QUARTERLY PROGRESS

Minerals Projects

Alumar - Refinery Expansion (Brazil) 36%

Alumina

900

Q2 CY09

2 million tpa of alumina

On schedule with revised budget. Budget revised due to foreign exchange and other industry cost pressures which are in line with other major projects in BrazilEngineering is complete and procurement well advanced. Construction is 70% complete with the project overall 85% complete

Worsley Efficiency & Growth (Australia)

86%

Alumina

1,900

H1 CY11

1.1 million tpa of alumina

On schedule and budget. Major contracts for precipitation, structural, mechanical and piping awarded. Site works commenced.

Iron Ore (Western Australia)

RGP4

86.2%

Iron Ore

1,850

H1 CY10

26 million tpa

additional iron ore system capacity

On schedule and on budget in local currency. Engineering is now over 90% complete and construction is 48% complete.

Gemco (Australia)

60%

Manganese

110

H1 CY09

1 million tpa of additional

manganese concentrate

On schedule and budget in local currency. Project civil construction is underway and procurement activities progressing well. Project is 65% complete.

Klipspruit (South Africa)

100%

Energy Coal

450

H2 CY09

Incremental 1.8 million tpa export thermal coal

Incremental 2.1 million tpa domestic thermal coal

On schedule and budget. Engineering significantly advanced with civil and plant erection works progressing well. Project is over 50% complete.

Douglas-Middelburg Optimisation (South Africa)

100%

Energy Coal

975

Mid CY10

10 million tpa export thermal coal and 8.5 million tpa domestic thermal coal (sustains current output)

On schedule and budget. Earthworks and civil engineering are well advanced and steel fabrication is progressing as scheduled. All long lead time items ordered.

Newcastle Third Port Project (Australia)

35.5%

Energy Coal

390

CY10

Export coal loading facility 30 million tpa

On schedule and budget. Project is over 20% complete.

MINERALS EXPLORATION

BHP Billiton remains committed to invest in our future through the pursuit of global exploration opportunities for key commodities of interest utilising both in-house capabilities and partnerships.

Grassroots exploration continued on copper targets in AustraliaChileArgentina and the Democratic Republic of Congo (DRC); on nickel targets in AustraliaRussiaColombia and Africa and on diamond targets in the DRC and Canada. Exploration for iron ore, coal, bauxite and manganese was undertaken in a number of regions including AustraliaSouth AmericaRussia and West Africa

For the quarter ended 30 September 2008, BHP Billiton spent US$166 million on minerals exploration, of which US$146 million was expensed. 

 

PETROLEUM EXPLORATION

Exploration and appraisal wells drilled during the quarter or in the process of drilling as at 30 September 2008.

WELL

LOCATION

BHP BILLITON EQUITY

STATUS

Calliance-3

Browse Basin

Western Australia

WA-28-R

20% BHP Billiton 

(Woodside operator)

Hydrocarbons encountered.

Well suspended.

Lambert-8

Dampier Sub-Basin

Western Australia

WA-16-L

16.67% BHP Billiton

(Woodside operator)

Drilling ahead.

Shenzi-81

Green Canyon

Gulf of Mexico

GC610

44% BHP Billiton operator

Drilling ahead.

Petroleum exploration expenditure for the quarter ended 30 September 2008 was US$148 million, of which US$107 million was expensed.

1 Shenzi-8 is the replacement well for Shenzi-7, which was plugged and abandoned after encountering mechanical difficulties in the top-hole section.

  

Further information on BHP Billiton can be found on our website: www.bhpbilliton.com

 

Australia

Samantha Evans, Media Relations

Tel: +61 3 9609 2898 Mobile: +61 400 693 915

email: [email protected]

United Kingdom & South Africa

Andre Liebenberg, Investor Relations 

Tel: +44 20 7802 4131 Mobile: +44 7920 236 974

email: [email protected]

Peter Ogden, Media Relations

Tel: +61 3 9609 2812 Mobile: +61 428 599 190

email: [email protected]

Illtud Harri, Media Relations

Tel: +44 20 7802 4195 Mobile: +44 7920 237 246

email: [email protected]

Leng Lau, Investor Relations

Tel: +61 3 9609 4202 Mobile: +61 403 533 706

email: [email protected]

United States Scott Espenshade, Investor Relations

Tel: +1 713 599 6431 Mobile: +1 713 208 8565

email: [email protected]

Ruban Yogarajah, Media Relations

Tel: US +1 713 966 2907 or UK +44 20 7802 4033MobileUK +44 7827 082 022

email: [email protected]

BHP Billiton Limited ABN 49 004 028 077 Registered in Australia Registered Office: Level 27, 180 Lonsdale Street Melbourne Victoria 3000 Telephone +61 1300 554 757 Facsimile +61 3 9609 3015
BHP Billiton Plc Registration number 3196209 Registered in England and Wales Registered Office: Neathouse Place London SW1V 1BH United Kingdom Telephone +44 20 7802 4000 Facsimile +44 20 7802 4111

The BHP Billiton Group is headquartered in Australia

This information is provided by RNS