17th Apr 2013 07:00
NEWS RELEASE | |
Release Time | IMMEDIATE |
Date | 17 April 2013 |
Number | 06/13 |
BHP BILLITON EXPLORATION AND DEVELOPMENT REPORT
FOR THE QUARTER ENDED 31 MARCH 2013
This report covers the Group's exploration and development activities for the March 2013 quarter. Unless otherwise stated, BHP Billiton's interest in the projects referred to in this report is 100 per cent and references to project schedules are based on calendar years.
Development
BHP Billiton continues to progress 19 major projects in various stages of development. These projects are largely low risk, brownfield expansions, which are expected to deliver first production before the end of the 2015 financial year. In line with prior guidance, no new major projects were approved during the March 2013 quarter.
Our Queensland Coal operations achieved a significant milestone during the March 2013 quarter with first production achieved at the Daunia mine, ahead of schedule. The continued ramp up of this mine and future commissioning of Caval Ridge will underpin an expected increase in the capacity of our Queensland Coal business to 66 million tonnes per annum (100 per cent basis) by the end of the 2014 calendar year. The Broadmeadow Life Extension project also achieved first production ahead of schedule and will not be reported in future Exploration and Development Reports.
Following the sale of BHP Billion's diamonds business to Dominion Diamond Corporation on 10 April 2013, the EKATI Misery Open Pit project is no longer included in this report.
BHP Billiton's Onshore US drilling and development expenditure totalled US$3.2 billion for the nine month period ended March 2013 and guidance for the 2013 financial year remains unchanged at US$4.0 billion. Over 80 per cent of this expenditure will be focused on the liquids rich areas of the Eagle Ford and Permian.
Project and ownership | Share of approved capex (US$m) | Initial production target date | Production capacity (100%) | Quarterly progress |
Petroleum projects | ||||
Macedon (Australia) 71.43% Operator Gas | 1,050 | CY13 | 200 million cubic feet gas per day. | On schedule and budget. Commissioning activities are progressing and the overall project is 96% complete. |
Bass Strait Turrum(a) (Australia) 50% Non operator Gas/Gas Liquids | 1,350 | CY13 | 11,000 bpd condensate and processing capacity of 200 million cubic feet gas per day. | On revised schedule and budget. The overall project is 88% complete. |
Bass Strait Longford Gas Conditioning Plant (Australia) 50% Non operator Gas | 520 | CY16 | Designed to process approximately 400 million cubic feet per day of high CO2 gas. | On schedule and budget. The overall project is 1% complete. |
North West Shelf North Rankin B Gas Compression (Australia) 16.67% Non operator LNG | 850 | CY13 | 2,500 million cubic feet gas per day. | On budget. Steady state production remains on track for CY13. Commissioning activities are progressing and the overall project is 98% complete. |
North West Shelf Greater Western Flank-A (Australia) 16.67% Non operator LNG | 400 | CY16 | To maintain LNG plant throughput from the North West Shelf operations.
| On schedule and budget. The overall project is 44% complete. |
Minerals projects | ||||
Escondida Organic Growth Project 1 (Chile) 57.5% Copper | 2,207 | H1 CY15 | Replaces the Los Colorados concentrator with a new 152,000 tpd plant. | On schedule and budget. The overall project is 32% complete. |
Escondida Oxide Leach Area Project (Chile) 57.5% Copper | 414 | H1 CY14 | New dynamic leaching pad and mineral handling system. Maintains oxide leaching capacity. | On schedule and budget. The overall project is 44% complete. |
WAIO Jimblebar Mine Expansion (Australia) 96% Iron Ore | 3,300(b) | Q1 CY14 | Increases mining and processing capacity to 35 million tpa with incremental debottlenecking opportunities to 55 million tpa. | On schedule and budget. The overall project is 75% complete. |
WAIO Port Hedland Inner Harbour Expansion (Australia) 85% Iron Ore | 1,900(b) | H2 CY12 | Increases total inner harbour capacity to 220 million tpa. Debottlenecking opportunities that would add substantial, low cost capacity are being evaluated. | First production was achieved in Q4 CY12. The overall project is 85% complete. |
WAIO Port Blending and Rail Yard Facilities (Australia) 85% Iron Ore | 1,400(b) | H2 CY14 | Optimises resource and enhances efficiency across the WAIO supply chain. | On schedule and budget. The overall project is 65% complete. |
WAIO Orebody 24 (Australia) 85% Iron Ore | 698 | H2 CY12 | Maintains iron ore production output from the Newman Joint Venture operations. | First production was achieved in Q4 CY12. The overall project is 74% complete. |
Samarco Fourth Pellet Plant (Brazil) 50% Iron Ore | 1,750 | H1 CY14 | Increases iron ore pellet production capacity by 8.3 million tpa to 30.5 million tpa. | On schedule and budget. The overall project is 81% complete. |
Daunia (Australia) 50% Metallurgical Coal | 800 | CY13 | Greenfield mine development with 4.5 million tpa of export metallurgical coal capacity. | First production was achieved in Q1 CY13, ahead of schedule. The final capital cost is expected to be below budget. The overall project is 89% complete. |
Broadmeadow Life Extension (Australia) 50% Metallurgical Coal | 450 | CY13 | Increases productive capacity by 0.4 million tpa and extends life of the mine by 21 years. | First production was achieved in Q1 CY13, ahead of schedule and on budget. The overall project is 99% complete. |
Hay Point Stage Three Expansion (Australia) 50% Metallurgical Coal | 1,250(b) | CY14 | Increases port capacity from 44 million tpa to 55 million tpa and reduces storm vulnerability. | On schedule and budget. The overall project is 60% complete. |
Caval Ridge (Australia) 50% Metallurgical Coal | 1,870(b) | CY14 | Greenfield mine development to produce an initial 5.5 million tpa of export metallurgical coal. | On schedule and budget. The overall project is 59% complete. |
Appin Area 9 (Australia) 100% Metallurgical Coal | 845 | CY16 | Maintains Illawarra Coal's production capacity with a replacement mining domain and capacity to produce 3.5 million tpa of metallurgical coal. | On schedule and budget. The overall project is 37% complete. |
Cerrejon P40 Project (Colombia) 33.3% Energy Coal | 437 | CY13 | Increases saleable thermal coal production by 8 million tpa to approximately 40 million tpa. | On schedule and budget. The overall project is 62% complete. |
Newcastle Third Port Project Stage 3 (Australia) 35.5% Energy Coal | 367 | CY14 | Increases total coal terminal capacity from 53 million tpa to 66 million tpa. | On schedule and budget. The overall project is 69% complete. |
Initial Mineral Resource declared at the Nickel West Venus prospect
BHP Billiton today declared an Inferred Mineral Resource of four million tonnes at an average grade of 3.5 per cent nickel at the Venus prospect near Leinster, which forms part of our wholly owned Nickel West business in Western Australia. This new resource represents a significant body of komatiite hosted, nickel sulphide mineralisation. This discovery demonstrates the success of BHP Billiton's focused brownfield exploration program. A drilling program to further define this nickel sulphide discovery is in progress.
Mineral Resource - Nickel West (100%)(c)
As at 17 April 2013 As at 30 June 2012
Measured Resource | Indicated Resource | Inferred Resource | Total Resource | Total Resource | ||||||||
Commodity Deposit | Ore type | Millions of dry metric tonnes | %Ni | Millions of dry metric tonnes | %Ni | Millions of dry metric tonnes | %Ni | Millions of dry metric tonnes | %Ni | Millions of dry metric tonnes | %Ni | BHP Billiton interest% |
Nickel | ||||||||||||
Venus | High grade massive sulphide | - | - | 1.5 | 6.0 | 1.5 | 6.0 | - | 100 | |||
Low-grade disseminated sulphide | - | - | 2.5 | 1.9 | 2.5 | 1.9 | - | 100 |
Minerals exploration
Greenfield minerals exploration is focused on advancing copper targets within Chile and Peru. Minerals exploration expenditure for the nine month period ended March 2013 was US$523 million, of which US$408 million was expensed.
Petroleum exploration
Exploration and appraisal wells drilled during the quarter or in the process of drilling as at 31 March 2013.
Well | Location | BHP Billiton equity | Status |
Goodwyn North-1 | Western Australia WA-1-L | 16.67% (Woodside operator) | Plugged and abandoned Dry hole |
Raptor-1 | Gulf of Mexico DC535 | 50% (Anadarko operator) | Drilling ahead |
Petroleum exploration expenditure for the nine month period ended March 2013 was US$468 million, of which US$379 million was expensed. Petroleum exploration expenditure of approximately US$775 million is anticipated in the 2013 financial year with the majority of drilling activity scheduled to occur in the Gulf of Mexico.
(a) Initial production through the Turrum facilities, scheduled for the 2013 calendar year, will be low CO2 gas. Additional high CO2 production from the Turrum reservoir will come online with completion of the Longford Gas Conditioning Plant in the 2016 calendar year.
(b) Excludes announced pre-commitment funding.
(c) Competent Person - Mr Marcel Menicheli (MAusIMM).
The statement of Mineral Resources is presented on a 100 per cent basis and is based on information compiled by the above named Competent Person and relates to Mineral Resources estimates as at 17 April 2013. Mr. Menicheli is a full time employee of BHP Billiton, has sufficient experience relevant to the style of mineralisation and type of deposit under consideration and to the activity he is undertaking to qualify as a Competent Person as defined in the 2004 edition of the 'Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves'. Massive and disseminated domains were 3D modelled and estimated with the software Minesight using an Inverse distance squared method (IDS). No cut-off was applied to the resources. Mr Menicheli consents to the inclusion in this report of the matters based on their information in the form and context in which it appears.
This report, together with the Production Report, represents the Interim Management Statement for the purposes of the UK Listing Authority's Disclosure and Transparency Rules. There have been no significant changes in the financial position of the Group in the quarter ended 31 March 2013.
Further information on BHP Billiton can be found at: www.bhpbilliton.com
Media Relations
Australia
Gabrielle Notley Tel: +61 3 9609 3830 Mobile: +61 477 325 803 email: [email protected]
Fiona Hadley Tel: +61 3 9609 2211 Mobile: +61 427 777 908 email: [email protected]
Eleanor Nichols Tel: +61 3 9609 2360 Mobile: +61 407 064 748 email: [email protected]
United Kingdom
Ruban Yogarajah Tel: +44 20 7802 4033 Mobile: +44 7827 082 022 email: [email protected]
Jennifer White Tel: +44 20 7802 7462 Mobile: +44 7827 253 764 email: [email protected]
Americas
Jaryl Strong Tel: +1 713 499 5548 Mobile: +1 281 222 6627 email: [email protected]
| Investor Relations
Australia
James Agar Tel: +61 3 9609 2222 Mobile: +61 467 807 064 email: [email protected]
Andrew Gunn Tel: +61 3 9609 3575 Mobile: +61 402 087 354 email: [email protected]
United Kingdom and South Africa
Tara Dines Tel: +44 20 7802 7113 Mobile: +44 7825 342 232 Email: [email protected]
Americas
Brendan Harris Tel: +44 20 7802 4131 Mobile: +44 7990 527 726 email: [email protected]
Matt Chism Tel: +1 71 359 96158 Mobile: +1 281 782 2238 email: [email protected]
|
BHP Billiton Limited ABN 49 004 028 077 Registered in Australia Registered Office: 180 Lonsdale Street Melbourne Victoria 3000 Australia Tel +61 1300 55 4757 Fax +61 3 9609 3015
|
BHP Billiton Plc Registration number 3196209 Registered in England and Wales Registered Office: Neathouse Place London SW1V 1BH United Kingdom Tel +44 20 7802 4000 Fax +44 20 7802 4111
|
Members of the BHP Billiton Group which is headquartered in Australia |
Related Shares:
BHP Group