Exploration and Development Report 31 Dec 2012

23rd Jan 2013 07:00

RNS Number : 1435W
BHP Billiton PLC
22 January 2013
 



NEWS RELEASE

Release Time

IMMEDIATE

Date

23 January 2013

Number

02/13

 

BHP BILLITON EXPLORATION AND DEVELOPMENT REPORT

FOR THE QUARTER ENDED 31 DECEMBER 2012

 

This report covers the Group's exploration and development activities for the December 2012 quarter. Unless otherwise stated, BHP Billiton's interest in the projects referred to in this report is 100 per cent and references to project schedules are based on calendar years.

 

Development

 

BHP Billiton's unchanged strategy, which is to invest in large, long life, low cost, expandable, upstream assets, diversified by commodity, geography and market, ensures we are well placed to deliver high margin growth in our major businesses. The Group has 20 low risk, largely brownfield projects in various stages of development and these projects, all of which remain on schedule, are expected to generate strong financial returns for our shareholders.

 

The Western Australia Iron Ore (WAIO) Port Hedland Inner Harbour Expansion project achieved first production during the December 2012 quarter as ore was received by the recently installed fifth car dumper at Finucane Island. Debottlenecking and optimisation projects across the WAIO supply chain are currently being evaluated and have the potential to underpin significant growth well beyond recently expanded port capacity of 220 million tonnes per annum (100 per cent basis). WAIO Orebody 24 also delivered first production.

 

During the December 2012 quarter, BHP Billiton announced approval for a US$520 million (BHP Billiton share) investment in the Longford Gas Conditioning Plant (LGCP) project as part of the Gippsland Basin Joint Venture (Australia). The LGCP will add carbon dioxide (CO2) removal capacity which is necessary to condition production from the Bass Strait Turrum project currently in development.

 

In addition, BHP Billiton signed a definitive agreement with PetroChina International Investment (Australia) Pty Ltd during the period to sell its 8.33 per cent interest in the East Browse Joint Venture and 20 per cent interest in the West Browse Joint Venture, located offshore Western Australia, for a cash consideration of US$1.63 billion. The transaction is subject to regulatory approval and other customary conditions. Completion is expected in the first half of calendar year 2013.

 

BHP Billiton's Onshore US drilling and development expenditure for the December 2012 half year was US$2.1 billion and guidance for the 2013 financial year remains unchanged at US$4.0 billion. Over 80 per cent of this expenditure will be focused on the liquids rich areas of the Eagle Ford and Permian.

 

Project and ownership

Share of approved capex (US$m)

Initial production target date

Production capacity (100%)

Quarterly progress

Petroleum projects

Macedon (Australia) 71.43%

Operator Gas

1,050

CY13

200 million cubic feet gas per day.

On schedule and budget. The overall project is 90% complete.

Bass Strait Turrum(a)

(Australia)

50%

Non operator

Gas/Gas Liquids

1,350

CY13

11,000 bpd condensate and processing capacity of 200 million cubic feet gas per day.

On revised schedule and budget. The overall project is 86% complete.

Bass Strait Longford

Gas Conditioning Plant

(Australia)

50%

Non operator

Gas

520

CY16

Designed to process approximately 400 million cubic feet per day of high CO2 gas.

Approval announced. See News Release dated 13 December 2012.

North West Shelf North Rankin B Gas Compression (Australia)

16.67%

Non operator LNG

850

CY13

2,500 million cubic feet gas per day.

On budget. Steady state production remains on track for CY13. The overall project is 98% complete.

North West Shelf Greater Western

Flank-A

(Australia)

16.67%

Non operator LNG

400

CY16

To maintain LNG plant throughput from the North West Shelf operations.

On schedule and budget. The overall project is 38% complete.

Minerals projects

Escondida Organic Growth Project 1

(Chile)

57.5%

Copper

2,207

H1 CY15

Replaces the Los Colorados concentrator with a new 152,000 tpd plant.

On schedule and budget. The overall project is 25% complete.

Escondida Oxide Leach Area Project

(Chile)

57.5%

Copper

414

H1 CY14

New dynamic leaching pad and mineral handling system. Maintains oxide leaching capacity.

On schedule and budget. The overall project is 28% complete.

 

EKATI Misery Open Pit Project(b)

(Canada)

80%

Diamonds

323

CY15

Project consists of a pushback of the existing Misery open pit which was mined from 2001 to 2005.

On schedule and budget. The overall project is 34% complete.

WAIO Jimblebar Mine Expansion

(Australia)

96%

Iron Ore

3,300(c)

Q1 CY14

Increases mining and processing capacity to 35 million tpa with incremental debottlenecking opportunities to 55 million tpa.

On schedule and budget. The overall project is 66% complete.

WAIO Port Hedland Inner Harbour Expansion

(Australia)

85%

Iron Ore

1,900(c)

H2 CY12

Increases total inner harbour capacity to 220 million tpa. Debottlenecking opportunities that would add substantial, low cost capacity are being evaluated.

First production was achieved in Q4 CY12. The overall project is 80% complete.

WAIO Port Blending and Rail Yard Facilities

(Australia)

85%

Iron Ore

1,400(c)

H2 CY14

Optimises resource and enhances efficiency across the WAIO supply chain.

On schedule and budget. The overall project is 55% complete.

WAIO Orebody 24

(Australia)

85%

Iron Ore

698

H2 CY12

Maintains iron ore production output from the Newman Joint Venture operations.

First production was achieved in Q4 CY12. The overall project is 66% complete.

Samarco Fourth Pellet Plant

(Brazil)

50%

Iron Ore

1,750

H1 CY14

Increases iron ore pellet production capacity by 8.3 million tpa to 30.5 million tpa.

On schedule and budget. The overall project is 71% complete.

Daunia

(Australia)

50%

Metallurgical Coal

800

CY13

Greenfield mine development with 4.5 million tpa of export metallurgical coal capacity.

On schedule and budget. The overall project is 82% complete.

Broadmeadow Life Extension

(Australia)

50%

Metallurgical Coal

450

CY13

Increases productive capacity by 0.4 million tpa and extends life of the mine by 21 years.

On schedule and budget. The overall project is 95% complete.

Hay Point Stage Three Expansion

(Australia)

50%

Metallurgical Coal

1,250(c)

CY14

Increases port capacity from 44 million tpa to 55 million tpa and reduces storm vulnerability.

On schedule and budget. The overall project is 57% complete.

Caval Ridge

(Australia)

50%

Metallurgical Coal

1,870(c)

CY14

Greenfield mine development to produce an initial 5.5 million tpa of export metallurgical coal.

On schedule and budget. The overall project is 52% complete.

Appin Area 9

(Australia)

100%

Metallurgical Coal

845

CY16

Maintains Illawarra Coal's production capacity with a replacement mining domain and capacity to produce 3.5 million tpa of metallurgical coal.

On schedule and budget. The overall project is 30% complete.

Cerrejon P40 Project (Colombia)

33.3%

Energy Coal

437

CY13

Increases saleable thermal coal production by 8 million tpa to approximately 40 million tpa.

On schedule and budget. The overall project is 57% complete.

Newcastle Third Port Project Stage 3 (Australia)

35.5%

Energy Coal

367

CY14

Increases total coal terminal capacity from 53 million tpa to 66 million tpa.

On schedule and budget. The overall project is 66% complete.

 

Minerals exploration

 

Greenfield minerals exploration is focused on advancing copper targets within Chile and Peru. Minerals exploration expenditure for the December 2012 half year was US$363 million, of which US$272 million was expensed.

 

Petroleum exploration

 

Exploration and appraisal wells drilled during the quarter or in the process of drilling as at 31 December 2012.

 

Well

Location

BHP Billiton equity

Status

Atlantis East

Gulf of Mexico

DC 211

44%

(BP operator)

Plugged and abandoned

Dry hole

Gunflint-3

Gulf of Mexico

MC948

11.2%

(Noble operator)

Temporarily abandoned

Hydrocarbons encountered

Under evaluation

Ness Deep

Gulf of Mexico

GC507

50%

(Operator)

Plugged and abandoned

Hydrocarbons encountered

Non-commercial

 

Petroleum exploration expenditure for the December 2012 half year was US$308 million, of which US$276 million was expensed. Petroleum exploration expenditure of approximately US$775 million is anticipated in the 2013 financial year with the majority of drilling activity scheduled to occur in the Gulf of Mexico.

 

(a) Initial production through the Turrum facilities, scheduled for the 2013 calendar year, will be low CO2 gas. Additional high CO2 production from the Turrum reservoir will come online with completion of the Longford Gas Conditioning Plant in the 2016 calendar year.

 

(b) BHP Billiton has agreed to sell its diamonds business, comprising its interests in the EKATI Diamond Mine and Diamonds Marketing operations, to Harry Winston Diamond Mines Ltd for an aggregate cash consideration of US$500 million. The transactions are subject to regulatory approval and other customary conditions. Completion is expected in the first half of calendar year 2013.

 

(c) Excludes announced pre-commitment funding.

 

Further information on BHP Billiton can be found at: www.bhpbilliton.com

 

Media Relations

 

Australia

 

Antonios Papaspiropoulos

Tel: +61 3 9609 3830 Mobile: +61 477 325 803

email: [email protected]

 

Fiona Hadley

Tel: +61 3 9609 2211 Mobile: +61 427 777 908

email: [email protected]

 

Eleanor Nichols

Tel: +61 3 9609 2360 Mobile: +61 407 064 748

email: [email protected]

 

United Kingdom

 

Ruban Yogarajah

Tel: +44 20 7802 4033 Mobile: +44 7827 082 022

email: [email protected]

 

Americas

 

Jaryl Strong

Tel: +1 713 499 5548 Mobile: +1 281 222 6627

email: [email protected]

Investor Relations

 

Australia

 

James Agar

Tel: +61 3 9609 2222 Mobile: +61 467 807 064

email: [email protected]

 

Andrew Gunn

Tel: +61 3 9609 3575 Mobile: +61 439 558 454

email: [email protected]

 

United Kingdom and South Africa

 

Tara Dines

Tel: +44 20 7802 7113 Mobile: +44 7825 342 232

Email: [email protected]

 

Americas

 

Brendan Harris

Tel: +44 20 7802 4131 Mobile: +44 7990 527 726

email: [email protected]

 

Matt Chism

Tel: +1 71 359 96158 Mobile: +1 281 782 2238

email: [email protected]

 

BHP Billiton Limited ABN 49 004 028 077

Registered in Australia

Registered Office: 180 Lonsdale Street

Melbourne Victoria 3000 Australia

Tel +61 1300 55 4757 Fax +61 3 9609 3015

 

BHP Billiton Plc Registration number 3196209

Registered in England and Wales

Registered Office: Neathouse Place

London SW1V 1BH United Kingdom

Tel +44 20 7802 4000 Fax +44 20 7802 4111

Members of the BHP Billiton Group which is headquartered in Australia

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 