Exploration and Development Report 30 June 2012

18th Jul 2012 07:00

RNS Number : 8975H
BHP Billiton PLC
17 July 2012
 



NEWS RELEASE

Release Time

IMMEDIATE

Date

18 July 2012

Number

16/12

 

BHP BILLITON EXPLORATION AND DEVELOPMENT REPORT

FOR THE YEAR ENDED 30 JUNE 2012

 

This report covers the Group's exploration and development activities for the June 2012 quarter. Unless otherwise stated, BHP Billiton's interest in the projects referred to in this report is 100 per cent and references to project schedules are based on calendar years.

 

Development

 

BHP Billiton's proven strategy to invest in large, long life, low cost, expandable, upstream assets, diversified by commodity, geography and market ensures we are well positioned to maintain strong momentum and returns in our major businesses, despite significant volatility in the external environment.

 

In the 2012 financial year, six major projects delivered first production while a total investment commitment of US$7.5 billion (BHP Billiton share) enabled another eight major projects to move into execution. In addition, US$2.7 billion (BHP Billiton share) of pre-commitment funding was approved to further progress a series of development options.

 

The six projects to deliver first production included: Western Australia Iron Ore (WAIO) Rapid Growth Project 5 (iron ore); Antamina Expansion and Escondida Ore Access (both copper); Worsley Efficiency & Growth (alumina); North West Shelf CWLH Life Extension (oil); and the RX1 Project (energy coal). The Antamina Expansion, Escondida Ore Access and RX1 projects will not be reported in future Exploration and Development Reports.

 

The eight projects that moved into execution span the ferrous, non-ferrous and energy product groups and included: WAIO Orebody 24 (iron ore); Caval Ridge and Appin Area 9 (both metallurgical coal); Escondida Organic Growth Project 1 and Escondida Oxide Leach Area Project (both copper); North West Shelf Greater Western Flank-A (LNG); Cerrejon P40 Project and the Newcastle Third Port Project Stage 3 (both energy coal).

 

During the June 2012 quarter, BHP Billiton announced approval of the Illawarra Coal Appin Area 9 project and pre-commitment funding of US$708 million (BHP Billiton share) for the Mad Dog Phase 2 project in the deepwater Gulf of Mexico (oil and gas).

 

BHP Billiton's Onshore US drilling and development expenditure totalled US$3.3 billion in the 2012 financial year.

 

Project and ownership

Share of approved capex (US$m)

Initial production target date

Production capacity (100%)

Quarterly progress

Petroleum projects

Macedon (Australia) 71.43% Gas

1,050

CY13

200 million cubic feet gas per day.

On schedule and budget. The overall project is 71% complete.

Bass Strait Kipper (Australia) 32.5% - 50% Gas/Gas Liquids

900

CY12(a)

10,000 bpd condensate and processing capacity of 80 million cubic feet gas per day.

On revised schedule and budget. The overall project is 97% complete.

Bass Strait Turrum (Australia) 50% Gas/Gas Liquids

1,350

CY13

11,000 bpd condensate and processing capacity of 200 million cubic feet gas per day.

On revised schedule and budget. The overall project is 79% complete.

North West Shelf North Rankin B Gas Compression (Australia) 16.67% LNG

850

CY13

2,500 million cubic feet gas per day.

On budget. Steady state production remains on track for CY13. The overall project is 94% complete.

North West Shelf Greater Western Flank-A (Australia) 16.67% LNG

400

CY16

To maintain LNG plant throughput from the North West Shelf operations.

On schedule and budget. The overall project is 15% complete.

Minerals projects

Antamina Expansion (Peru) 33.75% Copper

435

Q1 CY12

Increases ore processing capacity to 130,000 tpd.

First production was achieved in Q1 CY12. The overall project is 92% complete.

Escondida Ore Access (Chile) 57.5% Copper

319

Q2 CY12

The relocation of the in-pit crushing and conveyor infrastructure provides access to higher grade ore.

First production was achieved in Q2 CY12. The overall project is 95% complete.

Escondida Organic Growth Project 1 (Chile) 57.5% Copper

2,207

H1 CY15

Replaces the Los Colorados concentrator with a new 152,000 tpd plant.

On schedule and budget. The overall project is 13% complete.

Escondida Oxide Leach Area Project (Chile) 57.5% Copper

414

H1 CY14

New dynamic leaching pad and mineral handling system. Maintains oxide leaching capacity.

On schedule and budget. The overall project is 8% complete.

 

EKATI Misery Open Pit Project (Canada) 80% Diamonds

323

CY15

Project consists of a pushback of the existing Misery open pit which was mined from 2001 to 2005.

On schedule and budget. The overall project is 26% complete.

WAIO Jimblebar Mine Expansion (Australia) 96% Iron Ore

3,300(b)

Q1 CY14

Increases mining and processing capacity to 35 million tpa with incremental debottlenecking opportunities to 55 million tpa.

On schedule and budget. The overall project is 34% complete.

WAIO Port Hedland Inner Harbour Expansion (Australia) 85% Iron Ore

1,900(b)

H2 CY12

Increases total inner harbour capacity to 220 million tpa with debottlenecking opportunities to 240 million tpa.

On schedule and budget. The overall project is 59% complete.

WAIO Port Blending and Rail Yard Facilities (Australia) 85% Iron Ore

1,400(b)

H2 CY14

Optimises resource and enhances efficiency across the WAIO supply chain.

On schedule and budget. The overall project is 22% complete.

WAIO Orebody 24 (Australia) 85% Iron Ore

698

H2 CY12

Maintains iron ore production output from the Newman Joint Venture operations.

On schedule and budget. The overall project is 20% complete.

Samarco Fourth Pellet Plant (Brazil) 50% Iron Ore

1,750

H1 CY14

Increases iron ore pellet production capacity by 8.3 million tpa to 30.5 million tpa.

On schedule and budget. The overall project is 43% complete.

Daunia (Australia) 50% Metallurgical Coal

800

CY13

Greenfield mine development with capacity to produce 4.5 million tpa of export metallurgical coal.

On schedule and budget. The overall project is 56% complete.

Broadmeadow Life Extension (Australia) 50% Metallurgical Coal

450

CY13

Increases productive capacity by 0.4 million tpa and extends life of the mine by 21 years.

On schedule and budget. The overall project is 74% complete.

Hay Point Stage Three Expansion (Australia) 50% Metallurgical Coal

1,250(b)

CY14

Increases port capacity from 44 million tpa to 55 million tpa and reduces storm vulnerability.

On schedule and budget. The overall project is 45% complete.

Caval Ridge (Australia) 50% Metallurgical Coal

2,100(b)

CY14

Greenfield mine development and expansion of the Peak Downs Mine with capacity to produce 8.0 million tpa of export metallurgical coal.

On schedule and budget. The overall project is 37% complete.

Appin Area 9 (Australia) 100% Metallurgical Coal

845(c)

CY16

Maintains Illawarra Coal's production capacity with a replacement mining domain and capacity to produce 3.5 million tpa of metallurgical coal.

Approval announced. See News Release dated 22 June 2012.

RX1 Project (Australia) 100% Energy Coal

400

H2 CY12

Increases run-of-mine thermal coal production by approximately 4 million tpa.

First production was achieved in Q2 CY12, significantly ahead of schedule and on budget. The overall project is 85% complete.

Cerrejon P40 Project (Colombia) 33.3% Energy Coal

437

CY13

Increases saleable thermal coal production by 8 million tpa to approximately 40 million tpa.

On schedule and budget. The overall project is 35% complete.

Newcastle Third Port Project Stage 3 (Australia) 35.5% Energy Coal

367

CY14

Increases total coal terminal capacity from 53 million tpa to 66 million tpa.

On schedule and budget. The overall project is 43% complete.

 

 

Minerals exploration

Greenfield exploration continued on copper targets in South America, nickel and copper targets in Australia, and iron ore and potash in a number of regions globally.

 

Minerals exploration expenditure for the 2012 financial year was US$1.1 billion, of which US$0.9 billion was expensed.

 

Petroleum exploration

 

Exploration and appraisal wells drilled during the quarter or in the process of drilling as at 30 June 2012.

 

Well

Location

BHP Billiton equity

Status

Gunflint-3

Gulf of Mexico

MC948

11.2%

(Noble operator)

Drilling ahead

Ness Deep

Gulf of Mexico

GC507

50%

(Operator)

Drilling ahead

Julong East

Brunei

Block CA-01

22.5%

(Total operator)

Plugged and abandoned

Hydrocarbons encountered

Jagus East

Brunei

Block CA-01

22.5%

(Total operator)

Plugged and abandoned

Under evaluation

Tallaganda-1

Offshore Western Australia

WA-351-P

55%

(Operator)

Plugged and abandoned

Hydrocarbons encountered

Banambu Deep

Offshore Western Australia

WA-389-P

40%

(Woodside operator)

Abandonment operations in progress

Dry hole

 

Petroleum exploration expenditure for the 2012 financial year was US$1.4 billion, of which US$0.7 billion was expensed. This included US$0.4 billion of exploration expenditure in our recently acquired Onshore US business. Permian Basin appraisal activities for the June 2012 quarter included the successful completion and testing of seven wells with commercial rates. Further success in the Permian Basin is expected to lead to an increase in development expenditure and an associated reduction in exploration expenditure.

 

(a) Facilities ready for first production pending resolution of mercury content.

(b) Excludes announced pre-commitment funding.

(c) Approximately 50 per cent of the US$845 million investment will be capitalised.

 

The 2012 financial year development and exploration expenditures are subject to finalisation.

 

Further information on BHP Billiton can be found at: www.bhpbilliton.com

 

Media Relations

 

Australia

 

Antonios Papaspiropoulos

Tel: +61 3 9609 3830 Mobile: +61 477 325 803

email: [email protected]

 

Kelly Quirke

Tel: +61 3 9609 2896 Mobile: +61 429 966 312

email: [email protected]

 

Fiona Martin

Tel: +61 3 9609 2211 Mobile: +61 427 777 908

email: [email protected]

 

United Kingdom

 

Ruban Yogarajah

Tel: +44 20 7802 4033 Mobile: +44 7827 082 022

email: [email protected]

 

Deirdra McCrackenTel: +44 20 7802 7462 Mobile: +44 7827 253 764Email: [email protected]

 

Americas

 

Jaryl StrongTel: +1 713 499 5548 Mobile: +1 281 222 6627email: [email protected]

Investor Relations

 

Australia

 

James Agar

Tel: +61 3 9609 2222 Mobile: +61 467 807 064

email: [email protected]

 

Andrew Gunn

Tel: +61 3 9609 3575 Mobile: +61 439 558 454

email: [email protected]

 

United Kingdom and South Africa

 

Brendan Harris

Tel: +44 20 7802 4131 Mobile: +44 7990 527 726

email: [email protected]

 

Tara Dines

Tel: +44 20 7802 7113 Mobile: +44 7825 342 232

Email: [email protected]

 

Americas

 

Scott Espenshade

Tel: +1 713 599 6431 Mobile: +1 713 208 8565

email: [email protected]

 

 

BHP Billiton Limited ABN 49 004 028 077

Registered in Australia

Registered Office: 180 Lonsdale Street

Melbourne Victoria 3000 Australia

Tel +61 1300 55 4757 Fax +61 3 9609 3015

 

BHP Billiton Plc Registration number 3196209

Registered in England and Wales

Registered Office: Neathouse Place

London SW1V 1BH United Kingdom

Tel +44 20 7802 4000 Fax +44 20 7802 4111

Members of the BHP Billiton Group which is headquartered in Australia

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 