Exploration and Development Report 30 June 2009

22nd Jul 2009 07:00

RNS Number : 0587W
BHP Billiton PLC
21 July 2009
 



NEWS RELEASE

Release Time

IMMEDIATE

Date

22 July 2009

Number

14/09

BHP BILLITON EXPLORATION AND DEVELOPMENT report

for the QUARTER ENDED 30 June 2009

This report covers the Group's exploration and development activities for the quarter ended 30 June 2009. Unless otherwise stated, BHP Billiton's interest in the projects referred to in this report is 100 percent and references to project schedules are based on calendar years.

Development

First production was successfully achieved during the quarter at the Gemco Expansion Project in Australia (manganese) and the Atlantis North development in the deep water Gulf of Mexico (oil and gas). Both projects were ahead of schedule and within budget. In addition, the Alumar Refinery Expansion in Brazil (alumina) announced first production on 9 July. These projects will no longer be reported in future Exploration and Development Reports.

 

During the year ended 30 June 2009 an additional four projects to those noted above achieved first production and four projects were sanctioned. The four commissioned projects, all oil and gas, were NeptuneNorth West Shelf Train 5, North West Shelf Angel and Shenzi. The sanctioned projects were the Bass Strait Turrum, Angostura Gas Phase II and the North West Shelf Cossack, Wanaea, Lambert, Hermes (CWLH) Life Extension projects (all oil and gas), as well as the Western Australia Iron Ore Rapid Growth Project 5 (iron ore).

Project And Ownership

Share Of Approved Capex US$M

Initial Production Target Date

Production Capacity (100%)

Quarterly

Progress

Petroleum Projects

Atlantis North (USA)

44%

Oil/Gas

185

H2 CY09

Tieback to 

Atlantis South

First production achieved 5 June 2009, ahead of schedule and within budget.

Pyrenees (Australia)

71.43%

Oil/Gas

1,200

H1 CY10

96,000 barrels of oil and 60 million cubic feet gas per day 

On schedule and budget. Floating Production Storage and Offtake (FPSO) conversion continues. Final 3 of 15 tophole sections drilled and 2 producers and 1 injector well completed. Installation of subsea facilities continues.

Angostura Gas Phase II (Trinidad and Tobago)

45%

Gas

180

H1 CY11

280 million cubic feet gas per day

On schedule and budget. Platform fabrication continues.

Bass Strait Kipper (Australia)

32.5% - 50%

Gas/Gas Liquids

500

CY11

10,000 bpd condensate and processing capacity of 80 million cubic feet gas per day

On schedule and budget. West Tuna platform retrofit work continuing.

Bass Strait Turrum (Australia)

50%

Gas/Gas Liquids

625

CY11

11,000 bpd condensate and processing capacity of 200 million cubic feet gas per day 

On schedule and budget. Commenced jacket and topsides fabrication ahead of schedule.

North West Shelf CWLH Life Extension (Australia)

16.67%

Oil

245

CY11

Replacement vessel with capacity of 

60,000 bpd oil

On schedule and budget. Floating Production Storage and Offtake (FPSO) conversion continues.

North West Shelf North Rankin B Gas Compression (Australia)

16.67%

LNG

850

CY12

2,500 million cubic feet gas per day 

On schedule and budget. Jacket fabrication continuing ahead of schedule.

Minerals Projects

Alumar - Refinery Expansion (Brazil)

36%

Alumina

900

Q2 CY09

2 million tpa of additional alumina

First production announced. See News Release dated 9 July 2009.

Worsley Efficiency & Growth (Australia)

86%

Alumina

1,900

H1 CY11

1.1 million tpa of additional alumina

On schedule and budget. Engineering is 75% complete and construction has commenced. Capital expenditure profile is being managed to reflect changing market conditions.

Iron Ore (Western Australia)

RGP4

86.2%

Iron Ore

1,850

H1 CY10

26 million tpa of additional iron ore system capacity

On schedule and budget. Engineering is 99% complete and construction is over 90% complete.

Iron Ore (Western Australia)

RGP5

85%

Iron Ore

4,800

H2 CY11

50 million tpa additional iron ore system capacity

On schedule and budget. Engineering is currently 70% complete. Procurement and contracting activities are well advanced. Construction activities are continuing at all sites.

Gemco (Australia)

60%

Manganese

110

H1 CY09

1 million tpa of additional manganese concentrate

First ore delivered ahead of schedule and within budget. 

Klipspruit (South Africa)

100%

Energy Coal

450

H2 CY09

Incremental 1.8 million tpa export thermal coal. Incremental 2.1 million tpa domestic thermal coal

On schedule and budget. Commissioning of the crushing stream and coal processing plant is progressing. Project is 91% complete.

Douglas-Middelburg Optimisation (South Africa)

100%

Energy Coal

975

Mid CY10

10 million tpa export thermal coal and 8.5 million tpa domestic thermal coal (sustains current output)

On schedule and budget. Construction activities are progressing and first stacker reclaimer delivered. Steel erection and coal processing plant equipment installation remains on schedule. Project is 70% complete.

Newcastle Third Port Project (Australia)

35.5%

Energy Coal

390

CY10

30 million tpa export coal loading facility

On schedule and budget. Stacker reclaimer components delivered and construction activities are progressing well. Project is greater than 63% complete.

Minerals Exploration

BHP Billiton continues to identify and prioritise various exploration activities. All of the exploration activities are reviewed regularly to ensure that we are capturing value accretive opportunities for future development.

For the year ended 30 June 2009, BHP Billiton spent US$695 million on minerals exploration, of which US$609 million was expensed. This includes US$94 million of exploration spend for potash in SaskatchewanCanada.

Petroleum Exploration

Exploration and appraisal wells drilled during the quarter or in the process of drilling as at 30 June 2009.

Well

Location

BHP Billiton Equity

Status

Mad Dog South-1

Green Canyon Gulf of Mexico GC 826

23.9 % BHP Billiton

(BHP Billiton operator for this well - BP operator for all other activities)

Hydrocarbons encountered. Completing sidetrack drilling operations. 

Brecknock-4

Browse Basin Western Australia WA-32-R

8.33% BHP Billiton

(Woodside operator) 

Plugged and suspended.

Dry hole.

Petroleum exploration expenditure for the year ended 30 June 2009 was US$548 million, of which US$400 million was expensed.

Further information on BHP Billiton can be found on our website: www.bhpbilliton.com

Australia

Samantha Evans, Media Relations

Tel: +61 3 9609 2898 Mobile: +61 400 693 915

email: [email protected]

United Kingdom

Andre Liebenberg, Investor Relations 

Tel: +44 20 7802 4131 Mobile: +44 7920 236 974

email: [email protected]

Peter Ogden, Media Relations

Tel: +61 3 9609 2812 Mobile: +61 428 599 190

email: [email protected]

Illtud Harri, Media Relations

Tel: +44 20 7802 4195 Mobile: +44 7920 237 246

email: [email protected]

Kelly Quirke, Media Relations

Tel: +61 3 9609 2896 Mobile: +61 429 966 312

email: [email protected]

United States

Scott Espenshade, Investor Relations

Tel: +1 713 599 6431 Mobile: +1 713 208 8565

email: [email protected]

Leng Lau, Investor Relations

Tel: +61 3 9609 4202 Mobile: +61 403 533 706

email: [email protected] 

Ruban Yogarajah, Media Relations

Tel: US +1 713 966 2907 or UK +44 20 7802 4033

MobileUK +44 7827 082 022

email: [email protected]

South Africa

Bronwyn Wilkinson, Investor and Media Relations

Tel: +44 20 7802 4015 Mobile: +44 7500 785 892

email: [email protected] 

BHP Billiton Limited ABN 49 004 028 077

Registered in Australia

Registered Office: 180 Lonsdale Street

Melbourne Victoria 3000 Australia

Tel +61 1300 55 4757 Fax +61 3 9609 3015

BHP Billiton Plc Registration number 3196209

Registered in England and Wales

Registered Office: Neathouse Place

London SW1V 1BH United Kingdom

Tel +44 20 7802 4000 Fax +44 20 7802 4111

A member of the BHP Billiton group which is headquartered in Australia

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCSEWEEFSUSELW

Related Shares:

BHP Group
FTSE 100 Latest
Value8,463.46
Change46.12