30th Oct 2012 07:00
Issued by: | BHP Billiton Plc
|
Date: | 30 October 2012
|
To: | London Stock Exchange JSE Limited
|
For Release: | Immediately
|
Contact: | Elizabeth Hobley +44 (0) 20 7802 4054
|
BHP Billiton Plc - Delivering value through optimisation |
UK Listing Authority Submission
BHP Billiton Chief Executive Ferrous and Coal, Marcus Randolph, will present on the Company's Iron Ore and Metallurgical Coal businesses at a briefing in Sydney today.
A copy of the presentation has been submitted to the National Storage Mechanism and will shortly be available for inspection at: www.hemscott.com/nsm.do.
The document may also be accessed via BHP Billiton's website (www.bhpbilliton.com) or by using the following web link: http://www.bhpbilliton.com/home/investors/reports/Documents/2012/121030_DeliveringValueThroughOptimisation.pdf
Slide 7: Pursuing the capital efficient tonne
·; Our focus has shifted from the marginal tonne to the capital efficient tonne
·; Debottlenecking opportunities have the potential to release significant capacity well beyond 220 mtpa (100% basis)
·; We will exercise the options with the lowest capital intensity and highest returns to unlock substantial value
Slide 10: Debottleneck and optimise the supply chain
·; Targeting the release of substantial capacity at low capital intensity
Slide 13: Port: deliver the capital efficient tonne
·; 5th car dumper installed end CY12
·; Optimised throughput potential 55-60 mtpa per dumper
·; 7th and 8th shiploaders recently installed at Nelson Point
·; Optimised throughput potential 35-40 mtpa per shiploader
·; Low cost opportunity to debottleneck the conveyor, stockyard and stacker-reclaimer system
Slide 14: Port: low cost debottlenecking of our conveyors and stockyards
·; Latent capacity in our car dumpers and shiploaders has been tested and proven
·; Complex interconnections are constraining the system
·; System capacity will rise significantly as we debottleneck our stockyards and conveyors
Slide 16: Rail: substantial upside in our existing dual track
·; Dual track can deliver more than 300 mtpa of capacity with modest investment
Slide 17: Mines: readily expandable
·; Mobile crushers can unlock 20 mtpa of capacity
·; Jimblebar built for expansion beyond 35 mtpa
·; One new mine required to achieve >300 mtpa
BHP Billiton Plc Registration number 3196209
Registered in England and Wales
Registered Office: Neathouse Place London SW1V 1BH United Kingdom
A member of the BHP Billiton Group which is headquartered in Australia