BHP Billiton Quarterly Exploration Report

21st Jan 2009 07:00

RNS Number : 9760L
BHP Billiton PLC
20 January 2009
 



NEWS RELEASE

Release Time

IMMEDIATE

Date

21 January 2009

Number

03/09

BHP BILLITON QUARTERLY REPORT ON 

EXPLORATION AND DEVELOPMENT ACTIVITIES

QUARTER ENDED 31 DECEMBER 2008

DEVELOPMENT

BHP Billiton's strong balance sheet allows us to invest through the cycle with a highly disciplined and value-focused approach.

Highlighting our commitment to value accretive longer term growth, we sanctioned two projects during the quarter, being the Western Australia Iron Ore Rapid Growth Project 5 (RGP5), and the North West Shelf Cossack, Wanaea, Lambert, Hermes (CWLH) Life Extension projects.

PROJECT AND OWNERSHIP

SHARE OF APPROVED CAPEX US$M

INITIAL PRODUCTION TARGET DATE

PRODUCTION CAPACITY (100%)

QUARTERLY PROGRESS

 

 

 

Petroleum Projects

 

Shenzi (USA)

44%

Oil/Gas

1,940

Mid CY09

100,000 barrels of oil and 50 million cubic feet gas per day

Ahead of schedule and on budget. Hook-up and commissioning continuing. Six wells drilled and completed.

Atlantis North (USA)

44%

Oil/Gas

185

H2 CY09

Tieback to Atlantis South

On schedule and budget. Manifold fabrication continuing.

 

Pyrenees

(Australia)

71.43% 

Oil/Gas

1,200

H1 CY10

96,000 barrels of oil and 60 million cubic feet gas per day 

On schedule and budget. Subsea hardware delivery commenced and Floating Production Storage and Offtake (FPSO) conversion continues. 

 

Angostura Gas Phase II (Trinidad and Tobago)

45%

Gas

180

H1 CY11

280 million cubic feet gas per day

On schedule and budget. Awarded transportation and installation contract. Executed National Gas Company Interconnection Agreement.

Bass Strait Kipper (Australia)

32.5% - 50%

Gas/Gas Liquids

500

CY11

10,000 bpd condensate and processing capacity of 80 million cubic feet gas per day

On schedule and budget. Drilling rig secured. Detailed engineering progressing and commenced West Tuna platform retrofit work.

Bass Strait Turrum (Australia)

50%

Gas/Gas Liquids

625

CY11

11,000 bpd condensate and processing capacity of 200 million cubic feet gas per day 

On schedule and budget. Engineering and procurement progressing.

North West Shelf CWLH Life Extension

(Australia)

16.67%

Oil

245

CY11

Replacement vessel with capacity of 60,000 bpd oil

The project was sanctioned during the quarter. See News Release dated 3 December 2008.

North West Shelf North Rankin B Gas Compression 

(Australia)

16.67%

LNG

850

CY12

2,500 million cubic feet gas per day 

On schedule and budget. Detailed engineering and procurement well advanced. Jacket fabrication commenced.

Minerals Projects

 

Alumar - Refinery Expansion (Brazil) 36%

Alumina

900

Q2 CY09

2 million tpa of additional alumina

On schedule and revised budget. Engineering is complete and procurement well advanced. Construction is 82% complete with the project overall 92% complete.

Worsley Efficiency & Growth (Australia)

86%

Alumina

1,900

H1 CY11

1.1 million tpa of additional alumina

On schedule and budget. Engineering is 49% complete and construction camp now operational.

Iron Ore (Western Australia)

RGP4

86.2%

Iron Ore

1,850

H1 CY10

26 million tpa

additional iron ore system capacity

On schedule and budget. Engineering is now over 95% complete and construction is nearing 70% complete.

Iron Ore (Western Australia)

RGP5

85%

Iron Ore

4,800

H2 CY11

50 million tpa additional iron ore system capacity

The project was sanctioned during the quarter. See News Release dated 25 November 2008. Preliminary engineering and construction activities have commenced. 

Gemco (Australia)

60%

Manganese

110

H1 CY09

1 million tpa of additional

manganese concentrate

On schedule and budget in local currency. Cyclone tower operational and remainder of installation activities progressing well. Project is 77% complete.

Klipspruit (South Africa)

100%

Energy Coal

450

H2 CY09

Incremental 1.8 million tpa export thermal coal

Incremental 2.1 million tpa domestic thermal coal

On schedule and budget. Earthworks and civil and mechanical construction progressing well. The project is 70% complete with detailed commission planning commenced.

Douglas-Middelburg Optimisation (South Africa)

100%

Energy Coal

975

Mid CY10

10 million tpa export thermal coal and 8.5 million tpa domestic thermal coal (sustains current output)

On schedule and budget. Construction activities are progressing well with steel erection commencing as scheduled. The project is 34% complete.

Newcastle Third Port Project (Australia)

35.5%

Energy Coal

390

CY10

30 million tpa export coal loading facility

On schedule and budget. Project is over 35% complete.

MINERALS EXPLORATION

BHP Billiton continues to identify and prioritise various exploration activities. All of the exploration activities are reviewed regularly to ensure that we are capturing value accretive opportunities for future development. 

Selection study work on the proposed Olympic Dam Expansion (Australia) is effectively complete. A Draft Environmental Impact Statement (EIS) based on the five stage project configuration has been provided to the Federal, South Australian and Northern Territory Governments for a compliance review, with the intention that it be released for public comment during the first half of calendar year 2009. Pending government approvals for the EIS and consistent with the prevailing economic circumstances, project activity will be scaled back to that necessary to support the approvals process and the study of a number of mining and processing technology options. Olympic Dam Expansion expenditure for the six months ended 31 December 2008 was US$112 million, of which US$29 million was capitalised.

Grassroots exploration continued on targets in AustraliaChileArgentinaZambia and the Democratic Republic of Congo (DRC); and on diamond targets in Canada. Exploration for iron ore, coal, bauxite and manganese was undertaken in a number of regions including AustraliaSouth AmericaRussia and West Africa

For the six months ended 31 December 2008, BHP Billiton spent US$357 million on minerals exploration, of which US$313 million was expensed.

PETROLEUM EXPLORATION

Exploration and appraisal wells drilled during the quarter or in the process of drilling as at 31 December 2008.

WELL

LOCATION

BHP BILLITON EQUITY

STATUS

Lambert-8

Dampier Sub-Basin

Western Australia

WA-16-L

16.67% BHP Billiton

(Woodside operator)

Plugged and abandoned. Hydrocarbons encountered.

Lambert West

Dampier Sub-Basin

Western Australia

WA-16-L

16.67% BHP Billiton

(Woodside operator)

Plugged and abandoned. Hydrocarbons encountered.

Lady Nora-2

Dampier Sub-Basin

Western Australia

WA-28-P

16.67% BHP Billiton

(Woodside operator)

Plugged and abandoned. Hydrocarbons encountered.

Nereus-1

Dampier Sub-Basin

Western Australia

WA-28-P

16.67% BHP Billiton

(Woodside operator)

Plugged and abandoned. Dry hole.

Tidepole-2

Dampier Sub-Basin

Western Australia

WA-5-L

16.67% BHP Billiton

(Woodside operator)

Drilling ahead.

Torosa-5

Browse Basin

Western Australia

WAR

8.33% BHP Billiton

(Woodside operator)

Plugging and abandoning. Hydrocarbons encountered.

Puma-4

Green Canyon

Gulf of Mexico

GC823-2 

29.805% BHP Billiton

(BP Operator)

Drilling ahead.

Shenzi-8

Green Canyon

Gulf of Mexico

GC610

44% BHP Billiton, operator

Hydrocarbons encountered. Suspended.

Petroleum exploration expenditure for the six months ended 31 December 2008 was US$263 million, of which US$183 million was expensed

Further information on BHP Billiton can be found on our website: www.bhpbilliton.com

Australia
Samantha Evans, Media Relations
Tel: +61 3 9609 2898 Mobile: +61 400 693 915
United Kingdom & South Africa
Andre Liebenberg, Investor Relations 
Tel: +44 20 7802 4131 Mobile: +44 7920 236 974
 
Peter Ogden, Media Relations
Tel: +61 3 9609 2812 Mobile: +61 428 599 190
Illtud Harri, Media Relations
Tel: +44 20 7802 4195 Mobile: +44 7920 237 246
 
Kelly Quirke, Media Relations
Tel: +61 3 9609 2896 Mobile: +61 429 966 312
 
United States Scott Espenshade, Investor Relations
Tel: +1 713 599 6431 Mobile: +1 713 208 8565
 
Leng Lau, Investor Relations
Tel: +61 3 9609 4202 Mobile: +61 403 533 706
 
Ruban Yogarajah, Media Relations
Tel: US +1 713 966 2907 or UK +44 20 7802 4033Mobile: UK +44 7827 082 022
 
 
BHP Billiton Limited ABN 49 004 028 077
Registered in Australia
Registered Office: 180 Lonsdale Street
Melbourne Victoria 3000 Australia
Tel +61 1300 55 4757 Fax +61 3 9609 3015
 
BHP Billiton Plc Registration number 3196209
Registered in England and Wales
Registered Office: Neathouse Place
London SW1V 1BH United Kingdo
Tel +44 20 7802 4000 Fax +44 20 7802 4111
 
A member of the BHP Billiton group which is headquartered in Australia
 
This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCMGGZMFGNGLZZ

Related Shares:

BHP Group
FTSE 100 Latest
Value8,463.46
Change46.12