BHP Billiton Exploration & Development Report

20th Jan 2010 07:00

RNS Number : 8145F
BHP Billiton PLC
19 January 2010
 



NEWS RELEASE

Release Time

IMMEDIATE

Date

20 January 2010

Number

03/10

BHP BILLITON EXPLORATION AND DEVELOPMENT REPORT

FOR THE QUARTER ENDED 31 DECEMBER 2009

This report covers the Group's exploration and development activities for the quarter ended 31 December 2009. Unless otherwise stated, BHP Billiton's interest in the projects referred to in this report is 100 percent and references to project schedules are based on calendar years.

Development

During the December 2009 quarter Western Australia Iron Ore Rapid Growth Project 4 (RGP4) achieved first production, ahead of schedule and within budget. Klipspruit expansion project (energy coal) in South Africa is essentially complete and has delivered first coal. These projects will not be reported in future Exploration and Development Reports.

The approval of the Antamina Expansion project (base metals) in Peru was also announced on 5 January 2010.

On 18 January 2010 BHP Billiton announced US$267 million (BHP Billiton share) of pre-approval capital expenditure to accelerate the development of the Caval Ridge and Hay Point Coal Terminal Stage 3 Expansion (HPX3) projects. The funds will be used for feasibility studies, the procurement of long-lead time items and initial project activities.

On 20 January 2010 BHP Billiton announced approval for US$240 million (BHP Billiton share 100%) of capital expenditure to support the development of the first stages of the Jansen Potash Project in SaskatchewanCanada. This pre-approval expenditure will facilitate the early stage work for the establishment of the production and service shafts. The Jansen project is currently being designed to ultimately produce approximately 8 million tonnes per annum of agricultural grade potash, and represents BHP Billiton's first production of potash.

Future Exploration and Development Reports will disclose progress updates for all projects with US$250 million or above of BHP Billiton share of capital investment, which aligns disclosures with internal approval thresholds. Development projects that are currently disclosed with an investment amount below this threshold will continue to be shown until first production is announced.

Project And Ownership

Share Of Approved Capex US$M

Initial Production Target Date

Production Capacity (100%)

Quarterly Progress

Petroleum Projects

Pyrenees (Australia) 71.43% Oil/Gas

1,200

H1 CY10

96,000 barrels of oil and 60 million cubic feet gas per day 

On schedule and budget. Floating Production Storage and Offtake (FPSO) arrived on location and commissioning continues. 9 wells completed (7 producers, 1 gas injector and 1 water injector).

Angostura Gas Phase II (Trinidad and Tobago) 45% Gas

180

H1 CY11

280 million cubic feet gas per day

On schedule and budget. Jacket fabrication completed. Topsides fabrication continues.

Bass Strait Kipper (Australia) 32.5% - 50% Gas/Gas Liquids

500

CY11

10,000 bpd condensate and processing capacity of 80 million cubic feet gas per day

Schedule and budget under review following advice from operator. West Tuna platform retrofit work continuing.

Bass Strait Turrum (Australia) 50% Gas/Gas Liquids

625

CY11

11,000 bpd condensate and processing capacity of 200 million cubic feet gas per day 

On schedule and budget. Platform fabrication continues.

North West Shelf CWLH Life Extension (Australia) 16.67% Oil

245

CY11

Replacement vessel with capacity of  60,000 bpd oil

On schedule and budget. Floating Production Storage and Offtake (FPSO) conversion continues.

North West Shelf North Rankin B Gas Compression (Australia) 16.67% LNG

850

CY12

2,500 million cubic feet gas per day 

On schedule and budget. Jacket fabrication continuing ahead of schedule.

Minerals Projects

Worsley Efficiency & Growth (Australia) 86% Alumina

1,900

H1 CY11

1.1 million tpa of additional alumina

On schedule and budget. Engineering is near complete, procurement and contracting activities are well advanced and construction is 11% complete.

Antamina Expansion (Peru) 33.75% Copper

435

Q4 CY11

Increases ore processing capacity to 130,000 tpd

Approval announced, see news release dated 5 January 2010.

Iron Ore (Western Australia) RGP4 86.2% Iron Ore

1,850

H1 CY10

26 million tpa of additional iron ore system capacity

First ore produced ahead of schedule. The official opening of the Newman Hub occurred in November 2009.

Iron Ore (Western Australia) RGP5 85% Iron Ore

4,800

H2 CY11

50 million tpa additional iron ore system capacity

On schedule and budget. Engineering is over 85% complete, procurement and contracting activities are well advanced. Construction has reached 25% complete.

Klipspruit (South Africa) 100% Energy Coal

450

H2 CY09

Incremental 1.8 million tpa export thermal coal. Incremental 2.1 million tpa domestic thermal coal

On schedule and budget. Commissioning of coal processing plant is essentially complete. Relocation to new industrial and office complexes successful. Project is 99% complete.

Douglas-Middelburg Optimisation (South Africa) 100% Energy Coal

975

Mid CY10

10 million tpa export thermal coal and 8.5 million tpa domestic thermal coal (sustains current output)

On schedule and budget. Construction activities are progressing well with installation of all mechanical equipment at the ROM Tip complete. Erection of the coal processing plant continues as scheduled. Project is 84% complete.

Newcastle Third Port Project (Australia) 35.5% Energy Coal

390

CY10

30 million tpa export coal loading facility

On schedule and budget. Inbound concrete systems and structures completed with conveyor modules and substation installation progressing well. Project is 88% complete.

MAC20 Project (Australia) 100% Energy Coal

260

H1 CY11

Increases saleable thermal coal production by approximately 3.5 million tpa 

On schedule and budget. Coal handling and preparation plant construction commenced in September 2009. Project is 40% complete.

Minerals Exploration

BHP Billiton continues to identify and prioritise various exploration activities. All of the exploration activities are reviewed regularly to ensure that we are capturing value accretive opportunities for future development.

Grassroots exploration continued on copper targets in ChileArgentina and Zambia; nickel targets in Australia; manganese targets in Gabon; and diamond targets in Canada. Exploration for iron ore, coal, bauxite and manganese was undertaken in a number of regions including AustraliaSouth AmericaRussia and West Africa.

For the half year ended 31 December 2009, BHP Billiton spent US$239 million on minerals exploration, of which US$220 million was expensed.

Petroleum Exploration

Exploration and appraisal wells drilled during the quarter or in the process of drilling as at 31 December 2009.

Well

Location

BHP Billiton Equity

Status

Knotty Head-2 

Green Canyon Gulf of Mexico GC 512

25% BHP Billiton (Nexen operator)

Drilling ahead

Dabakan-1

Sandakan Basin Philippines

SC-56

25% BHP Billiton

(Exxon operator)

Hydrocarbons encountered

Deep Blue-1

Green Canyon Gulf of Mexico

GC 723

31.875% BHP Billiton

(Noble operator) 

Drilling ahead

Double Mountain-1

Green Canyon Gulf of Mexico

GC 555

70% BHP Billiton 

(operator)

Drilling ahead

Wolverine-1

Laurentian Basin Canada

E.L. 1087R

45% BHP Billiton

(CoP operator)

Drilling ahead

SE Remora-1

Gippsland Basin Australia

VIC/RL4

50% BHP Billiton

(Exxon operator)

Drilling ahead

Consistent with BHP Billiton's growth strategy, the total forecast exploration expenditure for the 2010 financial year has increased by US$200 million to US$800 million. This is primarily due to increased drilling activity.

Petroleum exploration expenditure for the half year ended 31 December 2009 was US$200 million, of which US$75 million was expensed.  Further information on BHP Billiton can be found on our website: www.bhpbilliton.com

Australia

Samantha Evans, Media Relations

Tel: +61 3 9609 2898 Mobile: +61 400 693 915

email: [email protected]

United Kingdom & South Africa

Andre Liebenberg, Investor Relations 

Tel: +44 20 7802 4131 Mobile: +44 7920 236 974

email: [email protected]

Amanda Buckley, Media Relations

Tel: +61 3 9609 2209 Mobile: +61 419 801 349

email: [email protected]

Illtud Harri, Media Relations

Tel: +44 20 7802 4195 Mobile: +44 7920 237 246

email: [email protected]

Kelly Quirke, Media Relations

Tel: +61 3 9609 2896 Mobile: +61 429 966 312

email: [email protected]

Americas

Scott Espenshade, Investor Relations

Tel: +1 713 599 6431 Mobile: +1 713 208 8565

email: [email protected]

Leng Lau, Investor Relations

Tel: +61 3 9609 4202 Mobile: +61 403 533 706

email: [email protected] 

Ruban Yogarajah, Media Relations

Tel: US +1 713 966 2907 or UK +44 20 7802 4033

MobileUK +44 7827 082 022

email: [email protected]

BHP Billiton Limited ABN 49 004 028 077

Registered in Australia

Registered Office: 180 Lonsdale Street

Melbourne Victoria 3000 Australia

Tel +61 1300 55 4757 Fax +61 3 9609 3015

BHP Billiton Plc Registration number 3196209

Registered in England and Wales

Registered Office: Neathouse Place

London SW1V 1BH United Kingdom

Tel +44 20 7802 4000 Fax +44 20 7802 4111

A member of the BHP Billiton group which is headquartered in Australia