BHP Billiton Exploration and Development Report

22nd Apr 2009 07:00

RNS Number : 9475Q
BHP Billiton PLC
21 April 2009
 



NEWS RELEASE

Release Time

IMMEDIATE

Date

22 April 2009

Number

08/09

BHP BILLITON QUARTERLY REPORT ON

EXPLORATION AND DEVELOPMENT ACTIVITIES

QUARTER ENDED 31 MARCH 2009

This report covers the Group's exploration and development activities for the quarter ended 31 March 2009. This report, together with the Production Report, represents the Interim Management Statement for the purposes of the UK Listing Authority's Disclosure and Transparency Rules. Other than the issue of US$3.25 billion in global bonds, as announced on 19 March 2009, there have been no significant changes to the financial position of the Group in the quarter ended 31 March 2009. Unless otherwise stated, BHP Billiton's interest in the projects referred to in this report is 100 percent and references to project schedules are based on calendar years.

Development

During the quarter, Shenzi development in the deep water Gulf of Mexico (oil and gas) delivered first production ahead of schedule within budget. This project will not be reported in future Exploration & Development Reports.

Project and Ownership

Share of Approved Capex US$M

Initial Production Target Date

Production Capacity (100%)

Quarterly Progress

Petroleum Projects

Shenzi (USA

44%

Oil/Gas

1,940

Mid CY09

100,000 barrels of oil and 50 million cubic feet gas per day

First production announced, ahead of schedule and within budget. See News Release dated 25 March 2009.

Atlantis North (USA)

44%

Oil/Gas

185

H2 CY09

Tieback to 

Atlantis South

On schedule and budget. Manifold fabrication continuing.

Pyrenees (Australia)

71.43%

Oil/Gas

1,200

H1 CY10

96,000 barrels of oil and 60 million cubic feet gas per day 

On schedule and budget. Floating Production Storage and Offtake (FPSO) conversion continued. Drilling commenced as well as installation of subsea facilities.

Angostura Gas Phase II (Trinidad and Tobago)

45%

Gas

180

H1 CY11

280 million cubic feet gas per day

On schedule and budget. Commenced platform fabrication.

Bass Strait Kipper (Australia)

32.5% - 50%

Gas/Gas Liquids

500

CY11

10,000 bpd condensate and processing capacity of 80 million cubic feet gas per day

On schedule and budget. West Tuna platform retrofit work continuing.

Bass Strait Turrum (Australia)

50%

Gas/Gas Liquids

625

CY11

11,000 bpd condensate and processing capacity of 200 million cubic feet gas per day 

On schedule and budget. Engineering achieved to support procurement schedule.

North West Shelf CWLH Life Extension (Australia)

16.67%

Oil

245

CY11

Replacement vessel with capacity of 

60,000 bpd oil

On schedule and budget. Floating Production Storage and Offtake (FPSO) conversion commenced.

North West Shelf North Rankin B Gas Compression (Australia)

16.67%

LNG

850

CY12

2,500 million cubic feet gas per day 

On schedule and budget. Jacket fabrication continuing. Topsides design review milestone completed.

Minerals Projects

Alumar - Refinery Expansion (Brazil)

36%

Alumina

900

Q2 CY09

2 million tpa of additional alumina

On schedule and revised budget. Engineering is complete and procurement nearing completion. Construction is 90% complete with the project overall 95% complete.

Worsley Efficiency & Growth (Australia)

86%

Alumina

1,900

H1 CY11

1.1 million tpa of additional alumina

Initial production date and total project scope and budget remain unchanged. Engineering is 58% complete and construction has commenced. The timing of capital expenditure will be modified in line with our disciplined cash flow management. The main component being the Marradong mine development; which is expected to be commissioned in 2012.

Iron Ore (Western Australia)

RGP4 86.2%

Iron Ore

1,850

H1 CY10

26 million tpa of additional iron ore system capacity

On schedule and budget. Engineering is over 95% complete and construction is nearing 80% complete.

Iron Ore (Western Australia)

RGP5 85%

Iron Ore

4,800

H2 CY11

50 million tpa additional iron ore system capacity

On schedule and budget. Engineering is currently 50% complete, procurement and contracting activities are advancing. Construction activities have commenced.

Gemco (Australia)

60%

Manganese

110

H1 CY09

1 million tpa of additional manganese concentrate

On schedule and budget in local currency. All major components on site in preparation for installation. Project is 77% complete.

Klipspruit (South Africa)

100%

Energy Coal

450

H2 CY09

Incremental 1.8 million tpa export thermal coal. Incremental 2.1 million tpa domestic thermal coal

On schedule and budget. First coal to Run Of Mine stockpile achieved. Processing plant and industrial buildings progressing well. The project is 81% complete.

Douglas-Middelburg Optimisation (South Africa)

100%

Energy Coal

975

Mid CY10

10 million tpa export thermal coal and 8.5 million tpa domestic thermal coal (sustains current output)

On schedule and budget. Construction activities are accelerating as scheduled. Steel erection and coal processing plant equipment installation progressing. The project is 48% complete.

Newcastle Third Port Project (Australia)

35.5%

Energy Coal

390

CY10

30 million tpa export coal loading facility

On schedule and budget. Wharf construction progressing well with delivery of stacker reclaimers commenced. Project is greater than 50% complete.

Minerals Exploration

BHP Billiton continues to identify and prioritise various exploration activities. All of the exploration activities are reviewed regularly to ensure that we are capturing value accretive opportunities for future development.

Grassroots exploration continued on targets in AustraliaChileArgentinaZambia and Gabon; and on diamond targets in Canada. Exploration for iron ore, coal, bauxite and manganese was undertaken in a number of regions including AustraliaSouth AmericaRussia and West Africa.

For the nine months ended 31 March 2009, BHP Billiton spent US$514 million on minerals exploration, of which US$460 million was expensed.

Petroleum Exploration

Exploration and appraisal wells drilled during the quarter or in the process of drilling as at 31 March 2009.

Well

Location

BHP Billiton Equity

Status

Lambert-9

Dampier Sub-Basin Western Australia WA-16-L

16.67% BHP Billiton

(Woodside operator)

Plugged and abandoned.

Hydrocarbons encountered.

Lady Nora-3

Dampier Sub-Basin Western Australia WA-28-P

16.67% BHP Billiton

(Woodside operator)

Plugged and abandoned.

Dry hole.

Tidepole-2

Dampier Sub-Basin Western Australia WA-5-L

16.67% BHP Billiton

(Woodside operator)

Plugged and abandoned.

Hydrocarbons encountered.

Torosa-5

Browse Basin Western Australia WAR

8.33% BHP Billiton

(Woodside operator)

Plugged and abandoned.

Hydrocarbons encountered.

Puma-4 

Green Canyon Gulf of Mexico GC823 

29.805% BHP Billiton

(BP Operator)

Temporarily abandoned.

Hydrocarbons encountered.

Petroleum exploration expenditure for the nine months ended 31 March 2009 was US$351 million, of which US$242 million was expensed.

On March 18, BHP Billiton was the apparent successful high bidder on 28 blocks in the Central Gulf of Mexico Lease Sale 208, representing a total investment of approximately US$50 million net to BHP Billiton. Final award of these blocks is subject to the usual process of confirmation by the Minerals Management Service (MMS) that BHP Billiton's bids are acceptable.

Further information on BHP Billiton can be found on our website: www.bhpbilliton.com

Australia

Samantha Evans, Media Relations

Tel: +61 3 9609 2898 Mobile: +61 400 693 915

email: [email protected]

United Kingdom

Andre Liebenberg, Investor Relations 

Tel: +44 20 7802 4131 Mobile: +44 7920 236 974

email: [email protected]

 

Peter Ogden, Media Relations

Tel: +61 3 9609 2812 Mobile: +61 428 599 190

email: [email protected]

Illtud Harri, Media Relations

Tel: +44 20 7802 4195 Mobile: +44 7920 237 246

email: [email protected]

Kelly Quirke, Media Relations

Tel: +61 3 9609 2896 Mobile: +61 429 966 312

email: [email protected]

United States  Scott Espenshade, Investor Relations

Tel: +1 713 599 6431 Mobile: +1 713 208 8565

email: [email protected]

 

Leng Lau, Investor Relations

Tel: +61 3 9609 4202 Mobile: +61 403 533 706

email: [email protected] 

Ruban Yogarajah, Media Relations

Tel: US +1 713 966 2907 or UK +44 20 7802 4033MobileUK +44 7827 082 022

email: [email protected]

South Africa

Bronwyn Wilkinson, Investor and Media Relations

Tel: +44 20 7802 4015 Mobile: +44 7500 785 892

email: [email protected] 

BHP Billiton Limited ABN 49 004 028 077

Registered in Australia

Registered Office: 180 Lonsdale Street

Melbourne Victoria 3000 Australia

Tel +61 1300 55 4757 Fax +61 3 9609 3015

BHP Billiton Plc Registration number 3196209

Registered in England and Wales

Registered Office: Neathouse Place

London SW1V 1BH United Kingdom

Tel +44 20 7802 4000 Fax +44 20 7802 4111

A member of the BHP Billiton group which is headquartered in Australia

This information is provided by RNS
The company news service from the London Stock Exchange
 