BHP Billiton Exploration and Development Report

18th Apr 2012 07:00

RNS Number : 5442B
BHP Billiton PLC
17 April 2012
 



news release

 

Release Time

IMMEDIATE

Date

18 April 2012

Number

11/12

 

BHP BILLITON EXPLORATION AND DEVELOPMENT report

for the QUARTER ENDED 31 March 2012

 

This report covers the Group's exploration and development activities for the March 2012 quarter. Unless otherwise stated, BHP Billiton's interest in the projects referred to in this report is 100 per cent and references to project schedules are based on calendar years.

 

Development

BHP Billiton's commitment to developing its portfolio of high return growth projects, diversified by commodity, geography and market was further reinforced by the approval of additional investment in its world class Base Metals, Iron Ore and Petroleum businesses.

 

During the March 2012 quarter, BHP Billiton announced approval of the US$2.2 billion (BHP Billiton share) Escondida Organic Growth Project 1 (OGP1) which involves the replacement of an existing concentrator and allows access to valuable, higher grade ore. BHP Billiton also approved the US$414 million (BHP Billiton share) Escondida Oxide Leach Area Project (OLAP).

In addition, pre-commitment expenditure of US$779 million (BHP Billiton share) for the proposed Western Australia Iron Ore (WAIO) Outer Harbour development was approved. This funding will enable feasibility studies to progress, the procurement of long lead time items and for dredging to begin, subject to the necessary regulatory approvals.

 

On 11 April 2012, BHP Billiton also approved pre-commitment funding of US$708 million (BHP Billiton share) for the Mad Dog Phase 2 project in the deepwater Gulf of Mexico which will facilitate detailed engineering and the procurement of long lead time items related to the hull, topsides and subsea equipment.

 

The Worsley Efficiency & Growth project will no longer be reported in future Exploration and Development Reports as it achieved first production in the March 2012 quarter and is 98 per cent complete.

 

BHP Billiton's Onshore US drilling and development expenditure totalled US$2.2 billion for the nine months ended March 2012.

 

Project and ownership

Share of approved capex (US$m)

Initial production target date

Production capacity (100%)

Quarterly progress

Petroleum projects

Macedon (Australia) 71.43% Gas

1,050

CY13

200 million cubic feet gas per day.

On schedule and budget. The overall project is 57% complete.

Bass Strait Kipper (Australia) 32.5% - 50% Gas/Gas Liquids

900

CY12(a)

10,000 bpd condensate and processing capacity of 80 million cubic feet gas per day.

On revised schedule and budget. The overall project is 92% complete.

Bass Strait Turrum (Australia) 50% Gas/Gas Liquids

1,350

CY13

11,000 bpd condensate and processing capacity of 200 million cubic feet gas per day.

On revised schedule and budget. The overall project is 78% complete.

North West Shelf North Rankin B Gas Compression (Australia) 16.67% LNG

850

CY13

2,500 million cubic feet gas per day.

On budget. Steady state production remains on track for CY13. The overall project is 87% complete.

North West Shelf Greater Western Flank-A (Australia) 16.67% LNG

400

CY16

To maintain LNG plant throughput from the North West Shelf operations.

On schedule and budget. The overall project is 9% complete.

Minerals projects

Worsley Efficiency & Growth (Australia) 86% Alumina

2,995

Q1 CY12

1.1 million tpa of additional alumina.

First production was achieved in Q1 CY12 and ramp up is underway. The overall project is 98% complete.

Antamina Expansion (Peru) 33.75% Copper

435

Q1 CY12

Increases ore processing capacity to 130,000 tpd.

Commissioning of the SAG mill and first production was achieved in Q1 CY12. The overall project is 90% complete.

Escondida Ore Access (Chile) 57.5% Copper

319

Q2 CY12

The relocation of the in-pit crushing and conveyor infrastructure provides access to higher grade ore.

On schedule and budget. The overall project is 85% complete.

Escondida Organic Growth Project 1 (Chile) 57.5% Copper

2,207

H1 CY15

Replaces the Los Colorados concentrator with a new 152,000 tpd plant.

Approval announced. See News Release dated 14 February 2012.

Escondida Oxide Leach Area Project (Chile) 57.5% Copper

414

H1 CY14

New dynamic leaching pad and mineral handling system. Maintains oxide leaching capacity.

Approval announced. See News Release dated 14 February 2012.

EKATI Misery Open Pit Project (Canada) 80% Diamonds

323

CY15

Project consists of a pushback of the existing Misery open pit which was mined from 2001 to 2005.

On schedule and budget. The overall project is 22% complete.

WAIO Jimblebar Mine Expansion (Australia) 96% Iron Ore

3,300(b)

Q1 CY14

Increases mining and processing capacity to 35 million tpa with incremental debottlenecking opportunities to 55 million tpa.

On schedule and budget. The overall project is 27% complete.

WAIO Port Hedland Inner Harbour Expansion (Australia) 85% Iron Ore

1,900(b)

H2 CY12

Increases total inner harbour capacity to 220 million tpa with debottlenecking opportunities to 240 million tpa.

On schedule and budget. The overall project is 49% complete.

WAIO Port Blending and Rail Yard Facilities (Australia) 85% Iron Ore

1,400(b)

H2 CY14

Optimises resource and enhances efficiency across the WAIO supply chain.

On schedule and budget. The overall project is 16% complete.

WAIO Orebody 24 (Australia) 85% Iron Ore

698

H2 CY12

Maintains iron ore production output from the Newman Joint Venture operations.

On schedule and budget. The overall project is 12% complete.

Samarco Fourth Pellet Plant (Brazil) 50% Iron Ore

1,750

H1 CY14

Increases iron ore pellet production capacity by 8.3 million tpa to 30.5 million tpa.

On schedule and budget. The overall project is 30% complete.

Daunia (Australia) 50% Metallurgical Coal

800

CY13

Greenfield mine development with capacity to produce 4.5 million tpa of export metallurgical coal.

On schedule and budget. The overall project is 40% complete.

Broadmeadow Life Extension (Australia) 50% Metallurgical Coal

450

CY13

Increases productive capacity by 0.4 million tpa and extends life of the mine by 21 years.

On schedule and budget. The overall project is 62% complete.

Hay Point Stage Three Expansion (Australia) 50% Metallurgical Coal

1,250(b)

CY14

Increases port capacity from 44 million tpa to 55 million tpa and reduces storm vulnerability.

On schedule and budget. The overall project is 40% complete.

Caval Ridge (Australia) 50% Metallurgical Coal

2,100(b)

CY14

Greenfield mine development and expansion of the Peak Downs Mine with capacity to produce 8.0 million tpa of export metallurgical coal.

On schedule and budget. The overall project is 33% complete.

RX1 Project (Australia) 100% Energy Coal

400

H2 CY12

Increases run-of-mine thermal coal production by approximately 4 million tpa.

On schedule and budget. The overall project is 78% complete.

Cerrejon P40 Project (Colombia) 33.3% Energy Coal

437

CY13

Increases saleable thermal coal production by 8 million tpa to approximately 40 million tpa.

On schedule and budget. The overall project is 21% complete.

Newcastle Third Port Project Stage 3 (Australia) 35.5% Energy Coal

367

CY14

Increases total coal terminal capacity from 53 million tpa to 66 million tpa.

On schedule and budget. The overall project is 21% complete.

 

Minerals exploration

 

Greenfield exploration continued on copper targets in South America, nickel and copper targets in Australia, and iron ore and potash in a number of regions globally.

 

For the nine months ended March 2012, BHP Billiton spent US$785 million on minerals exploration, of which US$668 million was expensed.

 

Petroleum exploration

 

Exploration and appraisal wells drilled during the quarter or in the process of drilling as at 31 March 2012.

 

Well

Location

BHP Billiton equity

Status

Gunflint-3

Gulf of Mexico

MC948

11.2% (Noble operator)

Drilling ahead

Julong Centre

Brunei

Block CA-01

22.5% (Total operator)

Plugged and abandoned

Dry hole

Julong East

Brunei

Block CA-01

22.5% (Total operator)

Hydrocarbons encountered

Drilling ahead

Jujur-1

Sabah Malaysia

Block N

60% (Operator)

Plugged and abandoned

Dry hole

N. Scarborough

Offshore Western Australia

WA-346-P

100% (Operator)

Plugged and abandoned

Hydrocarbons encountered

Tallaganda-1

Offshore Western Australia

WA-351-P

55% (Operator)

Hydrocarbons encountered

Drilling ahead

 

Petroleum exploration expenditure for the nine months ended March 2012 was US$925 million, of which US$409 million was expensed. Our guidance for petroleum exploration expenditure for the 2012 financial year is US$1.4 billion, including the Onshore US exploration program. Onshore US Permian Basin appraisal activities for the March 2012 quarter included the successful completion and testing of six wells with commercial rates.

 

This report, together with the Production Report, represents the Interim Management Statement for the purposes of the UK Listing Authority's Disclosure and Transparency Rules. There have been no significant changes in the financial position of the Group in the quarter ended 31 March 2012.

 

(a) Facilities ready for first production pending resolution of mercury content.

(b) Excludes announced pre-commitment funding.

 

Further information on BHP Billiton can be found at: www.bhpbilliton.com

 

Media Relations

 

Australia

 

Antonios Papaspiropoulos

Tel: +61 3 9609 3830 Mobile: +61 477 325 803

email: [email protected]

 

Kelly Quirke

Tel: +61 3 9609 2896 Mobile: +61 429 966 312

email: [email protected]

 

Fiona Martin

Tel: +61 3 9609 2211 Mobile: +61 427 777 908

email: [email protected]

 

United Kingdom

 

Ruban Yogarajah

Tel: +44 20 7802 4033 Mobile: +44 7827 082 022

email: [email protected]

 

Americas

 

Jaryl Strong

Tel: +1 713 499 5548 Mobile: +1 281 222 6627

email: [email protected]

Investor Relations

 

Australia

 

James Agar

Tel: +61 3 9609 2222 Mobile: +61 467 807 064

email: [email protected]

 

Andrew Gunn

Tel: +61 3 9609 3575 Mobile: +61 439 558 454

email: [email protected]

 

United Kingdom and South Africa

 

Brendan Harris

Tel: +44 20 7802 4131 Mobile: +44 7990 527 726

email: [email protected]

 

Tara Dines

Tel: +44 20 7802 7113 Mobile: +44 7825 342 232

Email: [email protected]

 

Americas

 

Scott Espenshade

Tel: +1 713 599 6431 Mobile: +1 713 208 8565

email: [email protected]

 

BHP Billiton Limited ABN 49 004 028 077

Registered in Australia

Registered Office: 180 Lonsdale Street

Melbourne Victoria 3000 Australia

Tel +61 1300 55 4757 Fax +61 3 9609 3015

 

 

BHP Billiton Plc Registration number 3196209

Registered in England and Wales

Registered Office: Neathouse Place

London SW1V 1BH United Kingdom

Tel +44 20 7802 4000 Fax +44 20 7802 4111

 

Members of the BHP Billiton Group which is headquartered in Australia

 