LONDON (Alliance News) - Wolf Minerals Ltd on Thursday said wet commissioning work has started at the Hemerdon tungsten and tin project in Devon.
The first ore has been fed into the processing plant at the site, and the group remains on track to deliver initial concentrates from the project in the third quarter.
"After an incredibly busy 15 months, we have put the first ore into the plant at the Hemerdon project on schedule. From this point GR Engineering will continue commissioning and is scheduled to hand the plant across to Wolf in August. We remain on target to deliver initial concentrates to our offtake partners in the third quarter this year. Importantly this achievement has been attained in conjunction with an excellent safety and environmental record," said Managing Director Russell Clark.
Wolf shares were up 1.0% to 19.95 pence on Thursday.
By Sam Unsted; [email protected]; @SamUAtAlliance