10th Dec 2018 11:23
LONDON (Alliance News) - W Resources PLC said Monday the mechanical completion of a crusher plant at its tungsten and tin La Parrilla project in western Spain.
W Resources said the mechanical completion of the crusher plant "paves the way" for commissioning of mined ore in January 2019.
"The crusher is the first of the three La Parrilla plants to be completed and it's a great credit to the team to complete it ahead of schedule and on budget. We are looking forward to first mined ore into the crusher early in the new year which will contribute to an increase in production rates from La Parrilla in line with the planned ramp-up programme," said Chairman Michael Masterman.
The crushing circuit is designed to process 350 tonnes per hour of ore. W Resources said the circuit has been designed for modular expansion to 700 tonnes per hour, requiring no modifications.
Shares in W Resources were up 0.2% Monday at 0.53 pence each.