26th Aug 2016 06:41
LONDON (Alliance News) - Europe and Africa-focused upstream oil and gas firm Sound Energy PLC on Friday said drilling has started on the second well at the Tendrara project, onshore Morocco.
Sound said the objective for the second well will be proving sufficient gas volumes and well deliverability in order to allow the finalisation of the field development plan and concession application.
Drilling and logging work on the well will take around 54 days, Sound said, with around 30 days then to be spent on completion and stimulation, before another 10 days on clean-up and initial well-testing.
By Sam Unsted; [email protected]; @SamUAtAlliance