NEWS RELEASE

10-41

November 9, 2010

www.first-quantum.com

 

 

 

 

FIRST QUANTUM MINERALS REPORTS OPERATIONAL AND FINANCIAL RESULTS FOR THE THREE AND NINE MONTHS ENDED SEPTEMBER 30, 2010

(All figures expressed in US dollars, unless otherwise noted)

First Quantum Minerals Ltd. ("First Quantum" or the "Company", TSX Symbol "FM", LSE Symbol "FQM") today announced its results for the three and nine months ended September 30, 2010. The complete financial statements and management discussion and analysis are available for review at www.first-quantum.com and should be read in conjunction with this news release.

SUMMARY OPERATING AND FINANCIAL DATA

Three months ended

September 30

Nine months ended

September 30

(USD millions unless otherwise noted)

2010

2009

2010

2009

Production - copper (tonnes)

76,633

93,486

247,097

275,412

Production - gold (ounces)

46,718

43,357

142,831

130,609

Sales - copper (tonnes)

79,408

105,154

235,270

268,410

Realized copper price (per lb)

$2.99

$2.21

$2.84

$1.88

 

Net sales

$602.6

$546.3

$1,694.1

$1,219.4

Net earnings before impairment, derivatives and acquisition costs

$129.7

$164.2

$401.8

$375.7

Net earnings (loss)

$(136.7)

$123.8

$(578.7)

$236.2

Earnings per share before impairment, derivatives and acquisition costs

$1.62

$2.10

$5.02

$5.04

Earnings (loss) per share

$(1.70)

$1.59

$(7.24)

$3.17

Average copper unit cash cost of production (C1)[1](per lb)

$1.21

$0.98

$1.21

$0.95

Cash

$632.8

$807.7

$632.8

$807.7

Unless otherwise indicated, all comparisons of performance throughout this report are to the comparative periods for 2009

[1] C1 cost is a non-GAAP measure. See “Regulatory disclosures – non-GAAP measures” for further information

Q3 HIGHLIGHTS AND SIGNIFICANT ITEMS

·; Operating profit of $309.6 million increased by 36% from Q2 2010

·; Results benefitted from a higher copper price, but were adversely impacted by the forced shut down of Frontier operations on August 27, 2010

·; Net earnings of $129.7 million (EPS of $1.62) before impairment and derivative timing losses

·; Impairment of $243.8 million, net of tax and including closure costs, related to the Frontier copper operation following the forced shut down by the République démocratique du Congo ("RDC"). See "Other items" for further discussion

·; Increased on-site activities in the development of Ravensthorpe, Kevitsa and Trident (formerly Kalumbila)

·; 18% decrease in total copper production resulting from the shut down at Frontier and lower ore grades at Kansanshi

·; 8% increase in total gold production resulting from circuit improvements and plant expansions completed at Kansanshi

·; Strong cash and working capital position despite significant investments in Ravensthorpe, Kevitsa and Trident in 2010

RECENT DEVELOPMENTS AND NEAR TERM OUTLOOK

Kansanshi copper and gold operation, Zambia

·; The new mining fleet continues to be commissioned with the nine of the twelve new 180 tonne AC drive units now operating. The third 250 tonnes excavator was commissioned and together with improvements to the mobile plant availability, mining rates lifted during Q3. These enhancements are expected to continue during Q4.

·; The secondary crusher on the sulphide circuit was commissioned during Q3 and will be optimised during Q4.

Guelb Moghrein copper and gold operation, Mauritania

·; Ongoing optimization of the autogenous circuit, including the high pressure grinding rollers, will continue in Q4 with a goal to achieve design throughput and increase copper and gold recoveries.

Kevitsa nickel/copper/PGE project, Finland

·; Construction works at Kevitsa have advanced on schedule during Q3. Earthworks and concrete works have advanced well and the first construction steel will be erected at the beginning of Q4. The update of the Kevitsa resource has also progressed well during Q3 and is expected to be finalised during Q4.

Ravensthorpe nickel project, Australia

·; The refurbishment of the processing facilities at Ravensthorpe has advanced significantly during Q3 2010. The new crusher installations are well advanced. Refurbishment of the existing fixed plant facilities has commenced with commissioning on track for Q2 2011.

·; Grade control drilling has commenced to ensure the geological database is sufficiently advanced to allow detailed mine planning ahead of the re-commencement of the plant.

Trident project, Zambia

·; Significant exploration activities at the Sentinel copper deposit and Enterprise nickel target were undertaken in Q3 with an aim to further delineate the existing copper deposit and define other targets within the licence areas. An economic assessment including metallurgical test work, engineering and geotechnical studies are underway and expected to be completed in Q4 2010. Environmental studies also commenced in preparation for environmental and mining license applications.

·; Base-line environmental and social consultations are planned as part of the environmental impact assessment to be prepared in support of a mining license. Exploration activities will focus on the three main prospects, Sentinel, Enterprise and Intrepid, targeting both copper and nickel.

Production Guidance

·; The Company's 2010 production outlook has been lowered to 322,000 tonnes of copper and 195,000 ounces of gold. The lower estimated copper production reflects the closure of Frontier.

·; Estimated average C1 cost for 2010 is unchanged at $1.17 per pound

Acquisition of Antares Minerals Inc.

·; In October 2010, the Company entered into an agreement to acquire Antares Minerals Inc. ("Antares") for CAD $460 million in cash and shares. Antares' principal asset is the 100% owned Haquira project in Peru, one of the world's major undeveloped copper deposits.

Sale of investment in Equinox Minerals Limited

·; In November 2010, the Company announced the sale of its approximate 16% interest in Equinox Minerals Limited which will raise proceeds of approximately CAD $650 million in cash. The funds will be used towards advancement of the Company's diversified pipeline of growth projects.

REVENUES

NET SALES

(after provisional pricing and realization charges)

Three months ended

September 30

Nine months ended

September 30

(USD millions unless otherwise noted)

2010

2009

2010

2009

Kansanshi - copper

375.7

379.7

1,082.3

770.8

- gold

29.5

18.7

82.4

45.3

Guelb Moghrein - copper

49.6

24.1

116.8

70.3

- gold

23.0

16.3

57.8

57.4

Frontier - copper

80.9

107.5

225.3

273.4

Bwana/Lonshi - copper

17.2

-

47.8

0.4

- acid

-

-

-

1.8

Corporate

26.7

-

81.7

-

Net sales

602.6

546.3

1,694.1

1,219.4

Copper provisional pricing adjustment included above

6.5

12.9

(4.8)

40.1

COPPER SELLING PRICE

USD/lb

USD/lb

USD/lb

USD/lb

Current period sales

3.20

2.44

3.12

2.11

Prior period provisional pricing adjustment

0.04

0.06

(0.01)

0.07

Treatment charges/refining charges ("TC/RC") and freight parity charges

(0.25)

(0.29)

(0.27)

(0.29)

Realized copper price

2.99

2.21

2.84

1.89

The Q3 2010 average realized copper price was significantly higher than Q3 2009 due to an increase in the average LME copper price. Copper sales volumes for Q3 decreased 24% to 79,408 tonnes due to the shut down of operations at Frontier at the end of August. Sales volumes from Kansanshi, Guelb Moghrein and Bwana/Lonshi were consistent with production in Q3 and the inventory held in the Company's metal marketing division was consistent with the start of the period.

The Q3 positive provisional pricing adjustment resulted from the finalization of contracts totalling 16,949 tonnes of copper at an average price of $3.14 per pound ($6,913 per tonne). These contracts were provisionally priced at $2.96 per pound ($6,527 per tonne) at June 30, 2010 and were finalized during July and August 2010.

The year-to-date negative provisional pricing adjustment resulted from the finalization of contracts totalling 21,647 tonnes of copper at an average price of $3.24 per pound ($7,140 per tonne). These contracts were provisionally priced at $3.34 per pound ($7,361 per tonne) at December 31, 2009 and were finalized during January and February 2010.

At September 30, 2010, 16,024 tonnes of copper provisionally priced at $3.65 per pound ($8,054 per tonne) remain subject to final pricing in October and November 2010. Refer to the 'Outlook' section for further discussion.

Gold revenues increased by 50% over Q3 2009 to $52.5 million. The increase resulted from a higher realized gold price which offset lower sales volumes in Q3 2010.

Metal marketing division

A metal marketing division was established in Q1 2010 to improve the management of copper and gold sales from the Company's operations and reduce the Company's exposure to provisional pricing. Prior to the establishment of the division, revenues were recognized by operations when title transferred to buyers, usually upon leaving the mine site. Copper and gold sales managed by the metal marketing division are now recognized when title has transferred to final purchasers resulting in reduced sales volumes and higher inventory for the year-to-date. The impact on current quarter and current year sales volumes and inventory balances are summarized as follows:

Metal marketing division

Impact on sales volume for the period

Three months ended

September 30, 2010

Nine months ended

September 30, 2010

Copper (tonnes)

Kansanshi

(392)

798

Guelb Moghrein

736

3,493

Frontier

889

8,032

Total copper

1,233

12,323

Gold (ounces)

Guelb Moghrein

1,045

6,966

In addition to marketing the Company's production, the metal marketing division purchases and sells metal from external parties. During Q3, the division had revenues of $26.7 million and finished goods inventory of $44.5 million related to external purchases and sales.

In order to reduce the effect of movements in metal prices between the time of shipment of metal from the mine site and final recognition of the sale, the metal marketing division enters into futures contracts. As a result of the significant increase in LME copper prices during Q3, a derivative instrument loss of $23.8 million was recognized on these futures contracts in the period. This loss offsets an unrecognized gain in the fair market value of the inventory held by the metal marketing division at September 30, 2010.

SEGMENTED OPERATING RESULTS

Kansanshi Copper and Gold Operation

Three months ended

September 30

Nine months ended

September 30

2010

2009

2010

2009

Production (tonnes)

Copper cathode

21,914

25,436

61,761

70,509

Copper in concentrate

9,723

9,516

32,016

49,903

Copper cathode tolled

23,564

26,344

71,115

62,114

Total copper production (tonnes)

55,201

61,296

164,892

182,526

Copper sales (tonnes)

55,355

73,985

166,485

177,161

Gold production (ounces)

29,456

25,350

80,647

67,460

Sulphide ore tonnes milled (000's)

2,443

2,576

7,683

9,217

Sulphide ore grade processed (%)

0.8

0.9

0.8

1.0

Sulphide copper recovery (%)

93

93

92

90

Mixed ore tonnes milled (000's)

1,289

1,477

3,826

2,022

Mixed ore grade processed (%)

1.2

1.3

1.3

1.1

Mixed copper recovery (%)

67

65

66

81

Oxide ore tonnes milled (000's)

1,495

1,540

4,153

4,183

Oxide ore grade processed (%)

2.4

2.3

2.2

2.2

Oxide copper recovery (%)

78

80

86

81

Cash costs (C1) (per lb)1

$1.09

$1.01

$1.11

$1.00

Total costs (C3) (per lb)1

$1.42

$1.31

$1.33

$1.27

Gross operating profit (USD M)

$242.6

$208.5

$674.3

$379.2

[1]C1 costs and C3 costs are non-GAAP measures. See “Regulatory disclosures – non-GAAP measures” for further information

Q3 copper production decreased by 10% from Q3 2009 due to lower throughput and grades processed. Overall mining production improved in Q3 on the continued commissioning of new mining equipment. However, increased waste stripping resulted in lower total ore volumes mined and processed in the period.

Q3 sulphide circuit production was impacted by lower grades and tonnes processed. Throughput decreased from the comparative period on the testing and commissioning of the secondary sulphide crusher in Q3 2010 resulting in downtime on the crushing and milling circuit.

Mixed ore circuit throughput was constrained by maintenance downtime on the SAG mill in early Q3, resulting in processing of ore directly through the ball mill at lower rates. Circuit recovery remained strong in Q3 offsetting a small decrease in ore grade processed.

Kansanshi's oxide circuit recovers both oxide and sulphide minerals to produce copper cathode and copper in concentrate. Total copper recovery of 78% reflects an increase in the proportion of sulphide material floated in the circuit at a lower overall recovery. Q3 throughput was impacted by downtime caused by the construction and commissioning of circuit improvements aimed at achieving higher recoveries of sulphide and oxide material. The benefits of these improvements are expected to be realized in Q4 and into 2011.

Total gold production increased by 16% due to continued gravity circuit improvements. Kansanshi produced a record 14,482 ounces of gold in dore in Q3.

Kansanshi's cash unit cost of production (C1) increased from Q3 2009 due to higher ore costs and higher processing costs, partially offset by an increased gold credit. The cost of ore processed was 29% higher than Q3 2009, despite a decrease in total mining costs per tonne of mined material, due to lower grade ores mined and the impact of higher waste stripping on the cost per ore tonne mined. Increased processing costs resulted from lower overall copper production and higher maintenance costs. The increased gold credit resulted from higher gold sales volumes and prices realized in Q3.

 

Guelb Moghrein Copper and Gold Operation

Three months ended

September 30

Nine months ended

September 30

2010

2009

2010

2009

Production - copper in concentrate (tonnes)

8,487

7,425

27,282

24,792

Copper sales (tonnes)

9,291

6,958

22,232

26,106

Gold production (ounces)

17,262

18,007

62,184

63,149

Sulphide ore tonnes milled (000's)

644

514

2,048

1,518

Sulphide ore grade processed (%)

1.4

1.7

1.5

1.9

Sulphide copper recovery (%)

92

84

91

88

Cash costs (C1) (USD per lb)1

$0.79

$0.67

$0.85

$0.35

Total costs (C3) (USD per lb)1

$1.85

$1.19

$1.60

$0.61

Gross operating profit (USD M)

$35.0

$14.8

$82.8

$53.6

[1]C1 costs and C3 costs are non-GAAP measures. See “Regulatory disclosures – non-GAAP measures” for further information

Guelb Moghrein's Q3 production improved from 2009 on the plant expansion completed in 2010. The plant continued process configuration work aimed at achieving design throughput capacity and improved recoveries. This included a conversion to an autogenous circuit in Q3 which temporarily reduced overall mill availability and throughput. Ore grades processed are generally lower in 2010 reflecting the ore profile going forward.

Gold production was 4% lower than Q3 2009 due to lower gold grades processed, offset partially by increased recovery and throughput. The gold plant is expected to improve dore production with the addition of a gravity concentrator.

Guelb Moghrein's average cash cost of production (C1) was higher compared to Q3 2009 due to increased ore costs and processing costs incurred on lower grade ore and circuit downtime during optimization work undertaken. The gold credit benefitted from higher realized gold price which outweighed lower gold sales volume in Q3 2010.

Guelb Moghrein's Q3 operating profit increased from the comparative period due to increased copper sales volumes and significantly higher realized copper and gold prices. This was reduced by higher production costs incurred and increased depreciation on the plant expansion completed in 2010.

 

Frontier Copper Operation

Three months ended

September 30

Nine months ended

September 30

2010

2009

2010

2009

Production - copper in concentrate (tonnes)

10,541

24,765

47,508

68,094

Copper sales (tonnes)

12,360

24,211

39,643

65,143

Sulphide ore tonnes milled (000's)

1,346

2,183

5,425

5,788

Sulphide ore grade processed (%)

0.9

1.2

1.0

1.3

Sulphide copper recovery (%)

92

92

90

92

Cash costs (C1) (USD per lb)1

$2.22

$1.02

$1.77

$1.06

Total costs (C3) (USD per lb)1

$2.55

$1.19

$2.10

$1.21

Gross operating profit (USD M)

$30.6

$67.8

$93.6

$165.9

[1]C1 costs and C3 costs are non-GAAP measures. See “Regulatory disclosures – non-GAAP measures” for further information
 There was no copper production at Frontier following the forced shut down of operations on August 27, 2010 by the RDC government.

Copper production at Frontier during July and August was impacted by the effect of reduced capital investment in 2010 which was a consequence of the uncertainty following the legal proceedings instigated by the RDC state-owned mining agency, Sodimico. As a result, Frontier's mine equipment availability was lower and access to higher grade ore was limited.

A significant increase in cash costs was caused by lower ore grades processed, increased mining costs, and inefficiencies experienced on lower copper production in Q3 2010. The Company incurred an impairment charge of $249.8 million, net of tax and including closure costs, related to the Frontier copper operation following the forced shut down by the RDC. See "Other items" for further discussion.

 

Bwana/Lonshi Copper Operation

Three months ended

September 30

Nine months ended

September 30

2010

2009

2010

2009

Production - copper cathode (tonnes)

2,404

-

7,415

-

Copper sales (tonnes)

2,402

-

6,910

-

Oxide ore tonnes milled (000's)

112

-

327

-

Oxide ore grade processed (%)

2.2

-

2.5

-

Oxide copper recovery (%)

92

-

91

-

 

 

Cash costs (C1) (USD per lb)1

$1.24

-

$1.28

-

Total costs (C3) (USD per lb)1

$1.54

-

$1.43

-

Gross operating profit (loss) (USD M)

$7.1

$(6.3)

$1.7

$(12.9)

[1]C1 costs and C3 costs are non-GAAP measures. See “Regulatory disclosures – non-GAAP measures” for further information

The Bwana Mkubwa copper SX/EW plant continued production of grade A copper cathode from the Lonshi oxide ore stockpile until the end of Q3. The gross operating profit for Q3 includes a non-cash expense of $15.5 million related to the inventory net realizable value write-up recognized in 2009. The write-up was expensed as the Lonshi ore stockpile was processed in 2010. The facility has been placed on care and maintenance while options are considered for use of the SX/EW assets.

COSTS AND EXPENSES

Three months ended

September 30

Nine months ended

September 30

(USD millions unless otherwise noted)

2010

2009

2010

2009

Gross operating profit

309.6

284.8

847.6

585.8

General and administrative

(13.3)

(8.7)

(26.2)

(20.0)

Acquisition transaction costs

-

-

(18.5)

-

Other income (loss)

(2.0)

10.0

9.6

20.9

Derivative instrument adjustments

(22.6)

(40.4)

(14.6)

(139.5)

Exploration

(12.6)

(4.4)

(31.9)

(15.6)

Assets impaired

(306.9)

-

(1,120.0)

-

Interest

(15.5)

(19.5)

(44.0)

(42.1)

Income taxes

(61.1)

(73.2)

(104.3)

(111.7)

Non-controlling interests

(12.3)

(24.8)

(76.4)

(41.6)

Net earnings (loss) attributable to equity holders of the parent

(136.7)

123.8

(578.7)

236.2

Earnings (loss) per share

- basic (USD per share)

(1.70)

1.59

(7.24)

3.17

- diluted (USD per share)1

(1.70)

1.50

(7.24)

3.11

Weighted average shares outstanding

- basic (number of shares - millions)

80.2

78.1

80.0

74.6

- diluted (number of shares - millions)1

80.2

87.7

80.0

78.6

[1] As the Company has incurred a loss, pursuant to Canadian GAAP, the convertible bonds and stock options are excluded from the computation of diluted loss per share.

 

The derivative instrument adjustments of $22.6 million in Q3 2010 consist of losses recognized on LME futures sales contracts held by the metal marketing division as at September 30, 2010 following a significant increase in copper price during the current period. The commensurate gain in the underlying copper inventory is not recognized until it is sold. In the comparative period, the Company's derivative loss was incurred on derivative positions entered into in order to protect the Company against the uncertain economic outlook of early 2009.

Exploration expenses in Q3 include $7.5 million incurred at the Trident project representing a significant increase in exploration activity. See "Development activities" for further discussion

Asset impairment expense in Q3 2010 consists primarily of the impairment of Frontier's property, plant and equipment, and inventory that were deemed unrecoverable following the forced suspension of the Frontier operation. The tax impact of this impairment is included with income tax expense.

Interest expense has decreased from Q3 2009 due to a decrease in LIBOR and a lower balance of the corporate revolving credit and term loan facility.

Q3 income taxes were reduced by the impact of Frontier's impairment on current and future tax liabilities, representing a tax recovery of $63.1 million. Normalized income taxes have increased from Q3 2009 due to increased profitability and a decrease in the proportionate earnings contribution from Guelb Moghrein, which is operating under a tax holiday.

Non-controlling interests has decreased from Q3 2009 due to the 5% non-controlling interest portion of Frontier's impairment, resulting in a $12.5 million recovery in Q3 2010. In February 2010, the Company acquired the remaining 20% ownership interest in Mauritanian Copper Mines SARL, which owns Guelb Moghrein, resulting in no further non-controlling interests in this operation.

FINANCIAL POSITION AND LIQUIDITY

Three months ended

September 30

Nine months ended

September 30

(USD millions unless otherwise noted)

2010

2009

2010

2009

Cash flows from operating activities

- before changes in working capital

193.8

164.6

573.2

408.2

- after changes in working capital

8.3

196.7

471.0

292.5

Cash flows from financing activities

49.7

(52.2)

(21.1)

594.5

Cash flows from investing activities

(114.5)

(86.1)

(736.3)

(255.5)

Net cash flows

(56.5)

58.4

(286.4)

631.5

Cash balance

632.8

807.7

632.8

807.7

Available credit facilities

- Corporate revolving loan and short-term facility

250.0

250.0

250.0

250.0

- Corporate revolving credit and term loan facility

50.0

50.0

50.0

50.0

- Short-term borrowings

9.9

-

9.9

-

Cash flows from operating activities per share (basic)

- before working capital (USD per share)

$2.42

$2.11

$7.17

$5.47

- after working capital (USD per share)

$0.10

$2.52

$5.89

$3.92

Operating cash flows were generated from positive operating results during Q3. Working capital movements during Q3 2010 include an increase in accounts receivable of $86.4 million as a result of a significant increase in copper price, and a decrease in taxes payable due to payments of $115.0 million made by Kansanshi to the Government of the Republic of Zambia ("GRZ").

Cash inflows from financing activities comprise proceeds from debt of $66.2 million related to an increase in short-term borrowings required to finance material purchases and short-term hedging of copper and gold in Q3. Financing activities also include Q3 dividend payments of $15.2 million to equity holders of the Company and $1.9 million to non-controlling interests.

Investing activities in Q3 consist primarily of property, plant and equipment expenditures. The Company invested $25.7 million on the plant at Ravensthorpe and $33.4 million at Kevitsa as development continues to increase at both projects. Kansanshi expended $44.0 million on new mining equipment and the secondary crusher during the period. The Company undertook significant investing activities in early 2010 including; the acquisition of the Ravensthorpe nickel project for $338.8 million, of which $34.0 million was paid in 2009, the acquisition of Kiwara PLC for $133.2 million in net cash and $137.2 million in common shares of the Company, and the acquisition of the 20% non-controlling interest in Mauritanian Copper Mines for $63.0 million.

In addition to the Company's cash reserves, additional sources of funding available include the $250.0 million corporate revolving loan and $50.0 million available under the corporate revolving credit and term loan facility.

Subsequent to September 30, 2010, the Company cancelled the $250.0 million corporate revolving and loan facility and sold all of its marketable security investment in Equinox Minerals Limited which will raise proceeds of approximately CAD $650 million.

As at September 30, 2010, the Company had the following contractual obligations outstanding:

(USD millions)

Total

Less than 1 year

1 - 2 years

2 - 3 years

3 - 4 years

4 - 5 years

Thereafter

Term debt

208.3

182.6

5.3

5.1

5.1

5.1

5.1

Convertible bonds

500.0

-

-

-

-

500.0

-

Accounts payable

370.1

370.1

-

-

-

-

-

Deferred payments

9.3

0.4

0.4

0.3

0.2

-

8.0

Commitments

184.5

184.5

-

-

-

-

-

Asset retirement obligations

27.1

-

-

-

-

-

27.1

INVENTORY

Copper (tonnes)

Gold in dore (ounces)

Kansanshi

20,468

2,472

Guelb Moghrein

8,092

1,150

Frontier

8,032

-

Bwana/Lonshi

450

-

Total

37,042

3,622

The Company's finished copper inventory decreased by 3,658 tonnes in Q3 to 37,042 tonnes as at September 30, 2010 with an average cost of approximately $1.49 per pound ($3,279 per tonne). Guelb Moghrein's inventory includes finished copper in concentrate which required further blending prior to sale and will be sold in Q4. Frontier's inventory balance represents finished copper held in transit to final offtakers through the metal marketing division. Approximately 16,500 tonnes of Kansanshi copper in concentrate was in the process of being treated or stockpiled for treatment at the Mufulira smelter as at September 30, 2010. Included in the total finished goods inventory balance, but not in the table above, is 5,977 tonnes of third party material purchased for resale by the metal marketing division.

Contained gold in dore inventory increased to 3,622 ounces due to timing of shipments in Q3. Gold contained in copper in concentrate is not included in the inventory balances noted above.

COMPREHENSIVE INCOME

The market value of available-for-sale investments increased during Q3 resulting in the Company recognizing a tax affected increase in the fair value of investments of $208.5 million.

EQUITY

As at the date of this report the Company has 80,672,932 shares outstanding.

DEVELOPMENT ACTIVITIES

Ravensthorpe nickel project, Australia

In February 2010, the Company acquired the Ravensthorpe nickel project for $338.8 million.

Ravensthorpe is located in Western Australia, approximately 550km southeast of Perth. It is an open pit mine and hydrometallurgical process plant that uses proven technology to recover nickel and cobalt to produce a mixed nickel cobalt hydroxide intermediate product. Ravensthorpe's development was completed in 2007, however, operations were suspended in January 2009 after the LME nickel price dropped to as low as $8,810 per tonne in late 2008.

An engineering firm in Perth is completing the detailed design of modifications for the Ravensthorpe process plant, of which a significant part is the modification of the crushing, conveying, stockpile, reclaim and rejects handling areas of the plant. Various environmental and project management plans received approval from the relevant authorities during Q3. As a result, site works are progressing well. Concrete demolition work on both the limonite and saprolite crushing stations have been completed and new civil work is underway. Inspection, testing and re-commissioning of the existing plant continues. Major equipment deliveries have commenced. Upgrade and modification work scheduling will allow commissioning to commence in Q2 2011. This will be followed by approximately six months of commissioning and ramp-up. In order to provide further enhancements to the plant, the revised capital requirement for the modification has increased to approximately $190 million.

The operations recruitment program is continuing and is on schedule. The Company expects Ravensthorpe's average annual production of nickel metal will be approximately 39,000 tonnes for the first five years after recommencement of operations. The expected average annual production is 28,000 tonnes over the total life of mine of 32 years.

Kevitsa nickel/copper/PGE project, Finland

Detailed design is continuing and nearing completion for earth works, concrete works and structural steel. Procurement of the major items of equipment is well advanced and the first major components will be delivered to the site in Q4 2010.

Construction progressed with 160 contractors currently on site and 350 scheduled by Q1 2011. The earthworks are now 83% complete, the concrete works are 35% complete. The construction of the main power line is in progress and work on the water line will commence in Q1 2011. Additional major contracts are in progress for the primary crusher excavation, the tailings and water reservoir construction and the site switchyard.

The project remains on schedule to commence commercial production in mid 2012.

Trident project (formerly Kalumbila), Zambia

In January 2010, the Company acquired all of the issued share capital of Kiwara PLC ("Kiwara") which owned 85% of Kalumbila Minerals Limited ("Kalumbila") and holds mineral property licences on the periphery of the Kabombo Dome in North Western Province, Zambia. Under the terms of the Kiwara acquisition agreement, the Company acquired a further 10% interest in Kalumbila in February 2010 and 1% in May 2010 bringing its ownership interest to 96%. The Company holds options to acquire the remaining 4% interest in Kalumbila for GBP 3.5 million which will be exercised in Q4 2010.

Base-line environmental and social consultations have commenced as part of the environmental impact assessment to be prepared in support of a mining license.

Refer to the "Exploration" section for discussion on the Company's exploration program at Trident.

Kansanshi copper/gold operation, Zambia

Throughput optimization of the sulphide circuit is ongoing, mainly focused on the production of a finer product from the crusher. The first phase of the milling expert control system was implemented and is working well in its current restricted configuration. Full implementation will happen in a staged manner over the remainder of Q4.

The installation of additional flotation capacity on sulphide and mixed ore is progressing with commissioning due in January 2011. This additional capacity will enhance recovery potential of both sulphide and mixed ore at higher production rates. The installation of additional leaching capacity for the oxide circuit, aimed at improving recovery of soluble copper, is scheduled for completion towards the end of Q4 2010. The de-sliming circuit aimed at improving recovery of sulphide minerals from the oxide ore flotation circuit was commissioned in Q3 and optimization work to deal with capacity constraints is underway.

Optimization of gold recovery continues with an additional gravity concentrator installed and commissioned in the mixed ore milling circuit. Test work on the treatment of the acidic high pressure leach residue to extract gold was also positive. The goal for these installations is to reduce gold in concentrate to below payable levels and maximize the more favorable return on gold in dore.

Guelb Moghrein copper/gold operation, Mauritania

Ongoing optimization of the autogenous circuit, including the high pressure grinding rollers, will continue in Q4 with a goal to achieve design throughput and increase copper and gold recoveries.

Acquisition of the non-controlling interest in Mauritanian Copper Mines SARL

In February 2010, the Company completed the acquisition of the 20% non-controlling interest in Mauritanian Copper Mines SARL, which owns the Guelb Moghrein copper and gold operation, for $63.0 million.

Exploration

Exploration activities continued at a high rate during the period with staff, resources and drill rigs redeployed from the RDC to Zambia to boost the Trident program. Extra drilling capacity arrived in Mauritania and a substantial summer prospecting program in Finland has revealed significant potential for new nickel and copper projects.

Fourteen drill rigs are now active on the Trident project in Zambia. Nearly 50,000m of drilling has been completed in 142 holes on the Sentinel copper deposit since the Company acquired the project in Q1 2010. A pattern of 200m spaced sections has been largely completed in the area of the current mineral resources of approximately 4km by 1km with preliminary results demonstrating good continuity of mineralization. Furthermore, the focus of the drilling activity has now moved to the south west to test for potential significant extensions up to several kilometers and outside of the current mineral resource. Preliminary results are positive with visible mineralization observed and logged in the drill core.

A major regional exploration program is currently in progress over the entire Trident project of approximately 2,300 km2 of license area. Detailed airborne electro-magnetic work has been completed and is proving an excellent tool to identify the prospective target zones. A low level helicopter magnetic-radiometric survey is currently in progress and a systematic geochemical program of 23,000 soil samples is already providing targets for follow up drilling. Drilling has commenced on the Enterprise nickel target 12 km north of Sentinel and will progress to further regional targets over Q4.

At Kansanshi two exploration rigs continued drilling on the southeast dome prospect and 74 holes have now been completed that define a clear domal structure approximately 500m across hosting typical Kansanshi vein style mineralization. Recent drill results have defined the first area of near surface oxide mineralization.

At Kevitsa in Finland, drilling will focus on high priority geophysical targets in the Kevitsa tenure. Resource modeling of the new extensions to the south of the proposed Kevitsa pit has been completed and optimization studies are currently in progress. An extensive field validation program of regional targets has defined 22 prospects for follow up drilling during the coming winter.

In Mauritania a second drill rig and a boosted geological team are now in place which will accelerate the testing of regional targets over the next few months.

Antares Minerals Inc.

In October 2010, the Company entered into a definitive agreement to acquire, by way of a court-approved plan of arrangement, all of the outstanding securities of Antares. The total consideration for the purchase of 100% of the fully diluted shares of Antares is approximately CAD $460 million in cash and shares.

Antares' principal asset is the 100% owned Haquira project located in southern Peru adjacent to Xstrata Copper's Las Bambas copper-gold project. It is one of the world's major undeveloped copper deposits with excellent potential for the development of a large scale copper mine. Haquira currently has reported measured and indicated resources of 3.7 million tonnes of contained copper equivalent and inferred resources of 2.4 million tonnes of contained copper equivalent.

 

OTHER ITEMS

RDC - Kolwezi dispute

During 2007, the Government of the RDC announced a review of over 60 mining agreements entered into over the last decade with foreign companies. The Kolwezi mining convention ("Contract of Association"), to which the Company's subsidiary Congo Mineral Developments Limited ("CMD") is a party, in partnership with Industrial Development Corporation of South Africa ("IDC") and the IFC (International Finance Corporation). At the conclusion of the "Revisitation" CMD received a letter from the RDC Prime Minister dated August 21, 2009, which reported on the outcome of an August 4, 2009 meeting of the RDC Council of Ministers with respect to the Contract of Association. The letter notes the "impossibility to pursue the partnership" and directed that the Kolwezi exploitation permit held by KMT, the Company formed by the parties to pursue the KMT Project, be returned to Gécamines pursuant to the Contract of Association. Subsequently, the exploitation permit was cancelled and on September 15, 2009 CMD received an order by the General Prosecutor of Katanga to seal KMT's facilities. In January 2010, Gécamines terminated the Contract of Association.

The Company believes there is no legal basis for the cancellation of KMT's exploitation permit, the sealing of the KMT facilities, and Gécamines' termination of the Contract of Association, and as previously noted, that CMD and the KMT Project's other contributing partners, the IFC and the IDC, continue to have a valid and binding contract with the RDC and Gécamines.

Following the cancellation of the Kolwezi exploitation permit, on October 28, 2009 the RDC local court ruled on the incorporation of KMT and found on the basis of no evidence that there was a formal defect in the Decree granting authorization for the constitution of KMT. The local court also found without any evidence presented that there was fraud committed in the constitution of KMT and held for this reason KMT did not exist in law. CMD, IFC and IDC appealed this decision.

On February 1, 2010, CMD, IFC and IDC commenced international arbitration at the International Chamber of Commerce ("ICC") in Paris. A Tribunal has been appointed and a final decision is expected in the latter part of 2012.

On February 22, 2010, without any prior notice KMT and CMD received a Notice of Hearing Date from Gécamines and CAMI setting the appeal of the judgment of the local court for hearing in less than 48 hours on February 24, 2010. Gécamines and CAMI requested the confirmation of the local court judgment and also made an unsupported request for up to US$12 billion in damages to be awarded to Gécamines and CAMI. KMT's lawyers attended and objected to the proceedings. Following a hearing on February 24, 2010, the Company received official notification of the Court of Appeal's judgment on April 7, 2010 confirming the local court's decisions with respect to KMT and awarding US$12 billion in damages against CMD and KMT. On July 27, at the request of the RDC and Gécamines, the Court of Appeal appointed a liquidator to KMT for the purposes of winding up KMT and distributing its assets.

On October 12, 2010 CMD, IFC and IDC applied to the ICC Tribunal for interim protective procedural orders. On October 26, the Tribunal ordered that the RDC and Gécamines cannot enforce directly or indirectly the March 10, 2010 decision of the Court of Appeal, which includes the US$12 billion damages judgment issued by the Court of Appeal against KMT and CMD, maintaining a temporary Order issued on August 19, 2010. This ruling impacts the ongoing efforts by the RDC to enforce the Court of Appeal judgment through the appointment of a Liquidator and means that the RDC cannot liquidate KMT's assets in the country in payment of the damages claim.

Following the appointment of an official liquidator to liquidate KMT and CMD, the Company determined that a complete impairment of the Kolwezi assets was required. The historical carrying value of the Kolwezi development project was $791.1 million and was comprised of the initial acquisition cost and subsequent capital expenditures. A future tax liability of $109.5 million relating to the acquisition of Kolwezi was derecognized concurrently with the asset impairment.

Sodimico

Sodimico, a RDC state owned mining company, obtained a judgment against Compagnie Miniere De Sakania SPRL ("Comisa") and the Company on March 12, 2010 from the Tribunal de Commerce of Lubumbashi and the Company was notified of the judgment on April 5, 2010. The judgment orders Comisa and the Company to pay to Sodimico $17.3 million for the value of studies made by Sodimico over the perimeters of titles now held by Comisa and a further $40.0 million as additional unknown damages. The court found, based on documents provided by Sodimico, that Comisa acquired the rights over the Lonshi deposits "at the operation stage" and "therefore there is no doubt that it must have used the results of the geological and mining studies made by Sodimico". In fact, Comisa did not use any geological data or studies belonging to Sodimico and there is no factual or legal basis for the judgment. Comisa filed an appeal of the judgment, which is set to be heard November 16, 2010 in Lubumbashi. The Company believes that Sodimico could not enforce payment of the judgment amount against Comisa, and therefore no liability has been recorded as at September 30, 2010.

RDC - Frontier and Lonshi

On March 8, 2010, the Company, and its RDC subsidiaries Comisa and Frontier, and also Bwana, a wrongly named Zambian subsidiary of the Company, were served notices of a case introduced by Sodimico against the RDC before the RDC Supreme Court of Justice ("Supreme Court"). Sodimico requested the cancellation of a February 2000 letter from the Minister of Mines, which Sodimico alleged wrongfully withdrew mining titles belonging to Sodimico. These titles are further alleged to have been subsequently granted to Comisa and Frontier. A hearing was held by the Supreme Court on May 14, 2010 and on May 21, 2010 the Supreme Court delivered a judgment restoring certain mineral rights to Sodimico. These rights conflicted with mineral rights held by Frontier and Comisa. The conclusions of the Supreme Court are impossible to reconcile with the known history of the mineral rights in question.

On August 10, 2010 Frontier received notification from the RDC mining registry ("CAMI") of the withdrawal of its mining and exploration titles based on instructions from the Minister of Mines. On August 24, 2010 Comisa received notification from CAMI of the withdrawal of its mining and (bulk of) exploration titles based on instructions from the Minister of Mines.

On August 27, 2010 the Company announced the suspension of operations at the Frontier mine. This suspension followed the withdrawal of Frontier's exploitation permit by CAMI, and a letter received from Sodimico, which has purportedly been granted Frontier's titles, demanding that Frontier stop all mining and exports and leave the mining title areas. The threats by Sodimico rendered it impossible to continue safe and orderly operations at Frontier. Frontier's operations employed approximately 1500 workers and it was the largest tax payer in the RDC in 2009. The Company no longer has access to either Frontier or Lonshi and therefore has no ability to maintain the facilities or monitor for safety or environmental issues that may arise.

As a result of these actions the Company has determined there to be a complete impairment of the RDC assets of Frontier including product and supplies inventories, mineral properties, plant and equipment. The historical carrying value of these assets, and associated liabilities was $252.8 million in property, plant and equipment, $51.9 million in inventories and $1.2 million of other assets and associated liabilities. The impairment was recorded net of current and future tax recoveries of $62.8 million and includes closure costs of $6.7 million.

On October 1, 2010 the Company, through its subsidiaries International Quantum Resources Limited, Frontier and Comisa commenced international arbitration under the facilities of the International Centre for Settlement of Investment Disputes ("ICSID") in Washington, United States of America against RDC. The arbitration relates to the unjustified withdrawal and reissue of certain mining titles (the "Permits") held by Frontier and Comisa, in violation of the provisions of the RDC Mining Code and applicable laws. First Quantum contests the validity of the RDC's cancellation of the Permits and illegal possession of the Company's investments and assets, seeks their return and is pursuing damages as compensation for the losses the Company has suffered with respect to the RDC's actions.

The Comisa and Frontier ICSID arbitration forms part of First Quantum's overall effort to pursue its legal rights in RDC.

Zambian taxation

The Government of the Republic of Zambia ("GRZ") announced in January 2008 a number of proposed changes to the tax regime in the country in relation to mining companies. These changes included a new windfall tax on copper sales revenue; a new variable profit tax; a concentrate export levy of 15%; an increase in the royalty rate to 3%; an increase in the income tax rate to 30%; and other changes including changes in the timing of deductibility of capital allowances and streaming of hedging losses and gains. These changes were passed by Parliament in March 2008 and the majority of changes took effect from April 1, 2008.

Under the new President, the GRZ reviewed these tax changes and proposed that the new windfall tax be removed, the deductibility of capital allowances be increased back to 100% in the period of expenditure and to allow hedging income be part of mining income for tax purposes. These changes were passed by Parliament in March 2009 and the majority of changes took effect from April 1, 2009. These enacted changes are not retroactive to April 1, 2008. On May 18, 2009 the GRZ issued a temporary exemption of the concentrate export levy of 15% until December 31, 2009 in order to allow the Company to export the copper in concentrate that cannot be treated in Zambia due to the lack of smelter capacity within Zambia.

The Company, through its Zambian subsidiaries, is party to Development Agreements with GRZ for its existing operations which provide an express right to full and fair compensation for any loss, damages or costs (including interest) incurred by the Company by reason of the government's failure to comply with the tax stability guarantees set out in the Development Agreements, and rights of international arbitration in the event of any dispute. Following consultation with external legal counsel, the Company assessed there to be a high probability of recovery from the GRZ of payments made in respect of these taxes.

In the consolidated financial statements, the Company has recognized a tax expense in accordance with applicable laws from time to time notwithstanding the Development Agreements. In addition and reflecting the enforceability of the Development Agreements, the Company has recognized a receivable from the GRZ for an amount in respect of the expected ultimate repayment of taxes in excess of the taxes permitted under the Development Agreements. This receivable has been classified as "loans and receivables" and initially recorded at fair value based on management's best estimate of the timing of receipt and amounts due. As required, the receivable is assessed for impairment at each reporting period based on changes in facts and circumstances; any impairment amounts required may be material. As at September 30, 2010, this receivable amounts to $221.4 million.

Currently, the Company is involved in discussions with the GRZ to find an alternative solution to arbitration or litigation to fully resolve all outstanding matters in relation to the tax changes introduced in conflict with the Development Agreements. While the timing and outcome of these discussions remains uncertain, the Company recognizes that resolving this dispute through arbitration may not be in the best interest of either the Company or the GRZ. Accordingly, while no terms have been agreed to, the Company is seeking to achieve a compromise resolution which respects the key terms of the Development Agreements.

 

OPERATIONAL OUTLOOK

The Company's 2010 production outlook has been lowered to 322,000 tonnes of copper and 195,000 ounces of gold. The lower estimated copper production reflects no further production from Frontier in Q4.

The estimated average C1 cost for 2010 is unchanged at $1.17 per pound

For 2011, the forecast is for 305,000 tonnes of copper and 210,000 ounces of gold. The Company also expects to begin nickel production in 2011 with the commissioning of the Ravensthorpe project planned for the second half of the year.

Kansanshi

Significant focus for Q4 and into 2011 will be given to increasing throughput to the oxide circuit. Key focus areas will be crushing and milling capacity along with leach, CCD and SX capacity. The use of equipment from Bwana Mkubwa will allow fast tracking of this project. In addition, a review is underway to develop a means to treat higher quantities of mixed ore. Optimization of the sulphide circuit to derive the required throughput gains expected from the installation of secondary crushing capacity are ongoing.

Guelb Moghrein

Optimization of the 3.8 million tonne per annum expansion will continue during Q4. Increased throughput and metal recoveries will remain the focus of the overall plant optimization. The blend of mine feed will be enhanced to ensure that the ore quality remains within practical operational limits.

 

Hedging program

As at September 30, 2010, the following derivative positions were outstanding:

Maturity 2010

Maturity 2011

September 30, 2010

December 31, 2009

Asset

Liability

Asset

Liability

Foreign exchange

Foreign exchange contracts

10.9

-

0.7

-

0.9

(0.6)

Interest rate

Floating to fixed interest rate swap

- principal

32.7

26.0

-

(0.3)

-

(0.7)

Average fixed interest rate

1.80%

1.80%

Copper

Futures sales contracts over quotation period (tonnes)(a)

200

-

0.6

-

-

-

Average price ($/tonne)

$7,416

-

Futures sales contracts over quotation period (tonnes)(a)

31,725

-

-

(21.1)

-

-

Average price ($/tonne)

$7,485

-

Gold

Futures sales contracts over quotation period (ounces)(a)

21,898

-

-

(1.3)

-

-

Average price ($/ounce)

$1,249

-

Other

Embedded derivative (note 9c)

-

(4.1)

-

(7.6)

1.3

(26.8)

0.9

(8.9)

Copper embedded derivative (tonnes)(b)

16,024

-

Average price ($/tonne)

$8,054

-

Gold embedded derivative (ounces)(b)

2,377

-

Average price ($/ounce)

$1,308

-

Copper embedded derivative hedged by future sales contracts (tonnes)(a)

10,968

-

a) Copper and gold derivative contracts

Part of the Company's metal production is sold directly to end customers through its metal marketing division. As a consequence of these direct sales, there is an extended period between shipment of metal from the mine site and the timing of recognition of the final sale. In order to reduce the effects of movements in the metal price during this period, the Company enters into futures sales contracts.

b) Provisionally priced copper sales subject to final settlement prices in Q4 2010

At September 30, 2010, 16,024 tonnes of copper sales were provisionally priced at an average of $3.65 per pound ($8,054 per tonne). Of this total, 9,686 tonnes were priced in October and 6,338 tonnes will be priced in November. The average LME cash price for October 2010 was $3.76 per pound ($8,292 per tonne) resulting in a positive provisional adjustment of $2.3 million which will be recognized in Q4 2010.

 

 

On Behalf of the Board of Directors 12g3-2b-82-4461

of First Quantum Minerals Ltd. Listed in Standard and Poor's

G. Clive Newall

President

 

For further information visit our web site at www.first-quantum.com

 

North American contact: Sharon Loung, Director, Investor RelationsTel: (647) 346-3934 Fax: (604) 688-3818 Toll Free: 1 (888) 688-6577 E-Mail: [email protected] United Kingdom contacts: Clive Newall, PresidentTel: +44 140 327 3484 Fax: +44 140 327 3494 E-Mail: [email protected] 

or

Brian Cattell/James Devas, Maitland

Tel: +44 207 379 5151 Fax: +44 20 7379 6161 E-Mail: [email protected] E-Mail [email protected]

 

Certain statements and information herein, including all statements that are not historical facts, contain forward-looking statements and

forward-looking information within the meaning of applicable U.S. and Canadian securities laws. Such forward-looking statements or

information include but are not limited to statements or information with respect to future price of copper or gold, estimation of

mineral reserves and mineral resources, our exploration and development program, estimated future expenses, exploration and

development capital requirements, and our goals and strategies. Often, but not always, forward-looking statements or information can

be identified by the use of words such as "plans", "expects" or "does not expect", "is expected", "budget", "scheduled", "estimates",

"forecasts", "intends", "anticipates" or "does not anticipate" or "believes" or variations of such words and phrases or statements that

certain actions, events or results "may", "could", "would", "might" or "will" be taken, occur or be achieved.

 

With respect to forward-looking statements and information contained herein, we have made numerous assumptions including among other things, assumptions about the price of copper, gold, nickel, PGE, cobalt and sulphuric acid, anticipated costs and expenditures and our ability to achieve our goals. Although our management believes that the assumptions made and the expectations represented by such statements or information are reasonable, there can be no assurance that a forward-looking statement or information herein will prove to be accurate. Forward-looking statements and information by their nature are based on assumptions and involve known and unknown risks, uncertainties and other factors which may cause our actual results, performance or achievements, or industry results, to be materially different from any

future results, performance or achievements expressed or implied by such forward-looking statements or information.

 

See our annual information form and our quarterly and annual management's discussion and analysis for additional information on

risks, uncertainties and other factors relating to the forward-looking statements and information. Although we have attempted to

identify factors that would cause actual actions, events or results to differ materially from those disclosed in the forward-looking

statements or information, there may be other factors that cause actual results, performances, achievements or events not to be

anticipated, estimated or intended. Also, many of the factors are beyond our control. Accordingly, readers should not place undue

reliance on forward-looking statements or information. We undertake no obligation to reissue or update forward-looking statements or

information as a result of new information or events after the date hereof except as may be required by law. All forward-looking

statements and information made herein, are qualified by this cautionary statement.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Consolidated Balance Sheets

 (unaudited)

 (expressed in millions of U.S. dollars, except where indicated)

 

Note

September 30,

2010

December 31,

2009

Assets

Current assets

Cash and cash equivalents

632.8

919.2

Restricted cash

9a

-

40.3

Accounts receivable

307.9

342.6

Inventory

5

408.6

346.7

Current portion of other assets

8

254.9

195.2

1,604.2

1,844.0

Investments

6

654.3

460.4

Property, plant and equipment

7

1,991.7

2,157.9

Other assets

8

68.6

102.3

Total assets

4,318.8

4,564.6

Liabilities

Current liabilities

Accounts payable and accrued liabilities

370.1

323.0

Current taxes payable

316.7

320.8

Current portion of debt

9

182.6

84.5

Current portion of other liabilities

11

24.4

3.9

893.8

 732.2

Debt

9

25.7

107.1

Convertible bonds

10

448.6

438.4

Other liabilities

11

38.8

36.1

Future income tax liabilities

372.1

373.9

Total liabilities

1,779.0

1,687.7

Equity

Capital stock

885.3

750.4

Retained earnings

803.1

1,437.9

Accumulated other comprehensive income

466.2

297.2

Total equity attributable to equity holders of the parent

2,154.6

2,485.5

Non-controlling interests

385.2

391.4

Total equity

2,539.8

2,876.9

Total liabilities and equity

4,318.8

4,564.6

Commitments

16

Contingencies and measurement uncertainty

4, 17

 

 

Approved by the Board of Directors
 
Andrew Adams Peter St. George 
Director Director

 

 

 

 

 

Consolidated Statements of Earnings (Loss)

(unaudited)

(expressed in millions of U.S. dollars, except where indicated)

 

Three months ended

September 30

Nine months ended

September 30

Note

2010

2009

2010

2009

Sales revenues

Copper

550.1

511.3

1,553.9

1,114.9

Gold

52.5

35.0

140.2

102.7

Acid

-

-

-

1.8

602.6

546.3 

1,694.1

1,219.4

Cost of sales

(242.8)

(201.4)

(697.7)

(483.1)

Depletion and amortization

(25.8)

(43.2)

(84.8)

(113.6)

Royalties, windfall taxes and export levies

17b

(24.4)

(16.9)

(64.0)

(36.9)

Operating profit

309.6

284.8

847.6

585.8

Other income (expenses)

Exploration

(12.6)

(4.4)

(31.9)

(15.6)

General and administrative

(13.3)

(8.7)

(26.2)

(20.0)

Net assets impaired and closure costs

4

(306.9)

-

(1,120.0)

-

Acquisition transaction costs

3a

-

-

(18.5)

-

Interest

(15.5)

(19.5)

(44.0)

(42.1)

Derivative instrument adjustments

(22.6)

(40.4)

(14.6)

(139.5)

Other income (expense)

13

(2.0)

10.0

9.6

20.9

(372.9)

(63.0)

(1,245.6)

(196.3)

Earnings (loss) before income taxes

(63.3)

221.8

(398.0)

389.5

Income taxes

(61.1)

(73.2)

(104.3)

(111.7)

Net earnings (loss)

(124.4)

148.6

(502.3)

277.8

Earnings (loss) for the period attributable to:

Non-controlling interests

12.3

24.8

76.4

41.6

Equity holders of the parent

(136.7)

123.8

(578.7)

236.2

Earnings (loss) per common share

Basic

12b

$(1.70)

$1.59

$(7.24)

$3.17

Diluted

12b

$(1.70)

$1.50

$(7.24)

$3.11

Weighted average shares outstanding (000's)

Basic

12b

80,220

78,052

79,976

74,611

Diluted

12b

80,220

87,729

79,976

78,645

Total shares issued and outstanding (000's)

12a

80,669

78,536

80,669

78,536

 

 

The accompanying notes are an integral part of these consolidated financial statements.

For a copy of the notes visit the Company's website at www.first-quantum.com.

 

 

 

Consolidated Statements of Comprehensive Income (Loss)

(unaudited)

(expressed in millions of U.S. dollars, except where indicated)

 

Three months ended

September 30

Nine months ended

September 30

Note

2010

2009

2010

2009

Net earnings (loss)

(124.4)

148.6

(502.3)

277.8

Other comprehensive income (loss)

Unrealized gain on available-for-sale investments, net of tax

208.5

104.1

169.0

244.6

Realized gain on available-for-sale investments,net of tax

-

(7.7)

-

(9.0)

208.5

96.4

169.0

235.6

Comprehensive income (loss)

84.1

245.0

(333.3)

513.4

Total comprehensive income (loss) for the period attributable to:

Non-controlling interests

12.3

24.8

76.4

41.6

Equity holders of the parent

71.8

220.2

(409.7)

471.8

84.1

245.0

(333.3)

513.4

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

The accompanying notes are an integral part of these consolidated financial statements.

For a copy of the notes visit the Company's website at www.first-quantum.com.

Consolidated Statements of Changes in Shareholders' Equity

(unaudited)

(expressed in millions of U.S. dollars, except where indicated)

 

Three months ended

September 30

Nine months ended

September 30

Note

2010

2009

2010

2009

Capital stock

Common shares

Balance - beginning of period

868.4

713.7

724.2

441.8

Acquisition of Kiwara PLC

3b

-

-

137.2

-

Acquisition of logistical expertise

2.3

-

4.4

-

Stock options exercised

0.9

8.8

5.8

11.2

Stock issued on equity financing

-

-

-

269.5

Balance - end of period

871.6

722.5

871.6

 722.5

Equity portion of convertible bonds

Balance - beginning of period

56.9

56.9

56.9

-

Equity allocation of convertible bonds

10

-

-

-

56.9

Balance - end of period

 

56.9

56.9

56.9

56.9

Treasury shares

Balance - beginning of period

(46.4)

(38.8)

(47.2)

(38.8)

Shares purchased

(15.1)

-

(15.1)

-

Restricted and performance stock units vested

3.7

5.0

4.5

5.0

Balance - end of period

 

(57.8)

(33.8)

(57.8)

(33.8)

Contributed surplus

Balance - beginning of period

16.8

20.1

16.5

17.3

Stock-based compensation expense for the period

1.8

1.7

4.7

5.2

Transfers upon exercise of stock options

(0.3)

(2.2)

(2.1)

(2.9)

Restricted and performance stock units vested

(3.7)

(5.0)

(4.5)

(5.0)

Balance - end of period

14.6

14.6

14.6

14.6

Total capital stock

885.3

760.2

885.3

760.2

Retained earnings

Balance - beginning of period

955.0

1,092.7

1,437.9

980.3

Earnings (loss) attributable to equity holders of the parent

(136.7)

123.8

(578.7)

236.2

Acquisition

3c

-

-

(0.4)

-

Dividends

(15.2)

(5.8)

(55.7)

(5.8)

Balance - end of period

803.1

1,210.7

803.1

1,210.7

Accumulated other comprehensive income

Balance - beginning of period

257.7

139.2

297.2

-

Other comprehensive income for the period

208.5

96.4

169.0

235.6

Balance - end of period

466.2

235.6

466.2

235.6

Non-controlling interests

Balance - beginning of period

374.8

330.1

391.4

313.3

Earnings attributable to non-controlling interests

12.3

24.8

76.4

41.6

Dividends

(1.9)

(3.0)

(20.0)

(3.0)

Acquisition

3c

-

-

(62.6)

-

Balance - end of period

385.2

351.9

385.2

351.9

 

The accompanying notes are an integral part of these consolidated financial statements.

For a copy of the notes visit the Company's website at www.first-quantum.com.

Consolidated Statements of Cash Flows

(unaudited)

(expressed in millions of U.S. dollars, except where indicated)

 

Three months ended

September 30

Nine months ended

September 30

 

Note

2010

2009

2010

2009

Cash flows from operating activities

 Net earnings (loss) for the period

(124.4)

148.6

(502.3)

277.8

Items not affecting cash

Depletion and amortization

25.8

43.2

84.8

113.6

Assets impaired, net of tax

4

237.4

-

941.0

-

Adjustment to net realizable value of inventory

-

-

-

(10.7)

Unrealized foreign exchange loss (gain)

9.8

3.9

(4.8)

4.7

Future income tax

12.5

11.3

9.6

(0.7)

Stock‑based compensation expense

1.8

1.7

4.7

5.2

Unrealized derivative instruments loss (gain)

24.9

(43.7)

17.5

11.8

Other

6.0

(0.4)

22.7

6.5

193.8

164.6

573.2

408.2

Change in non‑cash operating working capital

Increase in accounts receivable and other

(86.4)

(101.8)

(28.1)

(222.8)

Decrease (increase) in inventory

(40.6)

23.4

(112.3)

(1.1)

Increase in accounts payable and accrued liabilities

20.8

38.3

30.8

6.1

Increase (decrease) in current taxes payable

(64.2)

72.2

22.5

102.1

Long-term incentive plan contributions

(15.1)

-

(15.1)

-

8.3

196.7

471.0

292.5

Cash flows from financing activities

Proceeds from debt

66.2

-

91.3

139.0

Repayments of debt

(40.3)

(90.3)

(80.7)

(341.8)

Proceeds from convertible bonds

-

-

-

488.0

Proceeds on issuance of common shares

0.6

6.6

3.7

277.8

Restricted cash

40.3

40.3

40.3

40.3

Dividends paid

(15.2)

(5.8)

(55.7)

(5.8)

Dividends paid to non-controlling interests

(1.9)

(3.0)

(20.0)

(3.0)

49.7

(52.2)

(21.1)

594.5

Cash flows from investing activities

Payments for property, plant and equipment

(112.5)

(97.6)

(231.8)

(270.8)

Acquisitions, net of cash acquired

3

-

-

(501.0)

-

Acquisition of logistical expertise

(2.1)

-

(3.7)

-

Disposal of available-for-sale investments, net

0.1

11.5

0.2

15.3

(114.5)

(86.1)

(736.3)

(255.5)

Increase (decrease) in cash and cash equivalents

(56.5)

58.4

(286.4)

631.5

Cash and cash equivalents - beginning of period

689.3

749.3

919.2

176.2

Cash and cash equivalents - end of period

632.8

807.7

632.8

807.7

The accompanying notes are an integral part of these consolidated financial statements.

For a copy of the notes visit the Company's website at www.first-quantum.com

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
QRTEAFFNESPEFAF

Related Shares:

FQM.L
FTSE 100 Latest
Value8,275.66
Change0.00